(HEALTHWISE - 1ST & 2ND FLRS) This building is fire sprinklered to substitute for 1-hr fire-resistance-rated construction. To remodel a 372 square foot area on the 1st floor and a 284 square foot area on the 2nd floor of an existing office building. Both areas will be used for offices. There is no change in the occupant load, the occupancy classification, or the tenant. Work is to include interior nonbearing walls, interior doors, and finishes all per the approved drawings and the plan review report on file. The location of fire sprinkler heads shall comply with NFPA 13 2002 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  6/7/2004 DONE
Letter of Compliance issured 6-7-04.
BLD-Final6/3/20046/4/20046/4/2004PPASS
DetailsTony Young
robert; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
perm c of o ok,,, Cathy, please doc. final 4 me :),, thanks, 415 6/4/2004 2:17:58 PM
FIRE-Final Inspection6/1/20046/2/20046/2/2004PPASS
DetailsRick Jackson
robert; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Framing/Rough-in5/17/20045/18/20045/18/2004APASS
DetailsTony Young
Robert; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes
BLD-Framing/Rough-in5/18/20045/18/20045/18/2004PDONE
DetailsTony Young
BLD-Conference5/12/20045/13/20045/13/2004APART
DetailsTony Young
robert; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
on project,, general ?s 5/13/2004 1:16:33 PM
Issue PAID IN FULL permit  5/4/2004 DONE
Plan assigned to (CJW)4/21/2004 5/3/2004 PASS
DetailsCarl Westfall
5/3/2004 11:23:16 CJW - activity updated through activity BLDA022 from case BLD04-00741.
Routing - PLAN CHECK4/30/2004 5/3/2004 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/3/2004 DONE
Permit Ready to Issue  5/3/2004 DONE
Inspection Record Card- Bld  5/3/2004 DONE
Telephone call  5/3/2004 DONE
Spoke with Robin and told her that permit is ready & fees///5/3/04 1:33pm BAM
Routing - FIRE4/27/2004 4/30/2004 PASS
Routing - PLAN CHECK4/22/2004 4/27/2004 PASS
IBC plan review was started April 26, 2004 and was finished the next day. The drawings were approved with clarifications. See the plan review report. A copy was E-mailed to the architect.
Routing - PUBLIC WORKS4/21/2004 4/22/2004 PASS
Plans ACCEPTED BY PLAN TECH  4/16/2004 DONE
Per Rita
Application received  4/13/2004  
Recd Pcfee & Taken To Pln CK  4/13/2004 DONE
Fee Review-notes4/13/20044/13/2004