BLD-Final | 8/15/2004 | 8/16/2004 | 8/16/2004 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/15/2004 at 6:35:42 PM. Contact: ###-####.
letter of compliance issued 8/16/2004 12:45:10 PM
|
DOC - Permit Finaled | 8/16/2004 | 8/16/2004 | 8/16/2004 | P | PASS |
Tony Young
|
|
|
Finaled by inspector at 8/16/2004 12:44:42 PM
|
BLD-Aging Inspection | 8/2/2004 | 8/2/2004 | 8/2/2004 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 8/2/2004 | 8/2/2004 | 8/2/2004 | | PASS |
Tony Young
|
|
|
|
MISC ACTIONS | | | 6/16/2004 | | DONE |
|
|
|
JV
|
Print Occupancy Form | | | 6/2/2004 | | DONE |
|
|
|
|
BLD-Footing | 6/1/2004 | 6/1/2004 | 6/1/2004 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 6/1/2004 at 11:18:22 AM. Contact: ###-####. contracter on site he is digging holes for column pads rebar and bolts ready ok to pour 6/1/2004 3:13:16 PM
|
Issue & PRINT to be Invoiced | | | 5/11/2004 | | DONE |
|
|
|
|
PubWorks Occupancy Approval | 5/7/2004 | 5/7/2004 | 5/7/2004 | | DONE |
|
|
|
No inspections required per B.Murphy, 5/07/04
|
Plan assigned to (JCM) | 4/16/2004 | | 5/7/2004 | | PASS |
John Menard
|
|
|
5/7/2004 10:41:54 JCM - activity updated through activity BLDA022 from case BLD04-00744.
|
Routing - PLAN CHECK | 5/7/2004 | | 5/7/2004 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/7/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/7/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/7/2004 | | DONE |
|
|
|
|
Telephone call | | | 5/7/2004 | | DONE |
|
|
|
permit ready and fees due
|
Routing - PUBLIC WORKS | 5/5/2004 | | 5/6/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 5/6/2004 | | DONE |
|
|
|
Received two structural calcs, two copies of sheets 3C,6C taken to John M.
|
Routing - FIRE | 4/30/2004 | | 5/5/2004 | | PASS |
|
|
|
Approved - no written comments necessary.
|
Plan Review Completed(1st rev) | | | 5/5/2004 | | FAIL |
|
|
|
Failed Public Works and Building
|
Plan resubmittals requested | | | 4/30/2004 | | |
|
|
|
E-mailed the applicant a copy of the plan review comments requesting revisions. JCM
|
Routing - PLAN CHECK | 4/27/2004 | | 4/30/2004 | | FAIL |
|
|
|
|
Routing - PLANNING | 4/21/2004 | | 4/27/2004 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 4/20/2004 | | 4/21/2004 | | PASS |
|
|
|
ESC approved with attached conditions.
|
Routing - PUBLIC WORKS | 4/16/2004 | | 4/20/2004 | | FAIL |
|
|
|
Failed as Brian Murphy requires a Drainage Plan
|
Plans ACCEPTED BY PLAN TECH | | | 4/16/2004 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 4/16/2004 | | 4/16/2004 | | PASS |
|
|
|
Site is over 5 acres in size.
|
Plan routing begun/NEW & ADDTN | | | 4/16/2004 | | DONE |
|
|
|
|
Application received | | | 4/13/2004 | | |
|
|
|
|
Fee Review-notes | 4/13/2004 | 4/13/2004 | | | |
|
|
|
|