Case Summary (BLD) | | | 8/15/2014 | | DONE |
Tisha Gallop
|
|
|
|
FIRE-Final Inspection | 2/15/2005 | 2/16/2005 | 2/16/2005 | A | PASS |
Troy Cobbley
|
|
|
Life safety finaled 2/16/2005 10:42:01 AM
|
BLD-Final | 2/15/2005 | 2/16/2005 | 2/16/2005 | P | PASS |
Tom Arcoraci
|
|
|
###-#### - scott lc issued 2/16/2005 2:44:58 PM
|
DOC - Permit Finaled | 2/16/2005 | 2/16/2005 | 2/16/2005 | P | PASS |
Tom Arcoraci
|
|
|
Finaled by inspector at 2/16/2005 2:45:07 PM
|
FIRE-Final Inspection | 1/7/2005 | 1/10/2005 | 1/10/2005 | A | FAIL |
Troy Cobbley
|
|
|
###-#### - scott Provide approved door hardware on both the south and the north facing exit doors. One door can have keyed hardware on the egress side. See review note #4. Provide sticker at the keyed door. Remove the manual flush bolts on these same doors. Emergency lighting not required per Dan Stuart. 1/10/2005 11:10:01 AM
|
BLD-Final | 1/3/2005 | 1/3/2005 | 1/3/2005 | P | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/3/2005 at 10:44:36 AM. Contact: ###-####. needs all sign offs 1/3/2005 2:37:18 PM
|
BLD-Framing/Rough-in | 10/27/2004 | 10/27/2004 | 10/27/2004 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 10/27/2004 at 8:20:53 AM. ok to cover int walls 10/27/2004 2:59:25 PM
|
Issue PAID IN FULL permit | | | 8/16/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/13/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/13/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/11/2004 | | 8/12/2004 | | PASS |
|
|
|
To permit desk to issue.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/12/2004 | | PASS |
|
|
|
Ready to issue.
|
Plan assigned to (DRS) | 7/14/2004 | | 8/12/2004 | | PASS |
|
|
|
8/12/2004 13:08:03 DRS - activity updated through activity BLDA022 from case BLD04-01522.
|
Routing - FIRE | 8/5/2004 | | 8/11/2004 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 8/11/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/5/2004 | | DONE |
|
|
|
Received transmittal record, with two response letters, and one set of sheets D-1D-2,D-3,E-1 taken to Dan S.
|
Routing - PLANNING | 8/3/2004 | | 8/5/2004 | | PASS |
|
|
|
Approve
|
Routing - PUBLIC WORKS | 8/3/2004 | | 8/3/2004 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 8/3/2004 | | 8/3/2004 | | PASS |
|
|
|
Request for waiver from ESC plan approved.
|
Routing - PLAN CHECK | 7/14/2004 | | 8/2/2004 | | PEND |
|
|
|
Routing to Planning for review.
|
Plans ACCEPTED BY PLAN TECH | | | 7/12/2004 | | DONE |
|
|
|
No Envelope Compliance Sheet
|
Application received | | | 7/8/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/8/2004 | | DONE |
|
|
|
|
Fee Review-notes | 7/8/2004 | 7/8/2004 | | | |
|
|
|
|