Third Notice BLD | 2/7/2006 | 2/7/2006 | 8/28/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 1/13/2006 | 1/13/2006 | 2/7/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 12/30/2005 | 1/13/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 12/30/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10856 issued 12-30-05 to the Idaho Central Credit Union.
|
BLD-Final | 9/14/2005 | 9/14/2005 | 9/14/2005 | P | PASS |
Dave Hannah
|
|
|
paul -pending fire fn ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok for perm occ
|
FIRE-Final Inspection | 9/14/2005 | 9/14/2005 | 9/14/2005 | P | PASS |
Forrest France
|
|
|
Code deficient items have been corrected, life safety finaled.
|
Permanent Occupancy | | 9/14/2005 | 9/14/2005 | | DONE |
|
|
|
|
FIRE-Final Inspection | 7/14/2005 | 7/15/2005 | 7/15/2005 | A | FAIL |
Forrest France
|
|
|
Provide signage above main entry/exit doors, remove thumbturn and provide approved door hardware at east exit.
|
BLD-Framing/Rough-in | 4/11/2005 | 4/11/2005 | 4/11/2005 | P | PART |
Dave Hannah
|
|
|
paul; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ceiling grid over teller area 4/11/2005 1:13:47 PM
|
BLD-Framing/Rough-in | 3/24/2005 | 3/24/2005 | 3/24/2005 | P | PART |
Dave Hannah
|
|
|
ceiling inspection please///paul; Phone #: ###-#### Internet Inspection Request from: Barbara Moore south half ok to drop in panales 3/24/2005 2:09:08 PM
|
BLD-Framing/Rough-in | 3/10/2005 | 3/10/2005 | 3/10/2005 | P | PART |
Dave Hannah
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Jan Rice wallway walls office side and sup soffits ok to cover 3/10/2005 2:20:26 PM
|
BLD-Framing/Rough-in | 12/29/2004 | 12/29/2004 | 12/29/2004 | P | PART |
Dave Hannah
|
|
|
Paul; Phone #: ###-#### Internet Inspection Request from: Jan Rice int wall ok to cover 12/29/2004 2:21:43 PM
|
BLD-Aging Inspection | 10/19/2004 | 10/19/2004 | 10/19/2004 | | PASS |
Dave Hannah
|
|
|
|
Case Summary (BLD) | | | 10/14/2004 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/16/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/13/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/13/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/13/2004 | | |
|
|
|
|
Telephone call | | | 7/13/2004 | | DONE |
|
|
|
left mess that permit is ready
|
Routing - PLAN CHECK | 7/2/2004 | | 7/12/2004 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/12/2004 | | PASS |
|
|
|
|
Plan assigned to (JCB) | 5/12/2004 | | 7/12/2004 | | PASS |
Jason Blais
|
|
|
7/12/2004 09:21:31 JCB - activity updated through activity BLDA022 from case BLD04-00982.
|
Routing - FIRE | 6/26/2004 | | 7/2/2004 | | PASS |
|
|
|
Resubmittal acceptable
|
Routing - PLAN CHECK | 6/15/2004 | | 6/26/2004 | | PEND |
|
|
|
When approved by Fire Dept. permit can be issued. Plans to route to Fire Dept. for review.
|
Plan resubmittals received | | | 6/22/2004 | | DONE |
|
|
|
Received transmittal letter with response letter, copy of TI applications for space #100,#101,102,#203,& 203A. two sets of sheets A0.1,A2.0,A2.3,A2.4,A2.5,A2.7,E2.4, E2.5,E3.2,Taken to jason
|
Routing - FIRE | 6/9/2004 | | 6/14/2004 | | FAIL |
Bill Alexander
|
|
|
Reference IBC Issues relating to the IFC.
|
Plan Review Completed(1st rev) | | | 6/14/2004 | | FAIL |
|
|
|
Failed:
Plan Check
Fire
|
Routing - PLAN CHECK | 5/13/2004 | | 6/9/2004 | | FAIL |
|
|
|
Plan review sent and faxed to architect. Plan resubmittals and written response required for further review. Project needs to be broken out into (5) permits that can be attached to the same set of plans. Plans to route to Fire Dept. for review.
|
Routing - PUBLIC WORKS | 5/12/2004 | | 5/13/2004 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/11/2004 | | DONE |
|
|
|
|
Application received | | | 5/6/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/6/2004 | | DONE |
|
|
|
|
Fee Review-notes | 5/6/2004 | 5/6/2004 | | | |
|
|
|
|