Letter of compliance | | | 12/10/2004 | | DONE |
|
|
|
Letter of Compliaince issued 12-10-04.
|
BLD-Final | 12/9/2004 | 12/9/2004 | 12/9/2004 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 12/9/2004 at 10:57:59 AM. Contact: ###-####.
signed card for temporary c of o.
Perm. c of o ok pending zoning/code enf. permanent occupancy approval 12/9/2004 2:04:39 PM
|
FIRE-Final Inspection | 12/7/2004 | 12/8/2004 | 12/8/2004 | P | PASS |
Troy Cobbley
|
|
|
Life safety finaled 12/8/2004 3:30:26 PM
|
Plan resubmittals received | | | 11/23/2004 | | PASS |
|
|
|
Resubmittal acceptable based on field verification of dimensions "red-lined" on plans to verify turning radius through gate to Spectrum St. Plans forwarded to Fire Inspector; permit has been issued and no additional fees apply for this plan mod. Called Primary Const and advised of approval.
|
Meeting | | | 11/18/2004 | | DONE |
|
|
|
Met with Paul, explained the turning radius problem with the proposed Plan for Modification of FD access from what was shown on issued/approved plan set. Apparently the roadway was erroneously shown on the approved plans and the inspector required a plan resubmittal to approve the actual roadway. The roadway as shown on the Modification plan lacks required turning radius. Explained what is required to Paul and gave him one plan with the required roadway turning radius penciled in for him. An option to removing part of existing curb and widening the roadway, is to re-design the roadway in any manner which meets the FD roadway requirements. He will review and resubmit revised plans. This project cannot be finaled until an approved modified plan is issued for field verification by the Fire inspector.
|
Plan resubmittals received | | | 11/10/2004 | | FAIL |
|
|
|
Plan modification dropped off 11/09 at request of FI, for approval of the modified FD access roadway which was changed in the field from the approved plans. The changed roadway does not provide required turning radius at one turn near the northern exit. Called Paul (primary contact), who dropped plans off at front desk; left voice message to call me do discuss the problem. Need to resubmit a modified plan.
|
FIRE-Final Inspection | 11/8/2004 | 11/8/2004 | 11/8/2004 | P | FAIL |
Troy Cobbley
|
|
|
Provide resubmitted site plans for the fire dept access. Roadways on plans and access from streets does not match plans. Provide signage on both access gates and atleast two signs at rear of property. 11/8/2004 2:02:22 PM
|
BLD-Framing/Rough-in | 10/12/2004 | 10/13/2004 | 10/13/2004 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 10/12/2004 at 3:23:56 PM. Contact: ###-####. wooden struc ok 10/13/2004 2:41:34 PM
|
BLD-Foundation | 9/16/2004 | 9/17/2004 | 9/17/2004 | A | CANC |
Lane Manuel
|
|
|
cory; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
insp. scheduled in error. 9/17/2004 11:09:47 AM
|
BLD-Foundation | 9/16/2004 | 9/16/2004 | 9/16/2004 | P | PASS |
Jim Storey
|
|
|
2nd lift ok ufer ground in place ok. 9/16/2004 1:58:51 PM
|
BLD-Foundation | 9/15/2004 | 9/15/2004 | 9/15/2004 | P | PART |
Lane Manuel
|
|
|
cory; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
2 ft. high section of perimeter stemwalls ok. to recall for remaining 6 ft portion of stemwall. 9/15/2004 2:11:06 PM
|
BLD-Footing | 9/9/2004 | 9/10/2004 | 9/10/2004 | P | PASS |
Jim Storey
|
|
|
cory; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
(F) Reprint permit | | | 9/8/2004 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 9/3/2004 | | DONE |
|
|
|
|
Telephone call | | | 8/25/2004 | | |
|
|
|
Left message for Russ Phillips that permit is ready but waiting for ACHD info///8/25/04 4:00pm BAM
|
Permit Ready to Issue | | | 8/25/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/18/2004 | | 8/19/2004 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/19/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/19/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/19/2004 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 6/8/2004 | | 8/19/2004 | | PASS |
John Menard
|
|
|
8/19/2004 10:39:04 JCM - activity updated through activity BLDA022 from case BLD04-01196.
|
Routing Off Site - STRUCTURAL | 8/16/2004 | | 8/19/2004 | | PASS |
|
|
|
Contacted PDQ for outside delivery for engineering. Received a fax from the consulting structural engineer approving the resubmittals. JCM
|
Routing - FIRE | 8/16/2004 | | 8/18/2004 | | PASS |
|
|
|
resubmittal acceptable
|
Routing - PLANNING Land Div | 8/18/2004 | | 8/18/2004 | | PASS |
|
|
|
Legal parcel in Ada County when annexed by Boise City.
|
Plan Reviewer's activity | | | 8/16/2004 | | PASS |
|
|
|
Plan resubmittals approved as revised. JCM
|
Routing - PLAN CHECK | 6/30/2004 | | 8/16/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/16/2004 | | DONE |
|
|
|
Received response letter with lighting compliance sheets, three copies of revised calculations, four sets of sheets A1,SO,SO.1,S1.1,S1.2 taken to John M.
|
Routing - FIRE | 6/24/2004 | | 6/29/2004 | | FAIL |
|
|
|
lack hyd locations, hyd flow and FD access. Review faxed to architect.
|
Plan Review Completed(1st rev) | | | 6/29/2004 | | FAIL |
|
|
|
failed Plan check, sructural, and Fire
|
Plan resubmittals requested | | | 6/24/2004 | | |
|
|
|
Faxed the architect a request for electrical lighting plans documentation showing compliance with the 2000 IECC for lighting. JCM
|
Routing - PLAN CHECK | 6/23/2004 | | 6/24/2004 | | FAIL |
|
|
|
|
Routing - PLUMBING | 6/18/2004 | | 6/23/2004 | | PASS |
|
|
|
1. sand and grease interceptor approved detail attache with downstream vent and sampling station 2. water line to area may require backflow protection.
|
Plan resubmittals requested | | | 6/23/2004 | | |
|
|
|
Faxed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLANNING | 6/16/2004 | | 6/18/2004 | | PASS |
|
|
|
Sarah Schafer CZC04-00097
Approved per CZC04-97.
|
Routing - Erosion and Sediment | 6/16/2004 | | 6/16/2004 | | PASS |
|
|
|
ESC approved with conditions attached to plans.
|
Routing - PUBLIC WORKS | 6/9/2004 | | 6/16/2004 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/4/2004 | | 6/14/2004 | | FAIL |
|
|
|
Contacted PDQ for out-side delivery DLD Received a comment list from the consulting structural engineer requesting revisions. JCM
|
Plans ACCEPTED BY PLAN TECH | | | 6/8/2004 | | DONE |
|
|
|
|
Application received | | | 6/1/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/1/2004 | | DONE |
|
|
|
|
Fee Review-notes | 6/1/2004 | 6/1/2004 | | | |
|
|
|
|