Third Notice BLD | 9/22/2008 | 9/22/2008 | 4/3/2009 | | DONE |
Alexandra L. DeYoung
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 8/11/2008 | 8/11/2008 | 9/22/2008 | | DONE |
Cathy Brown
|
|
|
First Notice has not been responded to.
|
First Notice | 4/15/2008 | 4/15/2008 | 8/11/2008 | | DONE |
Tom Arcoraci
|
|
|
|
DOC - Permit Finaled | 4/15/2008 | 4/15/2008 | 4/15/2008 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 2/18/2008 | 2/18/2008 | 2/19/2008 | | PASS |
Tom Arcoraci
|
|
|
|
Plan resubmittals received | | | 12/21/2007 | | |
|
|
|
Received 1 cover transmittal, 1 copy of (3 Pgs) letter from HDR dated 12/10/07, 1 copy (5 pgs) of RFI #0154, 1 copy of MTI report dated 12/7/07, 1 copy of owners acceptance of nonconforming work & RFI #1119.1 and taken to Tom Arcoraci's inbox///12/21/07 @ 12:25pm BAS
|
BLD-Aging Inspection | 12/19/2007 | 12/19/2007 | 12/19/2007 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 10/19/2007 | 10/19/2007 | 10/19/2007 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 8/17/2007 | 8/17/2007 | 8/17/2007 | | CANC |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 6/11/2007 | 6/11/2007 | 6/18/2007 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 4/10/2007 | 4/10/2007 | 4/10/2007 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 1/16/2007 | 1/16/2007 | 1/16/2007 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 11/15/2006 | 11/15/2006 | 11/15/2006 | | PASS |
Tom Arcoraci
|
|
|
wip
|
BLD-Aging Inspection | 9/13/2006 | 9/13/2006 | 9/13/2006 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 7/10/2006 | 7/10/2006 | 7/10/2006 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 3/3/2006 | 3/3/2006 | 3/6/2006 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 12/26/2005 | 12/26/2005 | 12/27/2005 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 10/24/2005 | 10/24/2005 | 10/24/2005 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 8/22/2005 | 8/22/2005 | 8/22/2005 | | PASS |
Tom Arcoraci
|
|
|
wip
|
BLD-Aging Inspection | 6/22/2005 | 6/22/2005 | 6/22/2005 | | NR |
Tom Arcoraci
|
|
|
wip
|
Plan resubmittals received | | | 6/15/2005 | | |
|
|
|
Received (2) copies of sheet PP-10FB-4. Routed to Lee R.
|
BLD-Foundation | 4/8/2005 | 4/11/2005 | 4/11/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/8/2005 at 10:26:06 AM. Contact: ###-####.
|
BLD-Foundation | 4/6/2005 | 4/7/2005 | 4/7/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 4/6/2005 at 12:39:06 PM. Contact: ###-####.
|
BLD-Footing | 4/7/2005 | 4/7/2005 | 4/7/2005 | P | PART |
Tom Arcoraci
|
|
|
|
BLD-Foundation | 3/28/2005 | 3/30/2005 | 3/30/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/28/2005 at 10:40:23 AM. Contact: ###-####.
|
BLD-Foundation | 3/28/2005 | 3/29/2005 | 3/29/2005 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/28/2005 at 10:39:38 AM. Contact: ###-####.
|
BLD-Foundation | 3/21/2005 | 3/22/2005 | 3/22/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/21/2005 at 5:03:52 PM. Contact: ###-####.
|
BLD-Foundation | 3/14/2005 | 3/15/2005 | 3/15/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/14/2005 at 9:16:10 AM. Contact: ###-####.
|
BLD-Foundation | 3/10/2005 | 3/11/2005 | 3/11/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/10/2005 at 11:02:27 AM. Contact: ###-####.
|
BLD-Foundation | 3/11/2005 | 3/11/2005 | 3/11/2005 | P | PART |
Tom Arcoraci
|
|
|
|
BLD-Footing | 2/17/2005 | 2/18/2005 | 2/18/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/17/2005 at 8:54:44 AM. Contact: ###-####.
|
BLD-Footing | 2/10/2005 | 2/11/2005 | 2/11/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/10/2005 at 9:34:59 AM. Contact: ###-####.
|
BLD-Foundation | 2/10/2005 | 2/11/2005 | 2/11/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/10/2005 at 9:35:34 AM. Contact: ###-####.
|
BLD-Footing | 1/31/2005 | 2/2/2005 | 2/2/2005 | A | PART |
Tom Arcoraci
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
BLD-Footing | 1/31/2005 | 2/1/2005 | 2/1/2005 | A | PART |
Tom Arcoraci
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 1/31/2005 | | |
|
|
|
per rita
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 1/31/2005 | | |
|
|
|
|
Override - Parcel Holds | | | 1/31/2005 | | |
|
|
|
|
BLD-Footing | 1/18/2005 | 1/19/2005 | 1/19/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/18/2005 at 2:22:16 PM. wip 1/19/2005 4:34:46 PM
|
BLD-Foundation | 1/11/2005 | 1/12/2005 | 1/12/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/11/2005 at 1:44:50 PM.
|
BLD-Footing | 1/7/2005 | 1/10/2005 | 1/10/2005 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/7/2005 at 5:12:44 PM. Contact: ###-####.
|
BLD-Foundation | 1/7/2005 | 1/10/2005 | 1/10/2005 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/7/2005 at 5:13:21 PM. Contact: ###-####.
|
BLD-Foundation | 1/4/2005 | 1/4/2005 | 1/4/2005 | P | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 1/4/2005 at 9:07:22 AM. Contact: ###-####. 1/5/2005 8:47:01 AM
|
BLD-Footing | 12/29/2004 | 12/29/2004 | 12/29/2004 | P | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/29/2004 at 10:09:34 AM. Contact: ###-####. spec in sp 12/29/2004 4:00:24 PM
|
BLD-Footing | 12/20/2004 | 12/22/2004 | 12/22/2004 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/20/2004 at 11:00:00 AM. Contact: ###-####.
|
BLD-Footing | 12/13/2004 | 12/14/2004 | 12/14/2004 | A | PASS |
Tom Arcoraci
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie mti on site 12/14/2004 10:06:46 AM
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 12/13/2004 | | |
|
|
|
needed an insp but will call the achd to see when the 30 day is expired
|
BLD-Footing | 12/10/2004 | 12/10/2004 | 12/10/2004 | P | PASS |
Tom Arcoraci
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Jan Rice 12/10/2004 4:05:36 PM
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 12/10/2004 | | |
|
|
|
|
BLD-Foundation | 11/18/2004 | 11/22/2004 | 11/22/2004 | P | PASS |
Tom Arcoraci
|
|
|
mike; Phone #: ###-#### Internet Inspection Request from: Barbara Moore mti on site 11/22/2004 3:01:21 PM
|
BLD-Footing | 11/15/2004 | 11/19/2004 | 11/19/2004 | A | PART |
Tom Arcoraci
|
|
|
per tom a. ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie wip 11/19/2004 10:48:19 AM
|
BLD-Footing | 11/15/2004 | 11/18/2004 | 11/18/2004 | A | PART |
Tom Arcoraci
|
|
|
per tom a. ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie wip 11/18/2004 10:55:05 AM
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 11/18/2004 | | |
|
|
|
this is for a foundation inspection
|
BLD-Footing | 11/15/2004 | 11/17/2004 | 11/17/2004 | A | PASS |
Tom Arcoraci
|
|
|
per tom a. ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie wip 11/17/2004 10:19:37 AM
|
BLD-Footing | 11/15/2004 | 11/16/2004 | 11/16/2004 | A | PASS |
Tom Arcoraci
|
|
|
per tom a. ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie wip ok mti on site 11/16/2004 10:36:52 AM
|
BLD-Footing | 11/15/2004 | 11/16/2004 | 11/16/2004 | A | PASS |
Tom Arcoraci
|
|
|
Mike; Phone #: ###-#### Internet Inspection Request from: Jan Rice wip mti on site 11/16/2004 10:36:22 AM
|
BLD-Footing | 11/15/2004 | 11/15/2004 | 11/15/2004 | P | PART |
Tom Arcoraci
|
|
|
per tom a. ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 11/15/2004 | | |
|
|
|
per tom arcoraci set up insp
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 11/15/2004 | | |
|
|
|
setting up insp for tom arcoraci
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 11/15/2004 | | |
|
|
|
General contractor has told him he has an OK
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 11/15/2004 | | |
|
|
|
per tom a.
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 11/15/2004 | | |
|
|
|
per tom a. set up insp
|
Override - Condition Holds | 1/1/1900 | 1/1/1900 | 11/15/2004 | | |
|
|
|
per tom a.
|
Override - Condition Holds | | | 11/12/2004 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/12/2004 | | DONE |
|
|
|
|
Plan assigned to (JCM) | 7/28/2004 | | 11/4/2004 | | PASS |
|
|
|
11/4/2004 10:40:30 JCM - activity updated through activity BLDA022 from case BLD04-01671.
|
Routing - PLAN CHECK | 10/8/2004 | | 11/4/2004 | | |
|
|
|
|
Routing - PLANNING Land Div | 11/4/2004 | | 11/4/2004 | | PASS |
|
|
|
Approved received recorded deed for Parcel A.
|
Routing - PLAN CHECK | 11/4/2004 | | 11/4/2004 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/4/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/4/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/4/2004 | | DONE |
|
|
|
|
Telephone call | | | 11/4/2004 | | DONE |
|
|
|
left mess for jim fisher at ###-#### is ready
|
Routing Off Site - STRUCTURAL | 10/18/2004 | | 10/21/2004 | | PASS |
|
|
|
Contacted PDQ for outside delivery - Received letter from cosulting structural engineer approving the last resubmittals. JCM
|
Plan Reviewer's activity | | | 10/21/2004 | | DONE |
|
|
|
E-mailed the architect a copy of the plan review comment list. JCM
|
Plan resubmittals received | | | 10/15/2004 | | DONE |
|
|
|
Received 3 response comments, 3 joint code check, 3 copies of sheet S-503 taken to John M,
|
Plan resubmittals requested | | | 10/14/2004 | | |
|
|
|
E-mailed the project architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 10/7/2004 | | 10/14/2004 | | FAIL |
|
|
|
Contacted PDQ to take resubmitted plans of 10/07/04 to outside engineering. kmm Received e-mailed comment list from consulting structural engineer on 3rd review, requesting additional revisions. JCM
|
Routing - Erosion and Sediment | 10/8/2004 | | 10/8/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLAN CHECK | 10/7/2004 | | 10/8/2004 | | |
|
|
|
|
Plan resubmittals received | | | 10/7/2004 | | DONE |
|
|
|
Received 2 Transmittal Letters 1 Copy of Sheet G-003-2B 3 Copys of sheet S-503 & 1 ESC Control Master Plan Booklet, 3 Sheets of C-100-3 Taken to John Menard...
|
Routing - FIRE | 10/1/2004 | | 10/6/2004 | | PASS |
|
|
|
10/7-Received and routed plans on. 10/6-Holding for 2nd copy of sheet G-003-2B. Called archtiect and left voice message to resubmit. All other items satisfactory.
|
Plan resubmittals requested | | | 10/4/2004 | | DONE |
|
|
|
Faxed the architect a copy of comment list form the consulting structural engineer requesting additional revisions. JCM
|
Routing Off Site - STRUCTURAL | 9/20/2004 | | 10/1/2004 | | FAIL |
|
|
|
Contacted PDQ for outside delivery. - Received comment list from consulting structural engineer requesting additional revisions. JCM
|
Plan resubmittals received | | | 10/1/2004 | | DONE |
|
|
|
Received Transmittal Letter,1 sheet for the United Water & 2 Sets of G-003-2B,PP-100B-4,PP-100E-4,PP-100F-4,PP-101B-4,PP-101C-4,PPD-101E-4,PP-101F-4,PP-102B-4PP-102C-4,PP-102E-4,PP-102F-4,PP-103B-4,PP-103E-4,PP-104B-4,PP-104E-4, Taken to John Menard...
|
Routing - PLAN CHECK | 9/16/2004 | | 10/1/2004 | | |
|
|
|
|
Plan resubmittals received | | | 9/20/2004 | | DONE |
|
|
|
Received 2 Transmittal Letters, 3 Sets of S-001,S-002,S-503 , 2 boxes of Structural Calcs... Taken to John M.
|
Plan Review Completed(1st rev) | | | 9/15/2004 | | FAIL |
|
|
|
failed Planning land div, structural, and Fire.
|
Routing - FIRE | 9/10/2004 | | 9/15/2004 | | FAIL |
|
|
|
Plans lack essential fire protection information, including FD access routes, hyd locations, fire flow, location of proposed undergroun penetrations through foudation walls, installation of temporary (or permanent( standpipes, propoesed location for fire pump, water supply reservoir and emergency fuel tanks, which are relavant to the strurural design. Phoned archtiect to advise and discussed issues with Jeff Cramer. He'll try to obtain info from mechanical and resubmit. To meet with him further on Friday to discuss in more depth.
|
Routing - PLAN CHECK | 8/11/2004 | | 9/10/2004 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/10/2004 | | PASS |
|
|
|
Reviewed and approved plans for this phase of the project with attached comment list. JCM
|
Plan resubmittals requested | | | 8/19/2004 | | DONE |
|
|
|
Faxed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing Off Site - STRUCTURAL | 8/2/2004 | | 8/18/2004 | | FAIL |
|
|
|
Contacted PDQ for outside engineering. - Received comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PLUMBING | 8/5/2004 | | 8/11/2004 | | PASS |
|
|
|
no plumbing with this phase, called jeff with hdr about waste main in basement not having grade.
|
Routing - PLANNING | 8/3/2004 | | 8/5/2004 | | PASS |
|
|
|
Approved per DRH04-00055.
|
Routing - PUBLIC WORKS | 7/30/2004 | | 8/2/2004 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 8/2/2004 | | 8/2/2004 | | FAIL |
|
|
|
ESC plan does not meet requirement per BCC 8-17. Plus RP not certified. Informed applicant.
|
Routing - PLANNING Land Div | 7/28/2004 | | 7/30/2004 | | FAIL |
|
|
|
Need to complete Record of Survey, Property Line Adjustment. Called Wayne at Briggs on 7/30/04
|
Plan routing begun/NEW & ADDTN | | | 7/28/2004 | | DONE |
|
|
|
|
Application received | | | 7/26/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/26/2004 | | DONE |
|
|
|
|
Fee Review-notes | 7/26/2004 | 7/26/2004 | | | |
|
|
|
|