Permanent Occupancy | | | 7/28/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 2/24/2012 | | |
|
|
|
|
Second Notice BLD | 9/13/2007 | 9/13/2007 | 9/13/2007 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | 8/29/2007 | 8/29/2007 | 9/13/2007 | | DONE |
Tony Young
|
|
|
|
Fee Review-notes | 5/4/2004 | 5/4/2004 | 9/13/2007 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/10/2004 | | 9/13/2007 | | PASS |
|
|
|
Contacted PDQ for outside engineering.
|
BLD-Aging Inspection | 8/29/2007 | 8/29/2007 | 8/29/2007 | | PEND |
Tony Young
|
|
|
|
DOC - Permit Finaled | 8/29/2007 | 8/29/2007 | 8/29/2007 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 5/22/2007 | 5/23/2007 | 5/23/2007 | A | PASS |
Tony Young
|
|
|
Buddy, Cathy W. has final paperwork on her desk; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt
|
FIRE-Final Inspection | 5/22/2007 | 5/23/2007 | 5/23/2007 | A | PASS |
Forrest France
|
|
|
Fire life safety is acceptable for final.
|
Permanent Occupancy | | 5/23/2007 | 5/23/2007 | | DONE |
|
|
|
|
Code Occupancy Approval | 5/17/2007 | 5/17/2007 | 5/17/2007 | P | PASS |
Michael Garner
|
|
|
SITE INSPECTION COMPLETE - i REVIEWED THE APPROVED PLANS AND CONDITIONS AND HAVE FOUND THEM TO BE IN SUBSTANTIAL COMPLIANCE: I DID NOTE THE FOLLOWING CHANGES -
1. PLANS CALLED FOR A SOLID PLANTER ON THE MINI-COURTYARD BETWEEN THE CENTER BLDGS - THAT WAS CHANGED TO INDIVIDUAL VASE PLANTERS PER CONSULTATION WITH THE FIRE DEPARTMENT WHO HAD CONCERNS ABOUT ACCESS TO HOSE CONNECTIONS AND INTO THE BLDGS. THEMSELVES
2. PLANS FOR THE CENTER BLDGS CALLED FOR THREE [3] VERTICALLY STACKED WINDOWS MIRRORING THE INTERIOR STAIRWELLS - THAT HAS BEEN CHANGED TO TWO WINDOWS, WITH THE MIDDLE WINDOW REMOVED TO ACCOMODATE A REQUIRED A NECESSARY STRUCTURAL BEAM
3. ORIGINAL PLANS CALLED FOR ROUGH-HEWN [CEDAR?] SHINGLES - BLDR. INSTEAD USED HARDI-PLANK SHINGLES BECAUSE THEY ARE LONGER LASTING, EASIER TO MAINTAIN
4. THE MOST INTERIOR [CLOSEST TO CREEK] BLDGS DO NOT HAVE A STUCCO SKIRT AS THE PLANS CALLED FOR...INSTEAD THEY HAVE A STONE SKIRT WHICH IS IN KEEPING WITH THE STONE SKIRTS ON ALL THE OTHER BLDGS.
THESE CHANGES ARE ACCEPTABLE AND WITHIN THE PARAMETERS OF THE SCOPE AND INTENT OF THE APPROVED PLANS AND CONDITIONS - PASS/CASE CLOSED
|
BLD-Aging Inspection | 2/28/2007 | 2/28/2007 | 2/28/2007 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 12/15/2006 | 12/15/2006 | 12/18/2006 | | PASS |
Tony Young
|
|
|
|
BLD-Final | 10/10/2006 | 10/11/2006 | 10/11/2006 | P | PART |
Jim Sly
|
|
|
buddy; Phone #: ###-#### Internet Inspection Request from: Patricia Smith OK for Temp Occ.
|
Temporary occupancy | | | 10/11/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5459 issued 10-11-06 to Highland Village Apts., Bldg. # 8
|
FIRE-Final Inspection | 10/10/2006 | 10/10/2006 | 10/10/2006 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave hannimans permission until the elevator recall has been tested. The elevator is to remain locked out and unusable until all inspections have been passed. All other life safety items have been tested.
|
BLD-Aging Inspection | 10/5/2006 | 10/5/2006 | 10/6/2006 | | PEND |
Tony Young
|
|
|
|
Inspection Record Card- Bld | | | 8/31/2006 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/31/2006 | | DONE |
|
|
|
|
BLD-Aging Inspection | 7/17/2006 | 7/17/2006 | 7/18/2006 | | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 4/24/2006 | 4/25/2006 | 4/25/2006 | A | PASS |
Tony Young
|
|
|
Phone #: ###-#### Internet Inspection Request from: Rita DeYoung
|
BLD-Energy code compliance | 4/18/2006 | 4/19/2006 | 4/19/2006 | P | PART |
Tony Young
|
|
|
Keil ###-#### --- also sprinkler insulation insp with Forrest France 4-19 PM need some f/block at kitchen, upper south east by f/p
|
FIRE-Sprinkler Rough-in | 4/18/2006 | 4/19/2006 | 4/18/2006 | P | PART |
Forrest France
|
|
|
Overhead fire sprinkler is good for cover.
|
Override - People Holds | | | 4/18/2006 | | |
|
|
|
|
Override - People Holds | | | 4/18/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 4/12/2006 | 4/13/2006 | 4/13/2006 | P | PART |
Tony Young
|
|
|
keal; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles c/n,, ok to insulate,, verify elec. permit for elevator prior to cover,, also sprinklers need another inspection for cover/tenting,,, c/n involves fireblocking w/ mineral wool,, point loads,, nail hangers,, straps on plates
|
BLD-Aging Inspection | 3/28/2006 | 3/28/2006 | 3/28/2006 | | PASS |
Tony Young
|
|
|
|
Case Summary (BLD) | | | 3/16/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 1/19/2006 | 1/20/2006 | 1/20/2006 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 1/19/2006 at 3:44:58 PM. Contact: ###-####. ext. shear ok
|
BLD-Other | 1/17/2006 | 1/17/2006 | 1/17/2006 | P | FAIL |
Tony Young
|
|
|
shearing inspection to approve for exterior cover//keil ###-#### need to redo some areas
|
Override - People Holds | | | 1/17/2006 | | |
|
|
|
|
BLD-Framing/Rough-in | 10/17/2005 | 10/18/2005 | 10/18/2005 | A | CANC |
Jim Storey
|
|
|
JIM; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 7/19/2005 | 7/19/2005 | 7/19/2005 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 7/19/2005 at 7:39:50 AM. Contact: ###-####.
|
BLD-Foundation | 5/19/2005 | 5/20/2005 | 5/20/2005 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/19/2005 at 3:14:32 PM. Contact: ###-####.
|
BLD-Footing | 5/12/2005 | 5/13/2005 | 5/13/2005 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 5/12/2005 at 10:54:25 AM. Contact: ###-####.
south half ftgs ok, wip 5/13/2005 11:02:38 AM
|
BLD-Footing | 5/11/2005 | 5/11/2005 | 5/11/2005 | P | PART |
Dave Hannah
|
|
|
ok to pour north half
|
(F) Reprint permit | | | 2/14/2005 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/14/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/10/2005 | | 2/11/2005 | | PASS |
|
|
|
|
Received Certificate of Value | | | 2/11/2005 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/11/2005 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 2/11/2005 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 2/11/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/11/2005 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/11/2005 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/11/2005 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/11/2005 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 5/4/2004 | | 2/11/2005 | | PASS |
Mike Phillips
|
|
|
2/11/2005 14:38:50 M_P - activity updated through activity BLDA022 from case BLD04-00943.
|
Routing - PLAN CHECK | 1/28/2005 | | 2/10/2005 | | |
|
|
|
Routing to planning.
|
Routing - PLANNING | 2/10/2005 | | 2/10/2005 | | PASS |
|
|
|
Plans approved for CUP and DRH compliance.
|
Routing - FIRE | 1/21/2005 | | 1/28/2005 | | PASS |
|
|
|
resubmittal acceptable.
|
Plan resubmittals received | | | 1/25/2005 | | |
|
|
|
Received sheet A1.1
|
Routing - PLAN CHECK | 12/6/2004 | | 1/21/2005 | | |
|
|
|
Routing to Planning.
|
Routing - PLANNING | 1/21/2005 | | 1/21/2005 | | FAIL |
|
|
|
Need amenity clarification on BBQ pit and 22-feet of straight back-up on driveway for Unit #6 and handicap space designated on south property line. kg
|
Plan resubmittals received | | | 1/20/2005 | | DONE |
|
|
|
Received Transmittal Letter, & 8 Copys of sheets, L1,L2,L3,L4,L5,L6,L7,L8,L9 Taken to Mike P.
|
Routing - PLANNING | 12/16/2004 | | 1/7/2005 | | FAIL |
|
|
|
Revised plans needed for compliance with Design Review and Conditional Use approvals. Informed Steve Dresser via phone call on January 6, 2005.
|
Plan resubmittals received | | | 12/20/2004 | | DONE |
|
|
|
Received two sets of sheets A1.1,A2.1,A2.1A,A3.3,A3.4,A3.5,A3.6,A7.2,E2.1,E2.1,E2.1A,S2.1A,S2.2,S3.1,S6.1 Taken to Mike P.
|
Routing - PLAN CHECK | 11/1/2004 | | 12/6/2004 | | FAIL |
|
|
|
Third review failed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Plan resubmittals received | | | 11/23/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 2 Sets of A2.1, A2.1A, A2.2, A2.3, A3.1,A3.1A, A3.2, A3.2A, A3.3, A3.4, A3.5, A3.6, A4.1, E2.1, E2.1A, S1.1, S1.1(A), S2.1, S2.1(A) S2.2, S6.1, S7.1 Tasken to Mike P
|
Routing - FIRE | 10/27/2004 | | 11/1/2004 | | FAIL |
|
|
|
No fire resubmittal. Called architect and reviewed resubmittal requirement per 6/23/04 review. He overlooked, will resubmit.
|
Routing - PLAN CHECK | 9/7/2004 | | 10/27/2004 | | FAIL |
|
|
|
Second review failed sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Plan resubmittals received | | | 10/25/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 4 Copys of sheets 12 OF 15,13 OF 15,1 OF 1 Taken to Mike Phillips...
|
Plan resubmittals received | | | 9/30/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 2 Sets of A0.1,A0.2,A0.3,A0.4,A0.5,A0.6,A0.7,A0.8,A0.9,A1.1,A2.1,A2.1A,A2.2,A2.3,A2.4,A2.5,A3.1,A3.1A,A3.2,A3.2AA3.3,A3.4 (2) A3.5 A4.1,A5.1,A5.2,A7.1,A7.2,E2.1,E2.1A,E2.2 Taken to Mike Phillips
|
Routing - PLANNING | 8/26/2004 | | 9/7/2004 | | FAIL |
|
|
|
Plans do not comply with CU conditions.
Also, the DR approval requires that the CU conditions be met prior to approval of building permit plans. The Design Review also requires that the landscape plan be revised per Forester's comments.
|
Plan resubmittals received | | | 9/1/2004 | | DONE |
|
|
|
Received transmittal letter and eight sets of sheet 1 through 15 all taken to Mike P.
|
Routing - PLAN CHECK | 8/9/2004 | | 8/26/2004 | | |
Mike Phillips
|
|
|
Routing to planning
|
Routing - PLUMBING | 8/3/2004 | | 8/9/2004 | | PASS |
|
|
|
per plan and 2003 UPC
|
Routing - PLAN CHECK | 6/24/2004 | | 8/3/2004 | | |
|
|
|
Routing to Plumbing.
|
Routing - FIRE | 6/21/2004 | | 6/23/2004 | | FAIL |
|
|
|
Hydrant flow, AS info, FA not provided. Review comments faxed to architect.
|
Plan Review Completed(1st rev) | | | 6/23/2004 | | FAIL |
|
|
|
failed fire, plumbing and plan check.
|
Case Summary (BLD) | | | 6/21/2004 | | |
|
|
|
|
Routing - PLAN CHECK | 6/4/2004 | | 6/21/2004 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Routing - PLUMBING | 5/28/2004 | | 6/3/2004 | | FAIL |
|
|
|
please provide a plan showing the items listed above.
|
Routing - PLANNING | 5/27/2004 | | 5/28/2004 | | PEND |
|
|
|
Pend Conditional Use Modification approvals.
|
Routing - Erosion and Sediment | | | 5/27/2004 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 5/12/2004 | | 5/20/2004 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 5/10/2004 | | 5/11/2004 | | PASS |
|
|
|
Approved by ROS03-00009. Recorded ROS 6173 on 5/22/03.
|
Plans ACCEPTED BY PLAN TECH | | | 5/10/2004 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 5/10/2004 | | DONE |
|
|
|
|
Application received | | | 5/4/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/4/2004 | | DONE |
|
|
|
|