Permit Information
Permit NumberBLD04-00330
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 3563 S FEDERAL WAY
Project NameFAMILY CENTER-BANK OF AMERICA
Customer Number 
ePlanReviewNo
Description
(Family Center)(Bank of America) * To construct a 4,400 sf one story, Type VB new bank building with an attached 2,325 sq. ft. canopy for the drive-thru per approved plans and attachmnets. PC#099-04 DRH04-00020 CUP03-00112
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  9/27/2013 DONE
Voucher Form  6/20/2005 DONE
Telephone call  6/17/2005 DONE
Spoke with Wendy from Power Plus and asked her for a copy of the contract///6/17/05 9:50am BAS
Third Notice BLD5/20/20055/20/20056/8/2005 DONE
Second Notice has not been responded to.
Second Notice BLD4/26/20054/26/20055/20/2005 DONE
First Notice has not been responded to.
First Notice 11/15/20044/26/2005 DONE
Permanent occupancy  11/15/2004 DONE
Perm. Occ. Cert. # 10357 issued 11-15-04 to Bank of America.
BLD-Final10/20/200410/22/200410/22/2004PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 10/20/2004 at 4:21:24 PM. Contact: ###-####. ok for perm occ 10/22/2004 4:34:32 PM
Code Occupancy Approval10/22/200410/22/200410/22/2004PPASS
DetailsWm. Michael Meloy
Compliance met. 10/22/2004 2:21:29 PM
PubWorks Occupancy Approval10/22/200410/22/200410/22/2004 DONE
Drainage project complete, signed permanent occupancy 10/22/04. D.Erskine
Permanent Occupancy 10/22/200410/22/2004 DONE
Details
FIRE-Final Inspection10/20/200410/21/200410/21/2004PPASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/20/2004 at 4:19:16 PM. Contact: ###-####. Will have address on Federal Way side building for structural 10/21/2004 4:12:24 PM
BLD-Wall cover10/20/200410/21/200410/21/2004APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/20/2004 at 4:20:30 PM. Contact: ###-####. exterior ceilling ok for cover at drive thru. 10/21/2004 10:11:29 AM
BLD-Wall cover10/7/200410/7/200410/7/2004PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/7/2004 at 7:36:26 AM. Contact: ###-####. ceilling ok pending ele. 10/7/2004 2:16:07 PM
BLD-Framing/Rough-in8/30/20048/30/20048/30/2004PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 8/30/2004 at 8:21:28 AM. Contact: ###-####.
BLD-Framing/Rough-in8/13/20048/16/20048/16/2004APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 8/13/2004 at 9:50:50 AM. Contact: ###-####. exterior sheathing atchment ok. 8/16/2004 2:58:59 PM
BLD-Footing7/21/20047/22/20047/22/2004PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/21/2004 at 2:28:09 PM. Contact: ###-####.found. ok pending special insp. appr. 7/22/2004 2:47:30 PM
BLD-Footing7/9/20047/12/20047/12/2004ACANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/9/2004 at 2:04:16 PM. Contact: ###-####.
BLD-Footing7/12/20047/12/20047/12/2004PDONE
DetailsJim Storey
Scheduled by a contractor via Hello! on 7/9/2004 at 2:04:16 PM. Contact: ###-####. pwo i ? si? 7/12/2004 4:44:11 PM
(F) Reprint permit  6/8/2004  
Issue PAID IN FULL permit  6/7/2004 DONE
Telephone call  5/28/2004 DONE
Left message for Donna to remind her that permit is ready & fees///5/28/04 1:55pm BAM
Print Occupancy Form  5/5/2004 DONE
Permit Ready to Issue  5/5/2004 DONE
Telephone call  5/5/2004  
permit ready and fees due 05/05/2004.// 05/13/2004 phone conversation with Bob Mitchell on 05/12/2004 requesting confirmation letter be written and sent to Dr. Vidilakis. Spoke with Teresa Sobotka and she wanted letter be sent to Bob Mitchell since he was the person requesting letter.
Routing - PLAN CHECK5/4/2004 5/4/2004 PASS
Case Summary (BLD)  5/4/2004  
PLANS/APPL TAKEN TO FRONT DESK  5/4/2004 DONE
Plan assigned to (MLO)3/1/2004 5/4/2004 PASS
DetailsMike Otto
5/4/2004 14:38:09 MLO - activity updated through activity BLDA022 from case BLD04-00330.
Routing - Erosion and Sediment5/3/2004 5/3/2004 PASS
Name of RP furnished. ESC approved with conditions attached to plans.
Routing - PLAN CHECK4/22/2004 4/22/2004 NR
Routing - PLUMBING4/21/2004 4/22/2004 PASS
1. yard hydrant on roof needs atmospheric vacuum breaker 2. horizonal roof drain and overflow drain piping needs to be three inch minimum, no two inch
Routing - Erosion and Sediment4/20/2004 4/20/2004 FAIL
Waiting for PD to furnish RP name.
Routing - PLANNING4/14/2004 4/19/2004 PASS
Plans need to be reviewed for DRH compliance (SS). Plans comply with CUP03-112 and CVA03-43 per KG, 4-15-04.

Approved per DRH04-20. SMS
Plan resubmittals received  4/16/2004 DONE
Received five copies of revised sheets C.1, C.2 & C.3. Routed to Mike O. kmm
Plan resubmittals received  4/15/2004 DONE
Received two lighing floor plans with lighting envelope sheets from Karen Gallagher I inserted the sheets into the plan sets.rad
Routing Off Site - STRUCTURAL4/9/2004 4/13/2004 PASS
Contacted PDQ for delivery
Routing - FIRE4/9/2004 4/13/2004 PASS
Resubmittal acceptable.
Routing - PLAN CHECK4/6/2004 4/8/2004 PEND
waiting for other dept. approvals
Plan resubmittals received  4/6/2004 DONE
Received transmittal letter, response letter, and two sets of sheets energy,A00.30,A00.51,A02.01,A09.11,A11.03,E-2 taken to Mike Otto.
Plan resubmittals received  4/5/2004 DONE
Received three copies of revised S02.01 & S02.03. routed to Mike O. kmm
Plan resubmittals received  3/31/2004 FAIL
Received one copy of plan check narrative
2. Door and hardware schedule A00.30. Plans not stamped or signed.
3. Site plan A00.51. Plans not stamped or signed.
4. Floor plan A202.01. Plans not stamped or signed.
5. Exterior Elevation A09.11. Plans not stamped or signed.
6. Interior Elevation All.03. Plans not stamped or signed.
7. Floor plan-lighting E-2. Plan OK for resubmittal
8. Heating and cooling load zone input reports with detailed sytem load report for each system. Reports ok for resubmittal.
9. 2000 IECC envelope compliance cert. 8 x 11. Not incorporated into the plan set.
Contacted Donna Williamson of the above needs.
1. Plans not stamped or signed
2. Envelope compliance cert. not incorporated in to the plan set.
Plan Review Completed(1st rev)  3/30/2004 DONE
Routing - PLAN CHECK3/30/2004 3/30/2004 NR
Routing - FIRE3/26/2004 3/30/2004 FAIL
DetailsBill Alexander
Need fire flows and clarification of addressing the installation of a fire alarm in this submittal package? (Emailed comments to donna-williamson@gensler.com)
Routing Off Site - STRUCTURAL3/1/2004 3/25/2004 FAIL
contacted PDQ for outside engineering. kmm corrections sent to architect
Plan resubmittals requested  3/25/2004 DONE
IBC and structural corrections
Routing - PLAN CHECK3/22/2004 3/25/2004 FAIL
corrections sent to architect
Routing - PLUMBING3/16/2004 3/22/2004 FAIL
civil plans dont match plumbing drawings.
Plan resubmittals received  3/22/2004 DONE
Received two copies of revised sheets L1.0 and L2.0. Routed to Mike O. kmm
Routing - PLANNING3/12/2004 3/16/2004 FAIL
Karen Gallagher cup03-00112 - needs landscape buffer on Federal Wy and wheel restraints or 6' s/w on east side of bldg / Sarah Schafer drh04-00020
Routing - Erosion and Sediment3/10/2004 3/11/2004 FAIL
See ESC activity notes.
Routing - PUBLIC WORKS3/2/2004 3/10/2004 PASS
Routing - PLANNING Land Div3/1/2004 3/1/2004 PASS
Approved as Parcel "F" on ROS 5725 recorded on February 28, 2002.
Plans ACCEPTED BY PLAN TECH  3/1/2004 DONE
Plan routing begun/NEW & ADDTN  3/1/2004 DONE
Application received  2/27/2004  
Recd Pcfee & Taken To Pln CK  2/27/2004 DONE
Fee Review-notes2/27/20042/27/2004