FIRE-Final Inspection | 10/7/2004 | 10/7/2004 | 10/7/2004 | P | PASS |
Rick Jackson
|
|
|
ivan; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Letter of compliance | | | 10/7/2004 | | DONE |
|
|
|
Letter of Compliance issued 10-7-04.
|
BLD-Final | 9/23/2004 | 9/24/2004 | 9/24/2004 | A | PASS |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 9/23/2004 at 10:25:27 AM. Contact: ###-####.
structural final ok
Fire/Life safety final OK per Troy Cobbley
OkK to issue CofO 9/24/2004 9:24:55 AM
|
Code Occupancy Approval | 9/24/2004 | 9/24/2004 | 9/24/2004 | A | PASS |
Wm. Michael Meloy
|
|
|
Compliance met. 9/24/2004 8:57:45 AM
|
FIRE-Final Inspection | 9/23/2004 | 9/23/2004 | 9/23/2004 | P | FAIL |
Troy Cobbley
|
|
|
Remove the deadbolts on all three doors and provide fire extinguishers tagged and mounted in the maintenance room 9/23/2004 1:00:42 PM
|
BLD-Framing/Rough-in | 7/6/2004 | 7/7/2004 | 7/7/2004 | A | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 7/6/2004 at 4:19:43 PM. Contact: ###-####.
|
BLD-Foundation | 5/17/2004 | 5/18/2004 | 5/18/2004 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/17/2004 at 2:02:14 PM. Contact: ###-####.
|
BLD-Footing | 5/17/2004 | 5/17/2004 | 5/17/2004 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/17/2004 at 8:18:55 AM. Contact: ###-####.
|
(F) Reprint permit | | | 4/26/2004 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/23/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/21/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/21/2004 | | DONE |
|
|
|
|
Telephone call | | | 4/21/2004 | | DONE |
|
|
|
permit ready and fee due
|
Routing - PLAN CHECK | 4/19/2004 | | 4/20/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 4/20/2004 | | DONE |
|
|
|
Recieved two copies of revised sheet A0.1. Routed to John M. kmm
|
Plan Reviewer's activity | | | 4/20/2004 | | PASS |
|
|
|
Reviewed and approved resubmittals with redlined corrections. JCM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/20/2004 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 3/25/2004 | | 4/20/2004 | | PASS |
John Menard
|
|
|
4/20/2004 15:40:29 JCM - activity updated through activity BLDA022 from case BLD04-00539.
|
Routing - FIRE | 4/15/2004 | | 4/19/2004 | | PASS |
|
|
|
approved - no written review comments necessary.
|
Plan Review Completed(1st rev) | | | 4/19/2004 | | FAIL |
|
|
|
Failed Building
|
Plan resubmittals requested | | | 4/15/2004 | | |
|
|
|
Faxed the architect a copy of the comment list requesting revisions. JCM
|
Routing - PLAN CHECK | 4/15/2004 | | 4/15/2004 | | FAIL |
|
|
|
|
Routing - PLUMBING | 4/12/2004 | | 4/14/2004 | | PASS |
|
|
|
per plans and 2000 upc
|
Routing - PLANNING | 4/8/2004 | | 4/9/2004 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 3/26/2004 | | 4/8/2004 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 3/25/2004 | | 3/26/2004 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 3/25/2004 | | 3/25/2004 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/25/2004 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 3/25/2004 | | DONE |
|
|
|
|
Application received | | | 3/24/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/24/2004 | | |
|
|
|
|
Fee Review-notes | 3/24/2004 | 3/24/2004 | | | |
|
|
|
|