Second Notice BLD | 10/13/2005 | 10/13/2005 | 10/26/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
Telephone call | | | 10/20/2005 | | DONE |
|
|
|
Faxed to KJ a cert of value to complete on this project///10/20/05 BAS
|
First Notice | | 7/13/2005 | 10/13/2005 | | DONE |
|
|
|
|
First Notice | | 5/25/2005 | 7/13/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 5/25/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10598 issued 5-25-05 to Insight Architects ofc. bldg.
|
BLD-Final | 5/17/2005 | 5/17/2005 | 5/17/2005 | | PASS |
|
|
|
Final per Jim Storey, ok for perm. occ.
|
Permanent Occupancy | | 5/17/2005 | 5/17/2005 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 4/20/2005 | | PASS |
|
|
|
Revised Site Plan provided and Landscaping complies with same.
|
Temporary occupancy | | | 11/9/2004 | | DONE |
|
|
|
Temp. Occ. Cert. # 5165 issued 11-9-04 to Insight Architect Office.
|
BLD-Final | 11/4/2004 | 11/5/2004 | 11/5/2004 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/4/2004 at 9:06:36 AM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Nov 5 2004 3:51AM.
|
BLD-Final | 11/5/2004 | 11/5/2004 | 11/5/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/5/2004 at 3:52:18 AM. Contact: ###-####. temp ok 11/5/2004 4:04:11 PM
|
FIRE-Conference | 11/5/2004 | 11/5/2004 | 11/5/2004 | A | PASS |
Rick Jackson
|
|
|
Russ Phillips (architect) provided site plans with Dave Millers approval to install fire sprinklers instead of installing the new hydrant as shown on plans 11/5/2004 10:34:20 AM
|
Code Occupancy Approval Temp | 11/5/2004 | 11/5/2004 | 11/5/2004 | P | DONE |
Wm. Michael Meloy
|
|
|
Approved Temp Occupancy with bonding with City 11/5/2004 3:13:44 PM
|
FIRE-Final Inspection | 11/4/2004 | 11/5/2004 | 11/5/2004 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 11/4/2004 at 9:05:00 AM. Contact: ###-####.
|
BLD-Conference | 10/26/2004 | 10/26/2004 | 10/26/2004 | P | PASS |
Jim Storey
|
|
|
Jack; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner wip 10/26/2004 1:34:02 PM
|
BLD-Energy code compliance | 10/13/2004 | 10/14/2004 | 10/14/2004 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/13/2004 at 3:39:03 PM. Contact: ###-####.
|
BLD-Energy code compliance | 10/8/2004 | 10/11/2004 | 10/11/2004 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/8/2004 at 3:34:18 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 10/7/2004 | 10/8/2004 | 10/8/2004 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 10/7/2004 at 3:39:30 PM. Contact: ###-####.
ok to cover pending Fire, and Mech. 10/8/2004 2:08:01 PM
|
BLD-Wall cover | 10/4/2004 | 10/4/2004 | 10/4/2004 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/4/2004 at 9:24:52 AM. Contact: ###-####. exterior sheer ok and interior sheer ok pending hds. 10/4/2004 2:50:15 PM
|
BLD-Framing/Rough-in | 9/23/2004 | 9/24/2004 | 9/24/2004 | A | PART |
Jim Storey
|
|
|
pat Note: sheer nailing inspection; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles roof deck ok for nailling/ 9/24/2004 9:06:02 AM
|
BLD-Concrete | 8/17/2004 | 8/18/2004 | 8/18/2004 | A | PART |
Jim Storey
|
|
|
JACK; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles placed with si 8/18/2004 8:04:44 AM
|
Routing - FIRE | 6/10/2004 | | 8/15/2004 | | PASS |
|
|
|
resubmittal acceptable.
|
BLD-Foundation | 7/19/2004 | 7/20/2004 | 7/20/2004 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/19/2004 at 3:03:09 PM. Contact: ###-####. foudation ok 7/20/2004 10:08:40 AM
|
BLD-Footing | 7/15/2004 | 7/16/2004 | 7/16/2004 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 7/15/2004 at 2:51:55 PM. Contact: ###-####. ft ok 7/16/2004 9:26:35 AM
|
(F) Reprint permit | | | 7/6/2004 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/2/2004 | | |
|
|
|
|
Permit Ready to Issue | | | 6/21/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/21/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/21/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/16/2004 | | 6/18/2004 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2004 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/18/2004 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/18/2004 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 4/28/2004 | | 6/18/2004 | | PASS |
Mike Phillips
|
|
|
6/18/2004 09:23:08 M_P - activity updated through activity BLDA022 from case BLD04-00866.
|
Routing - PUBLIC WORKS | 6/7/2004 | | 6/9/2004 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 6/7/2004 | | 6/7/2004 | | PASS |
|
|
|
ESC already approved on 5/10/04.
|
Routing Off Site - STRUCTURAL | 6/1/2004 | | 6/7/2004 | | DONE |
|
|
|
|
Routing - PLANNING | 6/3/2004 | | 6/4/2004 | | PASS |
|
|
|
Approved per DRH03-235. Joint access agreement in DR file.
|
Plan resubmittals received | | | 6/4/2004 | | DONE |
|
|
|
Received 2 letters of transmittal, 2 united water flow letter, two sets of sheets A1 & C1, with ESC application, Taken to Mike P.
|
Routing - PLAN CHECK | 6/3/2004 | | 6/3/2004 | | |
|
|
|
Routing to Planning.
|
Routing - PLAN CHECK | 5/26/2004 | | 6/3/2004 | | FAIL |
|
|
|
Need heating and cooling load calc's.
|
Plan resubmittals received | | | 5/27/2004 | | DONE |
|
|
|
Received transmittal letter, copy of plan review comment letter, four copies of response letters,three copies of review comment calculations, three sets of sheets A2,A4,A5,A6,EN1,M4,E1 with 5 copies of C1 sheets, taken to Mike P.
|
Plan Review Completed(1st rev) | | | 5/26/2004 | | FAIL |
|
|
|
failed public works, planning, bldg and fire reviews
|
Routing - FIRE | 5/21/2004 | | 5/26/2004 | | FAIL |
|
|
|
Hydrant location and flow info required.
|
Routing Off Site - STRUCTURAL | 4/28/2004 | | 5/21/2004 | | FAIL |
|
|
|
Contacted PDQ to take plans to outside engineering.
Additional information required for further review by oue outside engineering firm.
|
Routing - PLAN CHECK | 5/12/2004 | | 5/21/2004 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Routing - PLUMBING | 5/12/2004 | | 5/12/2004 | | PASS |
|
|
|
|
Routing - PLANNING | 5/11/2004 | | 5/11/2004 | | FAIL |
|
|
|
drh03-00235 / car03-00055 Karen G.
Condition 1f of DRH03-235 regarding the shared ingress/egress easement and the shared parking agreement has not been met. Also, Condition 8 which addresses swales next to public right of ways needs to be discussed.
Also, Rezone has not gone through the final reading. Documents can not be finalized until this is done.
|
Routing - PUBLIC WORKS | 4/29/2004 | | 5/10/2004 | | FAIL |
|
|
|
Requires Drainage Plan.
|
Routing - Erosion and Sediment | 5/7/2004 | | 5/10/2004 | | PASS |
|
|
|
ESC approved with conditons attached to plans.
|
Routing - PLANNING Land Div | 5/7/2004 | | 5/7/2004 | | PASS |
|
|
|
Approved. Parcel created prior to October 30, 1965. Verified by recorded deed.
|
Plans ACCEPTED BY PLAN TECH | | | 4/29/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 4/29/2004 | | DONE |
|
|
|
Received 2 copys of structural calcs & Joint Access and Parking Agreement. Routed to Mike Phillips. Sent 1 copy to out side Engineering & routed the other copy to Mike Phillips.
|
Routing - PLANNING Land Div | 4/28/2004 | | 4/29/2004 | | FAIL |
|
|
|
Need proof of legal parcel. Called Russ Phillips ###-#### and Mike Byrnes at B & A Engineering ###-#### (left voice message) on April 29, 2004.
|
Plan routing begun/NEW & ADDTN | | | 4/28/2004 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 4/28/2004 | | PEND |
|
|
|
No Struc. calcs. submitted, contacted Russ Phillips. kmm
|
Application received | | | 4/26/2004 | | |
|
|
|
|
Override - Parcel Holds | | | 4/26/2004 | | |
|
|
|
|
Override - Parcel Holds | | | 4/26/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 4/26/2004 | | |
|
|
|
|
Fee Review-notes | 4/26/2004 | 4/26/2004 | | | |
|
|
|
|