Information based on query as of Saturday, August 17, 2024.
Permit Information
Permit NumberBLD04-00896
StatusFinaled
Name JEFF JOHNS
Site Address 607 W GROVE ST
Project NameBASQUE BOARDING HOUSE
Customer Number 
ePlanReviewNo
Description
(CYRUS JACOBS / UBERUAGA BOARDINGHOUSE) This building will be fire sprinklered in lieu of exterior opening protection, in lieu of a basement enclosure, in lieu of stair enclosures, in lieu of fire-resistance-rated corridors, in lieu of shafts, and for story increase. To perform restoration work to an existing historic building. Work is to include plaster repair, paint, wallpaper, window repair, a new HVAC system, electrical upgrades, and plumbing changes all per the approved drawings and the plan review report on file. The 1994 Uniform Code for Building Conservation (UCBC) shall be used to regulate this building. This building will be used as a museum with office use. Tours by the public will be under the supervision of staff. The size of tour groups will be small. A fire alarm system and a fire sprinkler system will be installed. The fire sprinkler system shall comply with NFPA 13-2002 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  1/27/2009  
Third Notice 1/30/20061/30/2006 DONE
Second Notice BLD1/20/20061/20/20061/30/2006 DONE
First Notice has not been responded to.
First Notice 1/10/20061/20/2006 DONE
First Notice 1/10/20061/20/2006 DONE
Permanent occupancy  1/10/2006  
Perm. Occ. Cert. # 10865 issued 1-10-06 to the Cyrus Jacobs/Uberuaga House.
Permanent Occupancy 1/6/20061/6/2006 DONE
Details
BLD-Final1/3/20061/4/20061/4/2006PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 1/3/2006 at 2:22:23 PM. Contact: ###-####. ok for perm occ
BLD-Aging Inspection12/7/200512/7/200512/7/2005 PASS
DetailsDave Hannah
BLD-Final7/27/20057/28/20057/28/2005APART
DetailsDave Hannah
jeff; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok for temp occ
FIRE-Final Inspection7/28/20057/28/20057/28/2005PPASS
DetailsForrest France
Fire life safety passed inspection.
BLD-Final7/27/20057/27/20057/27/2005PNR
DetailsDave Hannah
jeff; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Final7/27/20057/27/20057/27/2005PNR
DetailsDave Hannah
jeff; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie needs other trades to sign off
BLD-Aging Inspection9/8/20049/8/20049/8/2004 PART
DetailsDave Hannah
wip 9/9/2004 8:35:12 AM
Issue PAID IN FULL permit  6/9/2004  
Routing - PLAN CHECK5/27/2004 5/28/2004 DONE
PLANS/APPL TAKEN TO FRONT DESK  5/28/2004 DONE
Permit Ready to Issue  5/28/2004 DONE
Inspection Record Card- Bld  5/28/2004 DONE
Print Occupancy Form  5/28/2004 DONE
Telephone call  5/28/2004 DONE
Left message for Jeff Johns that permit is ready & fees//5/28/04 10:25AM//BAM
Telephone call  5/28/2004 DONE
Spoke with Tom Zabala and told him that permit is ready & fees///5/28/04 10:25am BAM
Plan assigned to (CJW)5/3/2004 5/28/2004 PASS
DetailsCarl Westfall
5/28/2004 08:28:38 CJW - activity updated through activity BLDA022 from case BLD04-00896.
Routing - FIRE5/24/2004 5/27/2004 PASS
Plan Review Completed(1st rev)  5/27/2004 DONE
Routing - PLAN CHECK5/3/2004 5/24/2004 PASS
IBC plan review started May 20, 2004 and finished May 24, 2004. The drawings were approved with clarifications. See the plan review report. A copy was E-mailed to the architect.
Routing - PUBLIC WORKS5/3/2004 5/3/2004 PASS
Plans ACCEPTED BY PLAN TECH  4/29/2004  
Application received  4/28/2004  
Recd Pcfee & Taken To Pln CK  4/28/2004 DONE
Fee Review-notes4/28/20044/28/2004