Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD04-01638
StatusFinaled
Name BRS ARCHITECTS
Site Address 10062 W FAIRVIEW AVE
Project NameFAIRVIEW OFFICE PARK BLD# 1
Customer Number 
ePlanReviewNo
Description
FAIRVIEW OFFICE PARK BLD# 1 * Shell Only* To construct a 4,140 sq. ft. one story Type VB office shell building. Other work inlcudes all site improvements and landscaping per approved plans and attachments. No occupancy is authorized by this permit. Separate permits and plans are required to complete each tenant space. Energy compliance for HVAC and Lighting will be with tenant improvement permits
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Framing/Rough-in4/12/20054/12/20054/12/2005PPASS
DetailsJim Sly
terry ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie FINAL PASS 4/12/2005 2:00:21 PM
Letter of compliance  4/12/2005 DONE
Letter of Compliance issued 4-12-05
BLD-Framing/Rough-in4/6/20054/7/20054/7/2005AFAIL
DetailsJim Sly
terry; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Should be final Need plumb final. 4/7/2005 12:14:04 PM
FIRE-Final Inspection3/30/20053/31/20053/31/2005APASS
DetailsTroy Cobbley
Fire life safety passed. 3/31/2005 8:39:24 AM
BLD-Final3/30/20053/31/20053/31/2005PNR
DetailsJim Sly
terry; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Framing/Rough-in3/30/20053/30/20053/30/2005PCANC
DetailsJim Sly
terry; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Inspection cancelled from web by: Marsha Smylie
Code Occupancy Approval3/30/20053/30/20053/30/2005APASS
DetailsCarol Montgomery
Meets compliance with DR 3/30/2005 9:52:25 AM
Inspection Record Card- Bld  3/30/2005 DONE
FIRE-Sprinkler Rough-in3/22/20053/22/20053/22/2005PFAIL
DetailsTroy Cobbley
Provide exit discharge lighting, provide additional addressing as discussed and paint curbing as per sheet E1.0 3/22/2005 3:27:16 PM
BLD-Conference3/4/20053/7/20053/7/2005APASS
DetailsJim Sly
Terry; Phone #: ###-#### Internet Inspection Request from: Jan Rice Talked about Req for Shell/Core final. Would like to complete Energy code (for shell) at each separate T I 3/7/2005 10:20:40 AM 3/7/2005 10:29:04 AM
BLD-Wall cover12/2/200412/3/200412/3/2004APART
DetailsLane Manuel
Keith -Wall & roof; Phone #: ###-#### Internet Inspection Request from: Jan Rice
roof/shear nailing ok. 12/3/2004 10:24:50 AM
BLD-Framing/Rough-in11/2/200411/2/200411/2/2004PPART
DetailsJim Sly
terry///shear wall inspection; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Shear wall OK up to 8' only. 11/2/2004 2:03:58 PM
BLD-Foundation10/13/200410/14/200410/14/2004PPASS
DetailsJim Sly
terry Note: Midafternoon (around 1:00); Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
BLD-Footing10/11/200410/11/200410/11/2004PPASS
DetailsJim Sly
terry -; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Letter from Stapley Eng..... 2500 PSI design strength 10/11/2004 4:28:50 PM
(F) Reprint permit  9/29/2004  
Issue PAID IN FULL permit  9/28/2004 DONE
Permit Ready to Issue  9/27/2004 DONE
Telephone call  9/27/2004 DONE
talked to andrew davis at ###-#### that permit is ready
Routing - PLUMBING9/23/2004 9/24/2004 PASS
approved per plan and 2003 UPC
PLANS/APPL TAKEN TO FRONT DESK  9/24/2004 DONE
Plan assigned to (MLO)7/28/2004 9/24/2004 PASS
9/24/2004 15:07:25 MLO - activity updated through activity BLDA022 from case BLD04-01638.
Routing - PLANNING9/20/2004 9/21/2004 PASS
Approved per DRH00-00248 MOD #1, and per letter in D.R. file from Andrew Davis regarding h.c. parking.
Routing - PUBLIC WORKS9/13/2004 9/20/2004 PASS
Plan resubmittals received  9/16/2004 DONE
Received letter of transmittal with two SD-1 sheets taken to Mike Otto.
Routing - PLAN CHECK9/10/2004 9/13/2004 PASS
Plan resubmittals received  9/10/2004 DONE
sheets G-1, A3.1, A3.2, A3.3, M0.0
Routing - FIRE8/20/2004 8/25/2004 PASS
Plan Review Completed(1st rev)  8/25/2004 FAIL
failed planning, plan check, plumbing and public works
Routing - PLAN CHECK8/25/2004 8/25/2004 PEND
Plan resubmittals requested  8/20/2004 FAIL
IBC and IECC corrections
Routing - PLAN CHECK8/12/2004 8/20/2004 FAIL
faxed and mailed corrections to architect
Routing - PLANNING8/11/2004 8/12/2004 FAIL
Plans do not comply with Design Review, DRH00-248 Mod. #1, conditions, specifically condition 1d, which requires two accessible parking spaces for the proposed office development.
Routing - PLUMBING8/9/2004 8/11/2004 FAIL
water services from meter to vault do not match services from vault to building, increase roof drainage lines at the point they tie together to 4", please resubmit a revised site plan.
Routing - PUBLIC WORKS7/28/2004 8/9/2004 FAIL
Needs Geotech report per Brian Murphy.
Routing - Erosion and Sediment8/9/2004 8/9/2004 PASS
ESC plan approved with attached conditions.
Routing - PLANNING Land Div7/28/2004 7/28/2004 PASS
Lot 5, Knudsen Square Subdivision
Print Pending Permit.LaserJet4  7/28/2004 DONE
Plan routing begun/NEW & ADDTN  7/28/2004 DONE
Plans ACCEPTED BY PLAN TECH  7/27/2004 DONE
Mechanical envelope not signed and electrical sheets only stamped not signed.
Application received  7/21/2004  
Recd Pcfee & Taken To Pln CK  7/21/2004 DONE
Fee Review-notes7/21/20047/21/2004