Third Notice BLD | 3/15/2006 | 3/15/2006 | 3/27/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 3/1/2006 | 3/1/2006 | 3/15/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 2/14/2006 | 3/1/2006 | | DONE |
|
|
|
|
BLD-Final | 2/13/2006 | 2/14/2006 | 2/14/2006 | A | PASS |
Jim Sly
|
|
|
Bruce; Phone #: ###-#### Internet Inspection Request from: Elizabeth Esong OK for Perm Occ. (:
|
FIRE-Final Inspection | 2/10/2006 | 2/13/2006 | 2/14/2006 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled. Fire doors operated correctly. Per Sam the links on the stage sides only are ok.
|
Permanent Occupancy | | 2/14/2006 | 2/14/2006 | | DONE |
|
|
|
|
Permanent occupancy | | | 2/14/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 10905 issued 2-14-06 to Centennial High School.
|
BLD-Final | 2/10/2006 | 2/13/2006 | 2/13/2006 | P | NR |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/10/2006 at 2:45:09 PM. Contact: ###-####.
|
Temporary occupancy | | | 1/20/2006 | | DONE |
|
|
|
Temp. Occ. Cert. # 5356 issued 1-20-06 to Centennial High School Performing Arts Center.
|
BLD-Final | 1/18/2006 | 1/19/2006 | 1/19/2006 | P | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 1/18/2006 at 10:13:06 AM. Contact: ###-####. OK for Temp OCC.........OK to Perm when Fire perms. ():
|
FIRE-Final Inspection | 1/18/2006 | 1/19/2006 | 1/19/2006 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with dave hanniman's permission. The two roll down fire doors are to remain closed until their operation is worked out. Provide "Fire Doors Do Not Obstruct"signs at both doors and provide occupant load signs for the three assembly areas.
|
FIRE-Final Inspection | 1/13/2006 | 1/18/2006 | 1/18/2006 | A | CANC |
Troy Cobbley
|
|
|
Duplicate inspection
|
FIRE-Final Inspection | 1/13/2006 | 1/18/2006 | 1/18/2006 | A | CANC |
Troy Cobbley
|
|
|
ran out of time for life safety inspection
|
Code Occupancy Approval | 11/2/2005 | 11/2/2005 | 11/7/2005 | P | PASS |
Carol Montgomery
|
|
|
Complies w/ CUP04-0002 Plans on site. (Addendas 1,2, & 3 dated May 14, 2005.
|
PubWorks Occupancy Approval | 11/3/2005 | 11/3/2005 | 11/3/2005 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 11/02/05. R.Rokovitz
|
Extend Permit 180 days | 11/2/2005 | 11/2/2005 | 11/2/2005 | P | CANC |
Carol Montgomery
|
|
|
|
BLD-Conference | 10/18/2005 | 10/18/2005 | 10/18/2005 | P | FAIL |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles C/N Ceiling in Auditorium not per Architects original spec.....Architect to approve "as built" auditorium ceiling.
|
BLD-Framing/Rough-in | 10/17/2005 | 10/17/2005 | 10/17/2005 | P | FAIL |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Auditorium Ceiling not per Architects specs. Waiting for Architects approval for "as built" ceiling.
|
BLD-Framing/Rough-in | 9/1/2005 | 9/1/2005 | 9/2/2005 | P | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Ceilings in small rooms OK
|
BLD-Framing/Rough-in | 8/3/2005 | 8/3/2005 | 8/3/2005 | P | CANC |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 7/28/2005 | 7/29/2005 | 7/29/2005 | A | FAIL |
Jim Sly
|
|
|
darrell ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie C/N Arch to provide detail for Auditorium ceiling
|
BLD-Framing/Rough-in | 7/27/2005 | 7/28/2005 | 7/28/2005 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 7/27/2005 at 1:07:06 PM. Provide Eng. standard for Auditorium ceiling and call for insp.
|
BLD-Other | 7/14/2005 | 7/15/2005 | 7/15/2005 | A | DEFR |
Mike Jordan
|
|
|
ross - Note: hookup roof drains to seepage beds - water test inpsect; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Framing/Rough-in | 6/22/2005 | 6/23/2005 | 6/23/2005 | A | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Barbara Moore C/N Architect to provide UL assembly for top of all 1hr rated walls to metal pan deck.
|
BLD-Framing/Rough-in | 5/31/2005 | 6/1/2005 | 6/1/2005 | A | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa Interior E. & W. Auditorium walls, Ext. eyebrows, and misc interior walls OK.
|
BLD-Framing/Rough-in | 5/26/2005 | 5/27/2005 | 5/27/2005 | A | PART |
Jim Sly
|
|
|
bruce ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Looked at all metal stud walls....Need to check Eng for bracing later when time allows.
|
BLD-Framing/Rough-in | 4/26/2005 | 4/27/2005 | 4/27/2005 | A | PART |
Tom Arcoraci
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Barbara Moore hard lids in center baths ok and storage areas next to them box beams ok at front entry and rear entry furred aut framing ok at south bathroom and north office area
|
BLD-Framing/Rough-in | 4/7/2005 | 4/8/2005 | 4/8/2005 | A | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Rated Ceilings in storage rooms OK to cover. 4/8/2005 12:28:45 PM
|
BLD-Framing/Rough-in | 4/4/2005 | 4/4/2005 | 4/4/2005 | P | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Need Listed tested assembly from Architect that is do-able for 1hr ceilings in selected rooms. 4/4/2005 4:40:02 PM
|
Plan resubmittals received | | | 11/1/2004 | | DONE |
|
|
|
Received letter of transmittal with drainage calcs. and 5 sheets of C1.3 taken to Brian M per Marlene.
|
BLD-Foundation | 10/21/2004 | 10/22/2004 | 10/22/2004 | A | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Slab and stage wall.... MTI here... OK pending special insp reports and approvals. 10/22/2004 10:30:52 AM
|
BLD-Concrete | 10/12/2004 | 10/13/2004 | 10/13/2004 | A | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Footing at wall between lobby and auditorium OK pending MTI special insp tests and approvals 10/13/2004 10:09:35 AM
|
BLD-Foundation | 9/28/2004 | 9/29/2004 | 9/29/2004 | A | PART |
Jim Sly
|
|
|
BRUCE; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Pouring small Sect of wall N E corner and Sm sect foot @ S E co 9/29/2004 11:49:50 AM
|
BLD-Foundation | 9/22/2004 | 9/23/2004 | 9/23/2004 | A | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Poured most of West wall and footing... A-2 to B-2 OK pending MTI special insp and appr. 9/23/2004 11:36:24 AM
|
BLD-Footing | 9/16/2004 | 9/17/2004 | 9/17/2004 | A | PART |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Foot at West wall and 3/4 of south wall OK Pending special insp reports and appr. 9/17/2004 10:55:40 AM
|
BLD-Foundation | 9/16/2004 | 9/17/2004 | 9/17/2004 | A | NR |
Jim Sly
|
|
|
bruce; Phone #: ###-#### Internet Inspection Request from: Barbara Moore !st pour of foundation walls NR....Need extra verts on order. 9/17/2004 10:56:48 AM
|
BLD-Footing | 9/13/2004 | 9/14/2004 | 9/14/2004 | A | PART |
Jim Sly
|
|
|
bruce cell ###-####; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie MTI Doing special insp. Partial footing insp at area B OK Pending special insp testing and appr. 9/14/2004 11:12:20 AM
|
(F) Reprint permit | | | 8/25/2004 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/24/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/24/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/24/2004 | | DONE |
|
|
|
|
Telephone call | | | 8/24/2004 | | DONE |
|
|
|
permit ready and fee due
|
Issue PAID IN FULL permit | | | 8/24/2004 | | DONE |
|
|
|
|
Routing - PLANNING | 8/19/2004 | | 8/23/2004 | | PASS |
|
|
|
Ok per CUP04-02.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2004 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 6/1/2004 | | 8/23/2004 | | PASS |
Mike Otto
|
|
|
8/23/2004 15:29:04 MLO - activity updated through activity BLDA022 from case BLD04-01188.
|
Routing Off Site - STRUCTURAL | 7/29/2004 | | 8/23/2004 | | PASS |
|
|
|
Called PDQ for pick -up
|
Routing - FIRE | 8/19/2004 | | 8/19/2004 | | PASS |
|
|
|
Resubmittal acceptable.
|
Plan resubmittals received | | | 8/19/2004 | | DONE |
|
|
|
Received letter of transmittal,three fax transmittals & response with structural calcs. taken to Mike Otto.
|
Routing - PLAN CHECK | 8/10/2004 | | 8/19/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/18/2004 | | DONE |
|
|
|
Received Transmittal Letter, 1 Set of A2.02, A2.03,E2.11F Taken to Mike Otto...
|
Plan resubmittals received | | | 8/18/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 2 Sets of A1.00,A1.01,A3.02 Taken to Mike Otto...
|
Routing - Erosion and Sediment | 8/9/2004 | | 8/10/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Plan resubmittals received | | | 8/9/2004 | | DONE |
|
|
|
Received Transmittal Letter, 3 Structural Calc Booklets 2 Sets of C1.2,C1.3,C1.4,C1.5,A1.00,A1.01,A2.01,A5.01 Taken to Mike Otto....
|
Routing - PLANNING | 7/30/2004 | | 8/3/2004 | | FAIL |
|
|
|
North elevation - 4 windows removed - add windows back somewhere on this elevation for staff to review.
Site Plan - widen parking stalls to 9-feet wide and show bike rack. KG
|
Plan resubmittals received | | | 7/29/2004 | | DONE |
|
|
|
Received Transmittal Letter, 2 Structural Calc books 2 Sets of A0.02,A2.03,A5.01,A6.02,S1.0,S2.0,S2.1,S2.2,S3.0,S3.1,S3.2,S3.3,S4.1,S5.0,S5.1,S5.2,S6.0S6.1,P1.0,P2.0,P2.1,P3.0,P3.1,M1.0,M1.1,M2.0,FP1.0,E3.00...& 1 set of S1.0,S2.0,S2.1,S2.2,S3.0,S3.1,S3.2,S3.3,S4.1,S5.0,S5.1,S5.2,S6.0S6.1 Taken to Mike Otto
|
Plan Review Completed(1st rev) | | | 7/8/2004 | | FAIL |
|
|
|
failed structural, ESC, planning, plan check and fire.
|
Routing - PLAN CHECK | 7/8/2004 | | 7/8/2004 | | FAIL |
|
|
|
|
Routing - FIRE | 6/30/2004 | | 7/8/2004 | | FAIL |
|
|
|
FD access, sprinler flow, fire extinguiisher and building review resubmittal comments relating to IFC. Review faxed to architect.
|
Plan resubmittals requested | | | 6/30/2004 | | DONE |
|
|
|
IBC corrections
|
Routing Off Site - STRUCTURAL | 6/2/2004 | | 6/30/2004 | | FAIL |
|
|
|
Contacted PDQ for pickup Corrections sent to architect
|
Routing - PLAN CHECK | 6/16/2004 | | 6/30/2004 | | FAIL |
|
|
|
corrections sent to architect
|
Routing - PLUMBING | 6/16/2004 | | 6/16/2004 | | PASS |
|
|
|
1. branch drains over five feet need cleanouts(not shown on p2.0) 2. water line to concession stand needs backflow preventor as it is a seperate building.
|
Routing - PLANNING | 6/15/2004 | | 6/15/2004 | | FAIL |
|
|
|
Need bike rack, class III trees, and February 1/, 2004 colored elevations before I can approve (CUP04-02). Called Ed Daniels on 6-15-2004.
|
Routing - Erosion and Sediment | 6/14/2004 | | 6/15/2004 | | FAIL |
|
|
|
Contractor is listed as CM company. Individual listed as RP not certified by Boise City.
|
Routing - PUBLIC WORKS | 6/3/2004 | | 6/14/2004 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 6/2/2004 | | 6/2/2004 | | PASS |
|
|
|
Site is over 5 acres in size.
|
Pending Assignment by JCM | 5/29/2004 | | 6/1/2004 | | DONE |
John Menard
|
|
|
6/1/2004 07:47:07 JCM - activity updated through activity BLDA174 from case BLD04-01188.
|
Plans ACCEPTED BY PLAN TECH | | | 5/29/2004 | | DONE |
|
|
|
Took 2 Project Manuals to Mike Otto ...
|
Application received | | | 5/28/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/28/2004 | | |
|
|
|
|
Fee Review-notes | 5/28/2004 | 5/28/2004 | | | |
|
|
|
|