BLD-Final | 4/14/2005 | 4/15/2005 | 4/15/2005 | A | PASS |
Tony Young
|
|
|
fred ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
DOC - Permit Finaled | 4/15/2005 | 4/15/2005 | 4/15/2005 | A | PASS |
Tony Young
|
|
|
Finaled by inspector at 4/15/2005 11:01:19 AM
|
BLD-Conference | 4/4/2005 | 4/4/2005 | 4/4/2005 | A | CANC |
Tony Young
|
|
|
|
BLD-Conference | 3/31/2005 | 4/1/2005 | 4/1/2005 | A | PART |
Tony Young
|
|
|
fred; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
needs trades, guard rail, hillside 4/4/2005 8:03:10 AM
|
BLD-Grading Inspection | 3/30/2005 | 3/30/2005 | 3/30/2005 | | DONE |
|
|
|
Final grading and drainage approved
|
BLD-Conference | 3/28/2005 | 3/29/2005 | 3/29/2005 | A | PART |
Tony Young
|
|
|
###-#### - fred
need trades,, guardrail per code,, hillside,, etc 3/30/2005 3:53:35 PM
|
BLD-Conference | 3/28/2005 | 3/28/2005 | 3/28/2005 | P | CANC |
Tony Young
|
|
|
###-#### - fred
|
FIRE-Supply Line Flush | 3/3/2005 | 3/4/2005 | 3/4/2005 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed. 3/4/2005 4:13:39 PM
|
BLD-Other | 12/30/2004 | 1/3/2005 | 1/3/2005 | A | PASS |
Tony Young
|
|
|
Fred-sheer nail; Phone #: ###-#### Internet Inspection Request from: Jan Rice
int. shear 1/3/2005 10:22:53 AM
|
BLD-Energy code compliance | 12/17/2004 | 12/20/2004 | 12/20/2004 | A | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 12/17/2004 at 1:12:59 PM. framing corrections ok 12/20/2004 9:11:33 AM
|
FIRE-Sprinkler Rough-in | 12/17/2004 | 12/20/2004 | 12/20/2004 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler piping is ok to cover 12/20/2004 9:28:05 AM
|
BLD-Framing/Rough-in | 12/14/2004 | 12/15/2004 | 12/15/2004 | A | PART |
Dave Hannah
|
|
|
Fred; Phone #: ###-#### Internet Inspection Request from: Jan Rice ok to insulate point load at bottom of stairs north side fire blocking furred out wall nain level master bedroom and furred down for duct work in basement 12/15/2004 10:27:05 AM
|
BLD-Other | 11/22/2004 | 11/22/2004 | 11/22/2004 | P | PART |
Tony Young
|
|
|
Fred-Shear Wall; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner
exterior shear ok 11/22/2004 1:50:33 PM
|
BLD-Other | 9/29/2004 | 9/29/2004 | 9/29/2004 | P | PART |
Tony Young
|
|
|
basement floor - footings ; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Foundation | 9/23/2004 | 9/23/2004 | 9/23/2004 | P | PASS |
Troy James
|
|
|
ben; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Footing | 9/22/2004 | 9/22/2004 | 9/22/2004 | P | PART |
Tony Young
|
|
|
ben; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
missed ftg,,, wip 9/22/2004 3:33:42 PM
|
BLD-Footing | 9/20/2004 | 9/21/2004 | 9/21/2004 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 9/20/2004 at 1:01:19 PM. Contact: ###-####.
wip on garage and upper ftgs 9/21/2004 11:31:02 AM
|
BLD-Grading Inspection | 9/21/2004 | 9/21/2004 | 9/21/2004 | | DONE |
|
|
|
Footing subgrade for for garage and main level have been approved by the geotechnical engineer.
|
BLD-Foundation | 9/20/2004 | 9/20/2004 | 9/20/2004 | P | NR |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 9/20/2004 at 7:43:14 AM. Contact: ###-####.
|
BLD-Energy code compliance | 9/7/2004 | 9/7/2004 | 9/7/2004 | P | PART |
Tony Young
|
|
|
fred; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
insulation in foundation wall ok 9/8/2004 9:37:59 AM
|
BLD-Foundation | 8/26/2004 | 8/27/2004 | 8/27/2004 | P | PART |
Tony Young
|
|
|
ben; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
walls on east side,, wip 8/27/2004 3:13:21 PM
|
BLD-Footing | 8/23/2004 | 8/23/2004 | 8/23/2004 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 8/23/2004 at 6:42:49 AM. Contact: ###-####.
wip on basement ftgs on east area 8/23/2004 4:11:03 PM
|
BLD-Grading Inspection | 8/20/2004 | 8/20/2004 | 8/20/2004 | | DONE |
|
|
|
Footing subgrade for basement has been approved by the geotechnical engineer
|
BLD-Footing | 8/19/2004 | 8/20/2004 | 8/20/2004 | A | NR |
Troy James
|
|
|
ben; Phone #: ###-#### Internet Inspection Request from: Annette Moore
Needs geotech report to terry records for approval. 8/20/2004 9:28:23 AM
|
PubWorks Subgrade Approval | 6/29/2004 | 6/29/2004 | 8/20/2004 | | DONE |
|
|
|
Footing subgrade must be approved by the geotechnical engineer prior to calling for footing inspection. Call Terry Records at ###-####
|
Override - Activity Holds | | | 8/19/2004 | | |
|
|
|
|
(F) Reprint permit | | | 8/19/2004 | | DONE |
|
|
|
|
Override - Activity Holds | | | 8/19/2004 | | |
|
|
|
|
(F) Reprint permit | | | 8/19/2004 | | DONE |
|
|
|
|
Override - Activity Holds | | | 7/21/2004 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/21/2004 | | DONE |
|
|
|
|
Meeting | | | 7/21/2004 | | DONE |
|
|
|
Meeting with the home G.C. to verify fire sprinkler requirements. This is a 13D and not a modified system! Change Scope of Work by deleting "modified." Indicated an outside bell with a flow switch (usually supplied by the fire sprinkler contractor). Gave list of sprinkler contractors and indicated they will be paying for the separate permit fees.
|
Plan assigned to (DJO) | 7/16/2004 | 7/16/2004 | 7/16/2004 | | PASS |
|
|
|
|
Plan Review Report | | | 7/16/2004 | | DONE |
|
|
|
|
Override - Activity Holds | | | 7/16/2004 | | |
|
|
|
|
Permit Ready to Issue | | | 7/16/2004 | | DONE |
|
|
|
|
Pending Assignment by DJO | 6/8/2004 | | 7/16/2004 | | DONE |
Dan Overy
|
|
|
7/16/2004 13:31:01 DJO - activity updated through activity BLDA169 from case BLD04-01262.
|
Plans ACCEPTED BY PLAN CHECK | | | 7/16/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/16/2004 | | DONE |
|
|
|
|
Routing - Erosion and Sediment | 7/14/2004 | | 7/14/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - FIRE | 7/7/2004 | | 7/14/2004 | | DONE |
|
|
|
Fire Sprinklers will be required per review by D. Miller, due to FD vehicle accessibility difficulty of Ginsel St.
|
Routing - PLANNING | 7/13/2004 | | 7/14/2004 | | PASS |
|
|
|
O.K. per revised set of drawings submitted on 7/13/04. CER
|
Routing - PLANNING | 6/30/2004 | | 7/1/2004 | | FAIL |
|
|
|
Spoke w/ Fred Slait, requested a site plan to scale so we can begin our review. 9:45 a.m. 7/1/04 CER
|
Routing - PLANNING Land Div | 6/30/2004 | | 6/30/2004 | | PASS |
|
|
|
Approved in Ada County prior to annexation.
|
Routing - PLANNING Land Div | 6/18/2004 | | 6/24/2004 | | FAIL |
|
|
|
Need to verify legal land division. Called Fred Slaight on June 24, 2004.
|
Routing - PUBLIC WORKS GRADING | 6/17/2004 | | 6/17/2004 | | PASS |
Rita DeYoung
|
|
|
Grading and drainage approved with conditions of approval in letter from Boise Public Works attached to plans.
|
Routing - PUBLIC WORKS | 6/17/2004 | | 6/17/2004 | | PASS |
|
|
|
NORTHWEST BOISE SEWER DISTRICT
|
Routing - PUBLIC WORKS GRADING | 6/8/2004 | | 6/10/2004 | | FAIL |
Rita DeYoung
|
|
|
Footing subgrade not 2 feet below grade
|
Application received | | | 6/8/2004 | | |
|
|
|
|
Routing - PLAN CHECK | 7/14/2004 | | | | |
|
|
|
|