VOIDED CHANGE STATUS | | | 6/27/2005 | | DONE |
|
|
|
Per Mike Miller he is not building this building so he will follow up with a letter for a refund.
|
BLD-Aging Inspection | 5/16/2005 | 5/16/2005 | 5/16/2005 | | PASS |
Jim Storey
|
|
|
wip slow
|
BLD-Aging Inspection | 12/2/2004 | 12/2/2004 | 12/2/2004 | | PASS |
Jim Storey
|
|
|
site work. 12/2/2004 8:34:51 AM
|
(F) Reprint permit | | | 9/3/2004 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/2/2004 | | DONE |
|
|
|
|
Telephone call | | | 7/14/2004 | | DONE |
|
|
|
left mess for m r miller that permit is ready & need a.c.h.d.
|
Routing - PLAN CHECK | 5/12/2004 | | 6/8/2004 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/8/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/8/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/8/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/8/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/8/2004 | | DONE |
|
|
|
|
Telephone call | | | 6/8/2004 | | DONE |
|
|
|
left mess with m r miller at ###-#### that permit is ready
|
Plan assigned to (JCM) | 3/4/2004 | | 6/8/2004 | | DONE |
John Menard
|
|
|
6/8/2004 08:28:53 JCM - activity updated through activity BLDA022 from case BLD04-00369.
|
Routing Off Site - STRUCTURAL | 6/3/2004 | | 6/7/2004 | | PASS |
|
|
|
Contacted PDQ for pickup to outside engineering. Received fax from the consulting structural engineer approving the resubmittals. JCM
|
Plan resubmittals received | | | 6/2/2004 | | DONE |
|
|
|
Received Transmittal Letter, 2 Foundation Design booklets,3 sheets of the Mezzanine framing plan, 2 Sets A-1 & A-2 Taken to John Menard...
|
Plan Reviewer's activity | | | 6/2/2004 | | PASS |
|
|
|
Reviewed and approved resubmitted revised plans with attached comment list and redlined notes. JCM
|
Routing - FIRE | 5/7/2004 | | 5/12/2004 | | PASS |
|
|
|
resubmittal acceptable
|
Routing - PLAN CHECK | 4/30/2004 | | 5/7/2004 | | |
|
|
|
|
Plan resubmittals received | | | 5/6/2004 | | DONE |
|
|
|
Received letter of transmittal, response letter and United Water comments. All taken to John M.
|
Routing Off Site - STRUCTURAL | 4/19/2004 | | 4/30/2004 | | FAIL |
|
|
|
Contacted PDQ to take plans to outside engineering. kmm Received a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Plan Review Completed(1st rev) | | | 4/29/2004 | | FAIL |
|
|
|
Failed Building & Fire
|
Routing - FIRE | 4/26/2004 | | 4/29/2004 | | FAIL |
|
|
|
fire flow, storage details required. Review comments faxed to architect.
|
Routing - PLAN CHECK | 3/29/2004 | | 4/26/2004 | | FAIL |
|
|
|
Plans on hold waiting for pre-engineered structural plans to be submitted. Received plans 4/19/04. JCM Waiting for response from consulting structural engineer before mailing my comment list. JCM
|
Plan resubmittals received | | | 4/19/2004 | | DONE |
|
|
|
Received two copies of revised calcs. Put one with outside engingeering and one with John M. Received four copies of revised sheets P-1, P-2, A-1, S1of 3, S2 of 3 and S3 of 3. Put one copy with outside engineering and routed the remainder to John M. kmm
|
Routing - PLUMBING | 3/18/2004 | | 3/28/2004 | | PASS |
|
|
|
provide water heater pan, pipe t&p drain to outside or approved location, vent pump chamber, r.p. required on branch line serving hydrants in shop.
|
Routing - PLANNING | 3/12/2004 | | 3/18/2004 | | PASS |
|
|
|
Approved per DRH02-00202.
|
Routing - PUBLIC WORKS | 3/5/2004 | | 3/11/2004 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 3/11/2004 | | 3/11/2004 | | PASS |
|
|
|
ESC approved with conditons attached to plans.
|
Plans ACCEPTED BY PLAN TECH | | | 3/4/2004 | | FAIL |
|
|
|
Struct. and Arch. sheets reflect the 97 UBC. Contacted Kyle Freutel of this need. Will still route plans Per John M. However will wait for the correct code year before sending out to engineering. kmm
Contacted Jane Miller for update. They are working on it. 3.30/04 kmm
|
Routing - PLANNING Land Div | 3/4/2004 | | 3/4/2004 | | PASS |
|
|
|
Parcel 21 on ROS 2436.
|
Plan routing begun/NEW & ADDTN | | | 3/4/2004 | | DONE |
|
|
|
|
Application received | | | 3/4/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/4/2004 | | |
|
|
|
|
Fee Review-notes | 3/4/2004 | 3/4/2004 | | | |
|
|
|
|