Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD04-00982
StatusFinaled
Name GORRINGE BROTHERS
Site Address 200 N 4TH ST Unit: 100
Project NameTERRACE PLAZA-1ST FLR
Customer Number 
ePlanReviewNo
Description
(IDAHO CENTRAL CREDIT UNION)(TERRACE PLAZA - 1ST FLR - STE 100) Interior remodel in an existing building to expand 762 sq. ft. of area to an existing 1,824 sq. ft. credit union/office space and relocate the exit hallway on the first floor per approved plans on file. New area total for space will be 2,586 sq. ft. There will be (2) "vanilla finish" permits and (2) other tenant permits also attached to the same set of plans that will be done on both the first floor and second floor of this building. Work to include miscellaneous interior demolition work, new relocated building core exit hallway, new interior walls, new interior doors and windows, interior finish, new suspended ceiling work, new soffit work, fire sprinkler work, fire alarm work, mechanical work, and electrical work. A Certificate of Occupancy is to be issued when completed and approved. NOTE: This building has a fire alarm system and is to be fully fire sprinklered by December of 2008 per an Upgrade Agreement on file. Fire sprinklers alleviate requirements for one-hour rated exit corridors and protection of elevator openings in building. This permit along with the (4) other permits attached to the plans (BLD04-01413, BLD04-01415, BLD04-01416, & BLD04-01417) will cover Phase I of the Upgrade Agreement. Fire sprinklers will be provided in corridors, lobby areas, restrooms, and remodeled and vacant tenant spaces on the first and second floors. (PC#0291-04) JCB
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD2/7/20062/7/20068/28/2006 DONE
Second Notice has not been responded to.
Second Notice BLD1/13/20061/13/20062/7/2006 DONE
First Notice has not been responded to.
First Notice 12/30/20051/13/2006 DONE
Permanent occupancy  12/30/2005 DONE
Perm. Occ. Cert. # 10856 issued 12-30-05 to the Idaho Central Credit Union.
BLD-Final9/14/20059/14/20059/14/2005PPASS
DetailsDave Hannah
paul -pending fire fn ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ok for perm occ
FIRE-Final Inspection9/14/20059/14/20059/14/2005PPASS
DetailsForrest France
Code deficient items have been corrected, life safety finaled.
Permanent Occupancy 9/14/20059/14/2005 DONE
Details
FIRE-Final Inspection7/14/20057/15/20057/15/2005AFAIL
DetailsForrest France
Provide signage above main entry/exit doors, remove thumbturn and provide approved door hardware at east exit.
BLD-Framing/Rough-in4/11/20054/11/20054/11/2005PPART
DetailsDave Hannah
paul; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie ceiling grid over teller area 4/11/2005 1:13:47 PM
BLD-Framing/Rough-in3/24/20053/24/20053/24/2005PPART
DetailsDave Hannah
ceiling inspection please///paul; Phone #: ###-#### Internet Inspection Request from: Barbara Moore south half ok to drop in panales 3/24/2005 2:09:08 PM
BLD-Framing/Rough-in3/10/20053/10/20053/10/2005PPART
DetailsDave Hannah
Mike; Phone #: ###-#### Internet Inspection Request from: Jan Rice wallway walls office side and sup soffits ok to cover 3/10/2005 2:20:26 PM
BLD-Framing/Rough-in12/29/200412/29/200412/29/2004PPART
DetailsDave Hannah
Paul; Phone #: ###-#### Internet Inspection Request from: Jan Rice int wall ok to cover 12/29/2004 2:21:43 PM
BLD-Aging Inspection10/19/200410/19/200410/19/2004 PASS
DetailsDave Hannah
Case Summary (BLD)  10/14/2004 DONE
Issue PAID IN FULL permit  7/16/2004 DONE
Inspection Record Card- Bld  7/13/2004 DONE
Print Occupancy Form  7/13/2004 DONE
Permit Ready to Issue  7/13/2004  
Telephone call  7/13/2004 DONE
left mess that permit is ready
Routing - PLAN CHECK7/2/2004 7/12/2004 PASS
Permit and plans approved and taken to front desk.
PLANS/APPL TAKEN TO FRONT DESK  7/12/2004 PASS
Plan assigned to (JCB)5/12/2004 7/12/2004 PASS
DetailsJason Blais
7/12/2004 09:21:31 JCB - activity updated through activity BLDA022 from case BLD04-00982.
Routing - FIRE6/26/2004 7/2/2004 PASS
Resubmittal acceptable
Routing - PLAN CHECK6/15/2004 6/26/2004 PEND
When approved by Fire Dept. permit can be issued. Plans to route to Fire Dept. for review.
Plan resubmittals received  6/22/2004 DONE
Received transmittal letter with response letter, copy of TI applications for space #100,#101,102,#203,& 203A. two sets of sheets A0.1,A2.0,A2.3,A2.4,A2.5,A2.7,E2.4, E2.5,E3.2,Taken to jason
Routing - FIRE6/9/2004 6/14/2004 FAIL
DetailsBill Alexander
Reference IBC Issues relating to the IFC.
Plan Review Completed(1st rev)  6/14/2004 FAIL
Failed:
Plan Check
Fire
Routing - PLAN CHECK5/13/2004 6/9/2004 FAIL
Plan review sent and faxed to architect. Plan resubmittals and written response required for further review. Project needs to be broken out into (5) permits that can be attached to the same set of plans. Plans to route to Fire Dept. for review.
Routing - PUBLIC WORKS5/12/2004 5/13/2004 PASS
Plans ACCEPTED BY PLAN TECH  5/11/2004 DONE
Application received  5/6/2004  
Recd Pcfee & Taken To Pln CK  5/6/2004 DONE
Fee Review-notes5/6/20045/6/2004