| Third Notice BLD | 9/22/2008 | 9/22/2008 | 3/10/2009 | | DONE |
Patricia Smith
|
|
|
Second Notice has not been responded to.
|
| Second Notice BLD | 8/11/2008 | 8/11/2008 | 9/22/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
| First Notice | 4/15/2008 | 4/15/2008 | 8/11/2008 | | DONE |
Tom Arcoraci
|
|
|
|
| DOC - Permit Finaled | 4/15/2008 | 4/15/2008 | 4/15/2008 | P | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 2/18/2008 | 2/18/2008 | 2/19/2008 | | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 12/19/2007 | 12/19/2007 | 12/19/2007 | | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 10/19/2007 | 10/19/2007 | 10/19/2007 | | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 8/17/2007 | 8/17/2007 | 8/17/2007 | | CANC |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 6/11/2007 | 6/11/2007 | 6/18/2007 | | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 4/9/2007 | 4/9/2007 | 4/9/2007 | | CANC |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 1/16/2007 | 1/16/2007 | 1/16/2007 | | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 11/13/2006 | 11/13/2006 | 11/13/2006 | | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 9/13/2006 | 9/13/2006 | 9/13/2006 | | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 7/10/2006 | 7/10/2006 | 7/10/2006 | | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 3/9/2006 | 3/9/2006 | 3/9/2006 | | NR |
Tom Arcoraci
|
|
|
|
| BLD-Other | 1/3/2006 | 1/3/2006 | 1/3/2006 | P | CANC |
Tom Arcoraci
|
|
|
tony
|
| BLD-Aging Inspection | 12/20/2005 | 12/20/2005 | 12/20/2005 | | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 10/18/2005 | 10/18/2005 | 10/18/2005 | | NR |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 8/16/2005 | 8/16/2005 | 8/16/2005 | | PASS |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 6/15/2005 | 6/15/2005 | 6/15/2005 | | NR |
Tom Arcoraci
|
|
|
|
| BLD-Aging Inspection | 12/28/2004 | 12/28/2004 | 12/28/2004 | | PASS |
Tom Arcoraci
|
|
|
wip ok 12/28/2004 8:59:54 AM
|
| Issue & PRINT permit | | | 9/28/2004 | | DONE |
|
|
|
|
| Permit Ready to Issue | | | 9/24/2004 | | DONE |
|
|
|
|
| Inspection Record Card- Bld | | | 9/24/2004 | | DONE |
|
|
|
|
| Telephone call | | | 9/24/2004 | | DONE |
|
|
|
Left message for Jeff Cramer that permit is ready & fees///9/24/04 2:00pm BAS
|
| Plan resubmittals received | | | 9/23/2004 | | DONE |
|
|
|
Received faxed response letter and supplimental calculations from the project structural engineer. JCM
|
| Routing Off Site - STRUCTURAL | 9/23/2004 | | 9/23/2004 | | |
|
|
|
Faxed the consulting structural engineer a copy of the response letter and calcuation sheet. JCM Received an e-mail response from the consulting structural engineer approving the resubmitted structural information. JCM
|
| PLANS/APPL TAKEN TO FRONT DESK | | | 9/23/2004 | | DONE |
|
|
|
|
| Plan assigned to (JCM) | 4/22/2004 | | 9/23/2004 | | PASS |
John Menard
|
|
|
9/23/2004 10:57:56 JCM - activity updated through activity BLDA022 from case BLD04-00814.
|
| Routing - PLAN CHECK | 7/28/2004 | | 9/23/2004 | | PASS |
|
|
|
|
| Plan resubmittals received | | | 9/21/2004 | | DONE |
|
|
|
Received transmittal letter, with 3 response letters from Schnable foundations co. Taken to John M.
|
| Plan resubmittals requested | | | 9/16/2004 | | DONE |
|
|
|
Faxed the architect a copy of the consulting structural engineers comment, requesting revisions. JCM
|
| Plan resubmittals received | | | 9/8/2004 | | DONE |
|
|
|
Received 1 Set of DWG # 1,2,3,4,5,6,7 Take to John Menard
|
| Plan resubmittals received | | | 9/8/2004 | | DONE |
|
|
|
Received 2 Design Calculation Booklets... Taken to John Menard....
|
| Plan resubmittals received | | | 9/8/2004 | | DONE |
|
|
|
Received 2 Sets of DWG. # 1,2,3,4,5,6,7, Taken to John Menard....
|
| Plan Review Completed(1st rev) | | | 7/28/2004 | | FAIL |
|
|
|
failed Planning and Plan Check
|
| Routing - FIRE | 7/23/2004 | | 7/28/2004 | | PASS |
|
|
|
approved with conditions, review faxed to arhchitect for his attention.
|
| Routing - PLANNING | 7/22/2004 | | 7/23/2004 | | PASS |
|
|
|
I talked to Mike Churella at ACHD and he is comfortable with the progress of the vacation of Curtisian at ACHD to allow the grading and drainage permit to be let. Will need vacation of right-of-way finalized prior to building the structure. CUP03-36, KG
|
| Routing - PLAN CHECK | 5/20/2004 | | 7/22/2004 | | PEND |
|
|
|
This project is on hold waiting for shoring plans and calculations to be submitted by the contractor. JCM
|
| Routing - PLUMBING | 5/18/2004 | | 5/19/2004 | | PASS |
|
|
|
|
| Routing - PLANNING | 5/5/2004 | | 5/11/2004 | | FAIL |
|
|
|
Karen Gallagher CUP03-00036: Need documentation that Curtisian right-of-way vacation has been completed.
Design Review application approved per DRH04-00055 (Marty Santoyo).
|
| Routing - Erosion and Sediment | 5/3/2004 | | 5/5/2004 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
| Routing - PUBLIC WORKS | 4/26/2004 | | 5/3/2004 | | PASS |
|
|
|
|
| Routing - PLANNING Land Div | 4/22/2004 | | 4/26/2004 | | PASS |
|
|
|
Approved for this work only. Must complete Record of Survey process before building permit issued for new structures.
|
| Plans ACCEPTED BY PLAN TECH | | | 4/22/2004 | | PEND |
|
|
|
Requires
1. Struct. calcs.
2. One extra civil set.
|
| Plan routing begun/NEW & ADDTN | | | 4/22/2004 | | DONE |
|
|
|
|
| Recd Pcfee & Taken To Pln CK | | | 4/21/2004 | | DONE |
|
|
|
|
| Application received | | | 4/20/2004 | | |
|
|
|
|
| PubWorks Occupancy Approval | 1/28/2008 | 1/28/2008 | | | DONE |
|
|
|
Project is complete. Final inspection 01/23/08 R. Anderson
|
| Fee Review-notes | 4/21/2004 | 4/21/2004 | | | |
|
|
|
|
| Routing Off Site - STRUCTURAL | 9/8/2004 | | | | FAIL |
|
|
|
Called PDQ for pick up... Received comment from consulting structural engineer requesting revisions. JCM
|