PubWorks Occupancy Approval | 1/28/2008 | 1/28/2008 | 1/11/2008 | | DONE |
|
|
|
Project complete.
|
Second Notice BLD | 12/5/2005 | 12/5/2005 | 12/16/2005 | | DONE |
|
|
|
First Notice has not been responded to.///Signed off 2004 permit per Jenifer & Rita
|
First Notice | | 9/30/2005 | 12/5/2005 | | DONE |
|
|
|
|
BLD-Final | 9/29/2005 | 9/30/2005 | 9/30/2005 | A | PASS |
Dave Hannah
|
|
|
Kent, ###-####
|
Letter of compliance | | | 9/30/2005 | | DONE |
|
|
|
Letter of Compliance issued 9-30-05.
|
Temporary occupancy | | | 7/20/2005 | | DONE |
|
|
|
Temp. Occ. Cert. # 5257 issued 7-20-05 to the Riverfront Plaza bldg.
|
BLD-Final | 7/15/2005 | 7/18/2005 | 7/18/2005 | P | PART |
Tony Young
|
|
|
kent; Phone #: ###-#### Internet Inspection Request from: Barbara Moore temp. occ ok
|
FIRE-Final Inspection | 7/18/2005 | 7/18/2005 | 7/18/2005 | P | PASS |
Forrest France
|
|
|
Fire life safety passed inspection.
|
BLD-Final | 7/14/2005 | 7/15/2005 | 7/15/2005 | P | NR |
Dave Hannah
|
|
|
kent; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
FIRE-Final Inspection | 7/15/2005 | 7/15/2005 | 7/15/2005 | P | FAIL |
Forrest France
|
|
|
Provide curb painting for fire dept. access as shown on plans and per discussion, repair exit sign 2nd floor corridor.
|
BLD-Other | 6/29/2005 | 6/30/2005 | 6/30/2005 | A | FAIL |
Dave Hannah
|
|
|
kent - Note: ceiling cover; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles needs more wires on south side of lobby
|
Plan Reviewer's activity | | | 6/30/2005 | | DONE |
|
|
|
Received letters from Cornel Larson Architects and United Water John Lee, confirming the additional fire hydrant and the 12" in-line isolation valve (allowing the sprinkler system to be isolated from the new fire hydrant in the event of a main failure) have been installed. Satisfactory flushing of the UG was witnessed by F. France on 6/16/2005. Letters sent to Records to be scanned into permit doc's.
|
BLD-Framing/Rough-in | 6/17/2005 | 6/17/2005 | 6/20/2005 | P | PART |
Dave Hannah
|
|
|
kent///cover inspection; Phone #: ###-#### Internet Inspection Request from: Barbara Moore ceilings in stair towers ok to cover
|
BLD-Framing/Rough-in | 6/14/2005 | 6/15/2005 | 6/15/2005 | A | PASS |
Dave Hannah
|
|
|
KENT NOTE: COVER; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok to cover
|
BLD-Concrete | 10/22/2004 | 10/26/2004 | 10/26/2004 | P | PART |
Dave Hannah
|
|
|
tony - Note; checking for mess and before pour; pouring slab before wed morn Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Footing | 10/22/2004 | 10/25/2004 | 10/25/2004 | A | FAIL |
Dave Hannah
|
|
|
tony; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles needs mti to sign off soils 10/25/2004 11:01:43 AM
|
Issue PAID IN FULL permit | | | 9/24/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/23/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/23/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/23/2004 | | DONE |
|
|
|
|
Telephone call | | | 8/23/2004 | | DONE |
|
|
|
permit ready and fee due//waiting for achd fee assessment
|
Routing - PLAN CHECK | 8/5/2004 | | 8/23/2004 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 6/30/2004 | | 8/23/2004 | | PASS |
|
|
|
8/23/2004 09:28:51 JCM - activity updated through activity BLDA022 from case BLD04-01429.
|
Plan resubmittals requested | | | 8/19/2004 | | |
|
|
|
Faxed the architect a copy of the comment list from the consulting structural engineer requesting additional calculations.
|
Routing Off Site - STRUCTURAL | 8/6/2004 | | 8/18/2004 | | FAIL |
|
|
|
Sent 8/3/04 resubs to outside engineer for review on this date. MYS Received comment list from consulting structural engineer requesting additional calculations. JCM
|
Plan resubmittals received | | | 8/9/2004 | | DONE |
|
|
|
Received transmittal with one set of sheets A-9,A-8,A-6,A-13 taken to John M.
|
Routing - FIRE | 8/3/2004 | | 8/5/2004 | | PASS |
Bill Alexander
|
|
|
|
Plan resubmittals received | | | 8/3/2004 | | DONE |
|
|
|
Received response letter two copies of structural calcs. two copies of sheets A-5,A-6,A-8,A-9,A-13, taken to John M.
|
Routing - PLAN CHECK | 7/27/2004 | | 8/3/2004 | | |
|
|
|
|
Plan resubmittals received | | | 7/30/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 2 Sets of 0, E-4,E-5, FP-1.1 Taken to John Menard
|
Plan Reviewer's activity | | | 7/27/2004 | | PASS |
|
|
|
Reviewed and approved resubmitted plan sheets. JCM
|
Routing - PLAN CHECK | 7/27/2004 | | 7/27/2004 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 7/27/2004 | | 7/27/2004 | | PASS |
|
|
|
Approved. Received Recorded Notice of Buildable Parcel and new tax parcel number and deed.
|
Plan Review Completed(1st rev) | | | 7/26/2004 | | FAIL |
|
|
|
failed Planning Land Div, Plan check, Structural and Fire.
|
Routing - FIRE | 7/21/2004 | | 7/26/2004 | | FAIL |
|
|
|
lacks water flow info for fire hydrants and srpinkler design. Review faxed to architect.
|
Plan resubmittals received | | | 7/24/2004 | | DONE |
|
|
|
Received response letter, three copies of sheets A-2,A-3,A-11,A-12 taken to John M.
|
Routing Off Site - STRUCTURAL | 7/21/2004 | | 7/21/2004 | | FAIL |
|
|
|
Called PDQ for pick-up
|
Plan resubmittals requested | | | 7/21/2004 | | |
|
|
|
Mailed the architect a copy of the comment list requesting revisions. JCM
|
Routing - PLAN CHECK | 7/21/2004 | | 7/21/2004 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 7/20/2004 | | DONE |
|
|
|
Received Transmittal Letter, 3 Structural calcs, 3 Sets of S-0, S-4, S-5, S-6,S-7, S-8, S-15, S-16 Taken to John Menard
|
Routing - PLUMBING | 7/15/2004 | | 7/20/2004 | | PASS |
|
|
|
INCREASE WATER PIPING AT RESTROOM BRANCH TO 2" TO 1ST WC BRANCH, VERIFY THERMOL EXPANTION TANK LOCATION WITH MANUFACTURER, IF AN AUTOMATIC SOAP DISPENSOR IS INSTALLED AT THE MOP SINKS PROVIDE A WATER SUPPLY FOR THEM.
|
Routing - PLANNING | 7/13/2004 | | 7/15/2004 | | PASS |
|
|
|
Approved per DRH03-227. Approved Mark Pecchenino for CU sign-off.
|
Plan resubmittals requested | | | 7/13/2004 | | |
|
|
|
Faxed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - Erosion and Sediment | 7/12/2004 | | 7/13/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 7/7/2004 | | 7/12/2004 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/30/2004 | | 7/12/2004 | | FAIL |
|
|
|
Called PDQ for pick - up.... DLD Received a faxed comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLANNING Land Div | 6/30/2004 | | 7/6/2004 | | FAIL |
|
|
|
Need to complete ROS03-00077. Called Cornel Larson for new site plans, called Cary Davis and called Pat Tealey.
|
Plans ACCEPTED BY PLAN TECH | | | 6/30/2004 | | DONE |
|
|
|
Envelop Compliance not signed , No ESC narrative.
|
Plan routing begun/NEW & ADDTN | | | 6/30/2004 | | DONE |
|
|
|
|
Application received | | | 6/28/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/28/2004 | | DONE |
|
|
|
|
Fee Review-notes | 6/28/2004 | 6/28/2004 | | | |
|
|
|
|