Third Notice BLD | 5/20/2005 | 5/20/2005 | 12/9/2005 | | DONE |
|
|
|
Second Notice has not been responded to.///Over a year old No final values
|
Second Notice BLD | 4/26/2005 | 4/26/2005 | 5/20/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 10/12/2004 | 4/26/2005 | | DONE |
|
|
|
|
Override - Condition Holds | | | 10/12/2004 | | |
|
|
|
|
Permanent occupancy | | | 10/12/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10325 issued 10-12-04 to McAnaney & Associates on 1st floor of Forest River VIII.
|
BLD-Final | 10/8/2004 | 10/8/2004 | 10/8/2004 | P | PASS |
Dave Hannah
|
|
|
This is the one we talke about on Friday afternoon. Cathy W. ok for perm occ 10/8/2004 3:12:52 PM
|
Permanent Occupancy | | 10/8/2004 | 10/8/2004 | | DONE |
|
|
|
|
Override - Condition Holds | | | 10/8/2004 | | |
|
|
|
|
BLD-Aging Inspection | 8/2/2004 | 8/2/2004 | 8/2/2004 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 8/2/2004 | 8/2/2004 | 8/2/2004 | | PASS |
Dave Hannah
|
|
|
|
Telephone call | | | 7/20/2004 | | DONE |
|
|
|
Talked w/contr. re: status of temp. occ. - structural is only item left for perm. occ.
|
Temporary occupancy | | | 6/3/2004 | | DONE |
|
|
|
Temp. Occ. Cert. # 5116 issued 6-3-04 to McAnaney & Associates.
|
BLD-Final | 6/1/2004 | 6/2/2004 | 6/2/2004 | P | PART |
Dave Hannah
|
|
|
Don, ###-#### ok for temp occ needs ada stall and exiting issue or upgrade agreement and door hard ware common areas 6/2/2004 3:43:33 PM
|
Override - Condition Holds | | | 6/1/2004 | | |
|
|
|
|
FIRE-Final Inspection | 5/28/2004 | 5/28/2004 | 5/28/2004 | P | PASS |
Rick Jackson
|
|
|
Don, ###-####
|
Plan resubmittals received | | | 5/14/2004 | | DONE |
|
|
|
Received Transmittal Letter, 3 Sets A1.0 , S1.0 , 1 Set of Calcs.. Taken to Jason Blais ...
|
BLD-Framing/Rough-in | 5/3/2004 | 5/4/2004 | 5/4/2004 | P | PART |
Dave Hannah
|
|
|
Don, ###-#### ok to cover int walls after elec r/i 5/4/2004 1:56:11 PM
|
Override - Condition Holds | | | 5/3/2004 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/3/2004 | | DONE |
|
|
|
|
Override - Condition Holds | | | 5/3/2004 | | |
|
|
|
|
Routing - PLAN CHECK | 4/14/2004 | | 4/30/2004 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
Plan assigned to (JCB) | 3/4/2004 | | 4/30/2004 | | PASS |
Jason Blais
|
|
|
4/30/2004 09:42:15 JCB - activity updated through activity BLDA022 from case BLD04-00364.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/30/2004 | | PASS |
|
|
|
|
OVERRIDE | | | 4/30/2004 | | |
|
|
|
|
Override - Condition Holds | | | 4/30/2004 | | |
|
|
|
|
Permit Ready to Issue | | | 4/30/2004 | | |
|
|
|
|
Override - Condition Holds | | | 4/30/2004 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/30/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/30/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/30/2004 | | DONE |
|
|
|
|
Telephone call | | | 4/30/2004 | | DONE |
|
|
|
left mess that permit is ready
|
Plan resubmittals received | | | 4/28/2004 | | DONE |
|
|
|
Received Letter and Memo Transmittal 2 Sets 6 sheets A1.0,A4.0,EN1.0 Routed to Jason Blais..
|
Meeting | | | 4/28/2004 | | |
|
|
|
A meeting concerning the exiting issue in this building was discussed and options presented by all. Present in the meeting were Wayne Gibbs, Marlene Southard, Jason Blais, Clinton Yaka, Jeff Likes, Marv Meyer, Don Bryant, and Amy Wray. It was decided to release the permit for this tenant but to not approve a permanent Certificate of Occupancy until an acceptable solution for the exiting issue on the first floor has been addressed.
|
Routing - PLAN CHECK | 3/17/2004 | | 4/14/2004 | | FAIL |
|
|
|
Called architect rep. concerning exit passageway issues and format of upgrade letter. New plan sheets will need to be provided and another upgrade letter.
|
Plan resubmittals received | | | 4/14/2004 | | DONE |
|
|
|
Received letter of transmittal, response letter, letter form RMH with two sets of sheets A1.0,A4.0,A5.0,EN1.0, taken to Jason B.
|
Plan Reviewer's activity | | | 4/14/2004 | | |
|
|
|
Called architect rep. concerning exit passageway issues and upgrade letter format. New plan sheets and another upgrade letter will need to be provided.
|
Routing - FIRE | 3/15/2004 | | 3/17/2004 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 3/15/2004 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 3/5/2004 | | 3/15/2004 | | FAIL |
|
|
|
Plan review sent and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Fire Dept. for review.
|
Routing - PUBLIC WORKS | 3/4/2004 | | 3/5/2004 | | PASS |
|
|
|
|
Application received | | | 3/3/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/3/2004 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/3/2004 | | DONE |
|
|
|
|
Fee Review-notes | 3/3/2004 | 3/3/2004 | | | |
|
|
|
|