Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD04-00958
StatusFinaled
Name BRIGHTON CORPORATION
Site Address 12754 W LASALLE ST
Project NameLASALLE BLDG
Customer Number 
ePlanReviewNo
Description
LaSalle Boise Research Center (Shell Office Building) - To construct a new 16,940 square foot, one story, concrete tilt-up offiice shell building and related site improvement. This is a shell building permit only and no occupancy is allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. This building is fully fire sprinklered. The sprinklers are used for area increase. All construction per the approved plans and attached comment list. DRH04-52/#04-280/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection3/24/20053/24/20053/24/2005PPASS
DetailsTroy Cobbley
fire life safety finaled
PubWorks Occupancy Approval3/14/20053/14/20053/15/2005 DONE
Drainage project complete, OK for occupancy 3/14/05. M.Strasser
BLD-Final3/14/20053/14/20053/14/2005PPASS
DetailsJim Sly
12601 w explorer drive suite 200 for signature card///dave kodanko; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Certificate of Compliance issued. 3/14/2005 3:03:39 PM
DOC - Permit Finaled  3/14/2005 DONE
BLD-Final2/11/20052/11/20052/11/2005PNR
DetailsJim Sly
Scheduled by a contractor via Hello! on 2/11/2005 at 8:32:26 AM. Verified Letter of approval from special insp agency and Pinnacle Engineering. Need sign off from Public Works and Code Enf. OK to final when these signed off. 2/11/2005 3:31:11 PM
BLD-Final1/28/20051/28/20051/28/2005PNR
DetailsJim Sly
Scheduled by a contractor via Hello! on 1/28/2005 at 8:13:13 AM. Need fire permit finaled. 1/28/2005 2:00:51 PM
BLD-Concrete9/29/20049/29/20049/29/2004PPART
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/29/2004 at 9:07:24 AM. Contact: ###-####.
BLD-Concrete8/25/20048/26/20048/26/2004APART
DetailsJim Sly
dave; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Approx 12 tilt up panels poured......MTI on site....OK pending special insp reports and approvals. 8/26/2004 11:24:35 AM
BLD-Concrete7/29/20047/29/20047/29/2004PPART
DetailsJim Sly
###-#### David On 7/28 Center footings for columns were poured.....Today slab poured.....MTI is doing special inspections. 7/29/2004 3:21:34 PM
BLD-Footing7/27/20047/28/20047/28/2004APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 7/27/2004 at 4:57:44 PM.
(F) Reprint permit  7/16/2004  
Issue PAID IN FULL permit  7/15/2004 DONE
Plan assigned to (JCM)5/10/2004 7/9/2004 PASS
DetailsJohn Menard
7/9/2004 13:16:55 JCM - activity updated through activity BLDA022 from case BLD04-00958.
Routing - PLANNING7/7/2004 7/9/2004 PASS
Approver per DRH04-52 and per revised site and landscape plans in file dated received 6/11 and 6/16/04.
Routing - PLAN CHECK7/9/2004 7/9/2004 PASS
PLANS/APPL TAKEN TO FRONT DESK  7/9/2004 DONE
Inspection Record Card- Bld  7/9/2004 DONE
Permit Ready to Issue  7/9/2004 DONE
Telephone call  7/9/2004 DONE
permit ready and fees due
Routing - PLAN CHECK7/7/2004 7/7/2004  
Routing - FIRE6/30/2004 7/6/2004 PASS
2nd resubmittal acceptable.
Plan Reviewer's activity  6/30/2004  
Inserted revised civil plans and routed to fire. JCM
Routing - PLAN CHECK6/23/2004 6/30/2004  
Plan resubmittals received  6/29/2004 DONE
Received Transmittal Letter, 3 Sets of C1 , C2 , C3 Taken to John M.....
Routing - FIRE6/18/2004 6/23/2004 FAIL
fire hydrant spacing is still inadequate.
Routing - PLAN CHECK6/18/2004 6/18/2004  
Routing - PUBLIC WORKS6/15/2004 6/18/2004 PASS
Plan resubmittals received  6/16/2004 DONE
Received two response letters to Bill Alexander and Tempra Wison, United water volume information three C4 sheets and one L1 sheet all taken to John M. 6-18-04 John M brought 1 L1 sheet and Transmittal letter to be taken to Tempra W.
Routing Off Site - STRUCTURAL6/9/2004 6/15/2004 PASS
Called PDQ for pick-up DLD Received a faxed response from the consulting structural engineer approving the structural resubmitted construction documents. JCM
Routing - PLAN CHECK6/10/2004 6/15/2004  
Routing - Erosion and Sediment6/11/2004 6/14/2004 PASS
ESC approved with conditions attached to plans. RP must be designated prior to the start of construction or a stop work order will be issued.
Plan Reviewer's activity  6/11/2004 PASS
Reviewed and approved resubmitals. JCM
Plan Review Completed(1st rev)  6/9/2004 DONE
Fail:
Public Works
Planning
Plan Check
Fire
Plan resubmittals received  6/9/2004 DONE
Received Transmittal Letter, 3 Booklets of Sturctural Plan Review Comments, 3 Sets with pages S3.1 , S4.1 , S4.2 ,S6.2 ,S7.1 ,S7.2 , S7.3 Taken to John Menard..
Routing - FIRE6/7/2004 6/9/2004 FAIL
DetailsBill Alexander
1. No fire hydrant locations provided in this package. (BMC 7-01-43, IFC 912.2.1.1, IFC 508.1.1, BMC 7-01-45, IFC 508.5.1, and IFC 912.2.1.1)

2. No Hydrant of Fire Sprinkler Design Flows provided in this package. (IFC 508.1, 508.3) System water flows information is for uniformity and consistency in the fire sprinkler system design.
Routing - PLUMBING6/4/2004 6/7/2004 PASS
per plans and 2000 upc.
Routing - PLANNING5/25/2004 6/3/2004 FAIL
Applicant needs to address conditions of DRH04-00052. Have contacted the applicant.
Plan resubmittals received  5/28/2004 DONE
Received response letter with four A2.2 sheets taken to John M.
Plan resubmittals received  5/27/2004 DONE
Received letter of transmittal with two copies of ESC narrative and two copies of C3 sheets. Taken to John M.
Plan resubmittals requested  5/26/2004  
Faxed the architect a copy of the plans review comment list from the consulting structural engineer requesting revisions. JCM
Routing Off Site - STRUCTURAL5/10/2004 5/26/2004 FAIL
Received a fax from the consulting structural engineer requesting revisions. JCM
Routing - Erosion and Sediment5/24/2004 5/25/2004 FAIL
ESC plan does not meet requirements of BCC 8-17 app. a and c.
Routing - PUBLIC WORKS5/11/2004 5/24/2004 FAIL
Failed storm water drainage (Brian Murphy). Calcs & O&M manual.
Routing - PLAN CHECK5/24/2004 5/24/2004 FAIL
Plan resubmittals requested  5/24/2004  
Mailed the architect a copy of the plans review comment list requesting revisions. JCM
Plans ACCEPTED BY PLAN TECH  5/10/2004 PEND
No Drainage Calcs or O&M Manuals Sent a fax letter to Wes Steele requesting 2 Drainage Calcs & 2 O & M Manuals Envelope compliance not signed. ///DLD
Routing - PLANNING Land Div5/10/2004 5/10/2004 PASS
Lot 3, Block 7 of Research Center #2.
Application received  5/4/2004  
Recd Pcfee & Taken To Pln CK  5/4/2004  
Fee Review-notes5/4/20045/4/2004