Second Notice BLD | 5/20/2005 | 5/20/2005 | 11/3/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 4/19/2005 | 5/20/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/19/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10535 issued 4-19-05 to Dr. Dennis Garpetti.
|
Permanent Occupancy | | 4/18/2005 | 4/18/2005 | | DONE |
|
|
|
|
BLD-Final | 4/15/2005 | 4/18/2005 | 4/18/2005 | A | PASS |
Jim Sly
|
|
|
scott; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Mech approved resubmittal for conditioned crawl......Bldg approved also. OK for Perm Occ. 4/18/2005 11:37:34 AM
|
BLD-Final | 4/14/2005 | 4/15/2005 | 4/15/2005 | A | FAIL |
Jim Sly
|
|
|
scott; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Told Scott that I need Mech approval for revised conditioned crawlspace B 4 I final. 4/15/2005 11:11:28 AM
|
Plan resubmittals received | | | 4/12/2005 | | DONE |
|
|
|
Received Transmittal Letter, & 2 Copys of sheet M1 Taken to Mike O.
|
Routing - PLAN CHECK | 4/12/2005 | | 4/12/2005 | | PASS |
|
|
|
minor revision ok MLO
|
Code Occupancy Approval | 4/7/2005 | 4/7/2005 | 4/7/2005 | A | PASS |
Carol Montgomery
|
|
|
ike rack is in - Compliance with permit. Final 4/7/2005 9:29:49 AM
|
Plan resubmittals received | | | 4/7/2005 | | DONE |
|
|
|
Received Transmittal Letter, 2 Copys of sheets G-1,A-4.1,A-5.1,M-1 Taken to Mike O.
|
Temporary occupancy | | | 3/14/2005 | | DONE |
|
|
|
Temp. Occ. Cert. # 5221 issued 3-14-05 to the Dr. Garpetti office.
|
BLD-Final | 3/10/2005 | 3/11/2005 | 3/11/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/10/2005 at 5:16:06 PM. Contact: ###-####. OK for Temp Occ. C/N Need underfloor insul, remove non rated vapor barrier Bsmnt walls Need Code Enf final All within 90 days of this notice. 3/11/2005 12:07:13 PM
|
FIRE-Final Inspection | 3/9/2005 | 3/10/2005 | 3/10/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled 3/10/2005 1:57:31 PM
|
BLD-Final | 3/9/2005 | 3/10/2005 | 3/10/2005 | A | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 3/9/2005 at 6:42:51 PM. Contact: ###-####.
|
BLD-Final | 3/10/2005 | 3/10/2005 | 3/10/2005 | P | NR |
Jim Sly
|
|
|
Scott; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
FIRE-Final Inspection | 3/8/2005 | 3/9/2005 | 3/9/2005 | P | FAIL |
Troy Cobbley
|
|
|
Provide exit signs and emergency light at the north east exit. Provide battery backup in the two exit signs out the main exit 3/9/2005 4:04:13 PM
|
BLD-Framing/Rough-in | 2/16/2005 | 2/17/2005 | 2/17/2005 | A | PASS |
Jim Sly
|
|
|
scott; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Grid OK. 2/18/2005 12:36:31 PM
|
BLD-Energy code compliance | 1/3/2005 | 1/4/2005 | 1/4/2005 | A | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Internet Inspection Request from: scott Hawker
|
BLD-Energy code compliance | 1/2/2005 | 1/3/2005 | 1/3/2005 | A | NR |
Jim Sly
|
|
|
Please call Scott Hawker prior to going to site for inspection; Phone #: ###-#### Internet Inspection Request from: scott Hawker
|
BLD-Framing/Rough-in | 12/29/2004 | 12/30/2004 | 12/30/2004 | A | PASS |
Jim Sly
|
|
|
Justin; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
BLD-Framing/Rough-in | 12/22/2004 | 12/23/2004 | 12/23/2004 | P | FAIL |
Lane Manuel
|
|
|
Justin ###-#### Internet Inspection Request from: Jan Rice
C/N POSTED 12/23/2004 2:16:43 PM
|
BLD-Foundation | 9/3/2004 | 9/7/2004 | 9/7/2004 | A | PASS |
Tom Arcoraci
|
|
|
chris; Phone #: ###-#### Internet Inspection Request from: Annette Moore
|
BLD-Footing | 8/30/2004 | 8/30/2004 | 8/30/2004 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 8/30/2004 at 8:35:15 AM. Contact: ###-####. Footings OK No special insp req. Not on plans....called engineer at Stapley ... Greg said 2500 PSI design. 8/30/2004 2:17:50 PM
|
(F) Reprint permit | | | 7/28/2004 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/27/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/26/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/26/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/26/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/26/2004 | | DONE |
|
|
|
|
Telephone call | | | 7/26/2004 | | DONE |
|
|
|
left mess for andres davis ###-#### that permit is ready
|
Plan assigned to (MLO) | 5/25/2004 | | 7/26/2004 | | PASS |
Mike Otto
|
|
|
7/26/2004 14:04:42 MLO - activity updated through activity BLDA022 from case BLD04-01073.
|
Routing - FIRE | 7/22/2004 | | 7/23/2004 | | PASS |
|
|
|
resubmittal acceptable.
|
Plan resubmittals received | | | 7/22/2004 | | DONE |
|
|
|
Received letter of transmittal with two sets of sheets A-1.1,A4.1,A5.2,A8.1, Taken to Mike O.
|
Routing - PLAN CHECK | 7/22/2004 | | 7/22/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/19/2004 | | DONE |
|
|
|
Received Transmittal Letter, and 2 Sets of G-1, SD-1, A-1.1, A-1.2, A-2.1, A-2.2, A3.1, A4.1, A5.1, A5.2, A7.1, A7.2, A8.1, A9.1, A10.1, ID-1 Taken to Mike Otto...
|
Routing - FIRE | 6/22/2004 | | 6/25/2004 | | FAIL |
|
|
|
hyd location, hyd flow and FR const details missing.
|
Plan Review Completed(1st rev) | | | 6/25/2004 | | FAIL |
|
|
|
failed plan check and Fire.
|
Plan resubmittals requested | | | 6/22/2004 | | DONE |
|
|
|
IBC corrections
|
Routing - PLAN CHECK | 6/16/2004 | | 6/22/2004 | | FAIL |
|
|
|
corrections sent to architect. MLO
|
Routing - PLUMBING | 6/14/2004 | | 6/16/2004 | | PASS |
|
|
|
1. sunp requires dual pumps on public buildings. 2.. vacuum pump discharge requires a moisture/air seperator on discharge line to roof
|
Routing - PLANNING | 6/11/2004 | | 6/14/2004 | | PASS |
|
|
|
Approve per DRH04-7
|
Routing - Erosion and Sediment | 6/8/2004 | | 6/11/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
PubWorks Occupancy Approval | 6/9/2004 | 6/9/2004 | 6/9/2004 | | DONE |
|
|
|
No drainage inspection required per Brian Murphy, 6/9/04. No inspections done.
|
Routing - PUBLIC WORKS | 5/25/2004 | | 6/8/2004 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/25/2004 | | 6/2/2004 | | PASS |
|
|
|
Contacted PDQ for outside engineering.
|
Pending Assignment by JCM | 5/24/2004 | | 5/25/2004 | | DONE |
John Menard
|
|
|
5/25/2004 08:44:30 JCM - activity updated through activity BLDA166 from case BLD04-01073.
|
Routing - PLANNING Land Div | 5/25/2004 | | 5/25/2004 | | DONE |
|
|
|
Lot 2, Block 1, Streeper Subdivision
|
Plans ACCEPTED BY PLAN TECH | | | 5/25/2004 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 5/25/2004 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/24/2004 | | DONE |
|
|
|
|
Application received | | | 5/18/2004 | | |
|
|
|
|