Third Notice BLD | 5/20/2005 | 5/20/2005 | 10/10/2005 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 4/26/2005 | 4/26/2005 | 5/20/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 8/19/2004 | 4/26/2005 | | DONE |
|
|
|
|
FIRE-Final Inspection | 8/18/2004 | 8/19/2004 | 8/19/2004 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 8/19/2004 7:36:35 AM
|
BLD-Final | 8/18/2004 | 8/19/2004 | 8/19/2004 | A | PASS |
Lane Manuel
|
|
|
mark; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
Permanent Occupancy | | 8/19/2004 | 8/19/2004 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 8/19/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10265 issued 8-19-04 to Brookstone in Boise Towne Square.
|
FIRE-Final Inspection | 8/16/2004 | 8/17/2004 | 8/17/2004 | A | FAIL |
Troy Cobbley
|
|
|
Zone 4 of the mall fire alarm zone that controls the smoke evacuation is inoperative. No inspection performed. 8/17/2004 4:03:31 PM
|
BLD-Final | 8/16/2004 | 8/17/2004 | 8/17/2004 | P | NR |
Jim Sly
|
|
|
mark ; Phone #: ###-#### Internet Inspection Request from: Annette Moore Need all trade, and Fire finals. 8/17/2004 4:24:48 PM
|
FIRE-Final Inspection | 8/6/2004 | 8/9/2004 | 8/9/2004 | A | CANC |
Troy Cobbley
|
|
|
Contractor was not ready for inspection. I did notify him of two deficiancies I noticed. One being the smoke detector at the main entrance is overspaced. A second detector will be required and the second item is the smoke detector in the storage room needs to be mounted at the deck. 8/9/2004 3:38:15 PM
|
BLD-Final | 8/6/2004 | 8/9/2004 | 8/9/2004 | P | NR |
Lane Manuel
|
|
|
mark; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Final | 8/5/2004 | 8/6/2004 | 8/6/2004 | A | NR |
Jim Sly
|
|
|
mark; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Need all other finals...notified Contr. 8/6/2004 11:43:13 AM
|
BLD-Framing/Rough-in | 7/27/2004 | 7/27/2004 | 7/27/2004 | P | PASS |
Jim Sly
|
|
|
Mark -- ceiling grid; Phone #: ###-#### Internet Inspection Request from: Aimee Hughes Grid 7/27/2004 5:04:30 PM
|
BLD-Framing/Rough-in | 7/21/2004 | 7/22/2004 | 7/22/2004 | A | PASS |
Jim Storey
|
|
|
barry; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles hard ceilling and store front ok per plan. 7/22/2004 9:58:46 AM
|
BLD-Framing/Rough-in | 7/14/2004 | 7/15/2004 | 7/15/2004 | A | PART |
Tom Arcoraci
|
|
|
mark; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ok east rear and west side 7/15/2004 10:32:28 AM
|
Issue PAID IN FULL permit | | | 7/13/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/9/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/8/2004 | | 7/9/2004 | | PASS |
|
|
|
|
Permit Ready to Issue | | | 7/9/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/9/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/9/2004 | | DONE |
|
|
|
|
Telephone call | | | 7/9/2004 | | DONE |
|
|
|
PERMIT READY AND FEE DUE
|
Plan assigned to (R_H) | 6/1/2004 | | 7/9/2004 | | PASS |
|
|
|
7/9/2004 08:22:19 RMH - activity updated through activity BLDA022 from case BLD04-01082.
|
Routing - FIRE | 7/8/2004 | | 7/8/2004 | | PASS |
|
|
|
resubmittal acceptable.
|
Routing - PLAN CHECK | 6/23/2004 | | 7/7/2004 | | PEND |
|
|
|
Permit pending fire departments 2nd review and letter from the mall accepting the engineers attachment design. Routed to fire on 7-7-04, spoke with Elizar about getting letter on 7-6-04.
|
Plan resubmittals received | | | 7/2/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 3sets of T1.0 , T3.0 ,A1.0 , A1.1 ,M1.0 ,E2.0 , E4.0 Taken to Ron Hill....
|
Plan resubmittals received | | | 7/2/2004 | | DONE |
|
|
|
Received transmittal letter, 3 copies of structural calculations, three sets of sheets S1, S2 taken to Ron.
|
Plan Review Completed(1st rev) | | | 6/22/2004 | | FAIL |
|
|
|
failed Plan Check and Fire review.
|
Routing - FIRE | 6/17/2004 | | 6/17/2004 | | FAIL |
|
|
|
HVAC, exiting and exit hardware issues, per IBC review. Review comments faxed to architect.
|
Case Summary (BLD) | | | 6/17/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/4/2004 | | 6/17/2004 | | FAIL |
|
|
|
Faxed and mailed requirements to the architect and faxed requirements to permit express. Routed plans to the fire department on 6/17/04,
|
Routing - PUBLIC WORKS | 6/1/2004 | | 6/4/2004 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/27/2004 | | DONE |
|
|
|
|
Application received | | | 5/19/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/19/2004 | | |
|
|
|
|
Fee Review-notes | 5/19/2004 | 5/19/2004 | | | |
|
|
|
|