Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD04-01476
StatusFinaled
Name ROBERT R COOPER
Site Address 3098 N FIVE MILE RD
Project NameMEDALLION BLDG #3
Customer Number 
ePlanReviewNo
Description
(COMMUNITY PARTNERSHIPS)(MEDALLION BLDG #3) To construct a 1,201 sq.ft. office in the northeast corner of the building per approved plans. Work to include, construction of an accessible restroom, new interior partitions, installation of suspended ceiling system, new lighting, and Hvac ducting. Miscelaneous related interior finishes. (pc#421-04) rmh
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD12/7/200512/7/200512/14/2005 DONE
Second Notice has not been responded to.///singed off 2004 permit per Jenifer & Rita
Second Notice 5/20/200512/7/2005 DONE
First Notice 10/14/20044/26/2005 DONE
Permanent occupancy  10/14/2004 DONE
Perm. Occ. Cert. # 10328 issued 10-14-04 to Community Partnerships.
Permanent Occupancy 10/5/200410/5/2004 DONE
Details
FIRE-Final Inspection10/4/200410/5/200410/5/2004APASS
DetailsTroy Cobbley
Fire life safety finaled 10/5/2004 9:20:29 AM
BLD-Final10/4/200410/5/200410/5/2004PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 10/4/2004 at 2:16:24 PM. Contact: ###-####. 10/5/2004 6:16:43 PM OK for Perm Occ. :) 10/5/2004 6:17:15 PM 10/5/2004 6:17:38 PM
FIRE-Final Inspection9/30/200410/1/200410/1/2004AFAIL
DetailsTroy Cobbley
Provide annual inspection for the fire extinguisher. See review note #2. Install door hardware so compliance can be verified. See review note #4. Provide verification to inspector that cfm rating for hvac unit. See note #17 for hvac shutdown requirements. Test emergency lights for inspector. 10/1/2004 8:51:38 AM
BLD-Final9/30/200410/1/200410/1/2004PNR
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/30/2004 at 3:19:54 PM. Contact: ###-####. Need fire. 10/1/2004 4:06:04 PM
BLD-Framing/Rough-in9/2/20049/3/20049/3/2004APASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 9/2/2004 at 1:04:44 PM. Contact: ###-####.
Issue PAID IN FULL permit  8/19/2004 DONE
Permit Ready to Issue  8/18/2004 DONE
Inspection Record Card- Bld  8/18/2004 DONE
Print Occupancy Form  8/18/2004 DONE
Telephone call  8/18/2004 DONE
Left message for Sam that permit is ready & fees///8/18/04 11:30am BAM
Routing - PLAN CHECK7/19/2004 8/17/2004 PASS
Plan resubmittals received  8/17/2004 DONE
Received Transmittal Letter, & 2 Sets of M2.0,A2.0,A7.0,M1.0, Taken to Ron Hill....
PLANS/APPL TAKEN TO FRONT DESK  8/17/2004 DONE
Plan assigned to (R_H)7/9/2004 8/17/2004 PASS
8/17/2004 13:10:16 RMH - activity updated through activity BLDA022 from case BLD04-01476.
Routing - FIRE7/15/2004 7/19/2004 PASS
Plan resubmittals requested  7/19/2004 DONE
In response to a fax from L. Bremmeyer requiresting I call to discuss the Haz Mat issues further, I faxed him a letter indicating I cannot deal with this issue further until they submit the HM information as required in our review comments.
Plan Review Completed(1st rev)  7/19/2004 FAIL
failed plan check
Routing - PLAN CHECK7/14/2004 7/15/2004 FAIL
Faxed and mailed requirements to the architect on 7/14/04, routed plans to the fire department on 7/15/04.
Routing - PUBLIC WORKS7/9/2004 7/14/2004 PASS
Plans ACCEPTED BY PLAN TECH  7/8/2004  
No Mechanical or Envelop Compliance
Application received  7/2/2004  
Recd Pcfee & Taken To Pln CK  7/2/2004 DONE
Fee Review-notes7/2/20047/2/2004