Third Notice BLD | 5/20/2005 | 5/20/2005 | 12/14/2005 | | DONE |
|
|
|
Second Notice has not been responded to.///Per Jenifer & Rita sign off 2004 permits
|
Second Notice BLD | 4/26/2005 | 4/26/2005 | 5/20/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 9/22/2004 | 4/26/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/22/2004 | | DONE |
|
|
|
Perm. Occ. Cert. # 10301 issued 9-22-04 to McDonald's at the airport.
|
Permanent Occupancy | | 9/21/2004 | 9/21/2004 | | DONE |
|
|
|
|
BLD-Final | 9/20/2004 | 9/21/2004 | 9/21/2004 | P | PASS |
Jim Storey
|
|
|
rod; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles final ok 9/21/2004 4:17:52 PM
|
Temporary occupancy | | | 9/21/2004 | | DONE |
|
|
|
Temp. Occ. Cert. # 5141 issued 9-21-04 to McDonald's at the airport.
|
FIRE-Final Inspection | 9/17/2004 | 9/17/2004 | 9/17/2004 | P | PASS |
Rick Jackson
|
|
|
|
BLD-Conference | 8/31/2004 | 9/1/2004 | 9/1/2004 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/31/2004 at 6:15:09 AM. wip 9/1/2004 9:56:12 AM
|
BLD-Foundation | 8/23/2004 | 8/23/2004 | 8/23/2004 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/23/2004 at 7:25:45 AM. framing ok 8/24/2004 9:52:34 AM
|
BLD-Other | 8/18/2004 | 8/19/2004 | 8/19/2004 | A | PASS |
Tom Arcoraci
|
|
|
ROD ; Phone #: ###-#### Internet Inspection Request from: Annette Moore floor sinks ok 8/19/2004 9:31:43 AM
|
FIRE-Conference | 8/11/2004 | 8/12/2004 | 8/12/2004 | A | PART |
Rick Jackson
|
|
|
rod ; Phone #: ###-#### Internet Inspection Request from: Annette Moore Met with Rod about placement of manual pulls for Ansul systems; will be located at exit hallway 10 - 20 ft from hoods and will have signs indicating systems covered 8/12/2004 10:39:05 AM
|
Issue PAID IN FULL permit | | | 7/27/2004 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 6/17/2004 | | 7/13/2004 | | PASS |
Carl Westfall
|
|
|
7/13/2004 14:05:16 CJW - activity updated through activity BLDA022 from case BLD04-01269.
|
Routing - FIRE | 7/7/2004 | | 7/13/2004 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 7/13/2004 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/13/2004 | | 7/13/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/13/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/13/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/13/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/13/2004 | | DONE |
|
|
|
|
Telephone call | | | 7/13/2004 | | DONE |
|
|
|
permit ready and fee due
|
Routing - PLAN CHECK | 6/23/2004 | | 7/7/2004 | | PASS |
|
|
|
IBC plan review started July 7, 2004 and was finished the same day. The drawings were approved with clarifications. See the plan review report. A copy was E-mailed to the architect.
|
Routing - PLUMBING | 6/22/2004 | | 6/23/2004 | | PASS |
|
|
|
coffee machine and soda dispenser will require seperate RPBF devices
|
Routing - PUBLIC WORKS | 6/17/2004 | | 6/22/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/16/2004 | | DONE |
|
|
|
Received Transmittal Letter... Taken to Carl Westfall
|
Plans ACCEPTED BY PLAN TECH | | | 6/15/2004 | | DONE |
|
|
|
Plans not stamped & signed by Central District Health Department Bob Meyer attached his sheet. No Envelope Compliance
|
Application received | | | 6/8/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/8/2004 | | DONE |
|
|
|
|
Fee Review-notes | 6/8/2004 | 6/8/2004 | | | |
|
|
|
|