BLD-Final | 11/17/2004 | 11/18/2004 | 11/18/2004 | A | PASS |
Dave Hannah
|
|
|
dwayne - cell ###-#### Note: call him if needed Please also notify when finished inspection ; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
DOC - Permit Finaled | 11/18/2004 | 11/18/2004 | 11/18/2004 | A | PASS |
Dave Hannah
|
|
|
Finaled by inspector at 11/18/2004 9:58:37 AM
|
BLD-Conference | 10/20/2004 | 10/21/2004 | 10/21/2004 | A | PASS |
Tony Young
|
|
|
Meet w/ Dwayne @ 11am,,, call ###-#### to verify,,, also address is south 13th
met to "get on the same page" and see approved plans,,, they will fix and re-call 10/21/2004 11:27:31 AM
|
BLD-Conference | 10/21/2004 | 10/21/2004 | 10/21/2004 | A | DONE |
Dave Hannah
|
|
|
Meet w/ Dwayne @ 11am,,, call ###-#### to verify,,, also address is south 13th
|
BLD-Final | 10/19/2004 | 10/20/2004 | 10/20/2004 | A | FAIL |
Tony Young
|
|
|
509 s 13th st corner of grand and 13th please call if you need Dewayne there he is in caldwell so need a little time to get there. ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
fail,,, need guard rails, rises, treads, etc to meet code, also add hand rail on upper portion,,, etc, call to meet out on job next time 10/20/2004 11:42:30 AM
|
BLD-Footing | 9/15/2004 | 9/16/2004 | 9/16/2004 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/15/2004 at 8:11:16 AM. Contact: ###-####.
|
BLD-Footing | 9/16/2004 | 9/16/2004 | 9/16/2004 | P | PASS |
Troy James
|
|
|
call ###-####
|
Issue PAID IN FULL permit | | | 8/19/2004 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 3/23/2004 | 3/23/2004 | 8/3/2004 | | PASS |
Mike Phillips
|
|
|
8/3/2004 09:34:45 M_P - activity updated through activity BLDA022 from case BLD04-00523.
|
Routing - PLAN CHECK | 4/7/2004 | | 8/3/2004 | | |
|
|
|
New plans were submitted on 7/15/04 designed by an architect.
|
Routing - PLAN CHECK | 7/20/2004 | | 8/3/2004 | | PASS |
|
|
|
Mike Phillips
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/3/2004 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/3/2004 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/3/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/3/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/3/2004 | | DONE |
|
|
|
|
Telephone call | | | 8/3/2004 | | DONE |
|
|
|
spoke with Pro West -- permit is ready.
|
Routing - PLANNING | 7/16/2004 | | 7/20/2004 | | PASS |
|
|
|
Approved.
|
Routing - Erosion and Sediment | 7/20/2004 | | 7/20/2004 | | PASS |
|
|
|
per Steve Webb Jim already approved.
|
Plan resubmittals received | | | 7/15/2004 | | DONE |
|
|
|
Received Transmittal Letter, 1Revised Tenant Improvement Application , 3 Revised Drawings of A0.0, A1.0, A1.1, A2.0 Taken to Mike Phillips
|
Plan Review Completed(1st rev) | | | 4/7/2004 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 3/31/2004 | | 4/7/2004 | | FAIL |
|
|
|
Plan review completed, sent correction report to applicant and designer requesting additional information be submitted for further review prior to issuing permit.
|
Routing - Erosion and Sediment | 3/26/2004 | | 3/31/2004 | | PASS |
|
|
|
|
Routing - PLANNING | 3/23/2004 | | 3/25/2004 | | PASS |
|
|
|
Approved per CZC04-00178.
|
Plans ACCEPTED BY PLAN TECH | | | 3/23/2004 | | DONE |
|
|
|
|
Plan routing begun/TENANTS | | | 3/23/2004 | | DONE |
|
|
|
|
Application received | | | 3/22/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/22/2004 | | |
|
|
|
|
Fee Review-notes | 3/22/2004 | 3/22/2004 | | | |
|
|
|
|