Permit Information
Permit NumberBLD04-01705
StatusFinaled
Name IDAHO ELK'S REHABILITATION HOSPITAL
Site Address 600 N ROBBINS RD
Project NameIDAHO ELK'S REHAB
Customer Number 
ePlanReviewNo
Description
(HYPERBARIC FACILITY)(IDAHO ELK'S REHABILITATION HOSPITAL-1ST FLR) 3rd PLAN MODIFICATION 2/23/05 - To remodel a 2,974 sq.ft. area in the north east portion of the 1st floor per approved plans. A "Letter of Compliance" is required. Work includes construction of a two (2) hour fire-barrier wall along the east side of the new hyperbaric chamber room area. This remodel will convert approximately 1,500 sq. ft. from "B" occupancy to become part of the existing 7,576 sq. ft. "I1.2" creating a 9,076 sq. ft., "I" occupancy suite. Construction of walls to be non-combustible framing with fire-rated sheetrock covering; interior finishes, cabinetry, electrical, mechanical, plumbing, sprinkler & alarm system upgrades to meet tenant needs and minimum codes. PC04-479/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  3/11/2014 DONE
Case Summary (BLD)  6/23/2008  
BLD-Final6/9/20056/9/20056/9/2005PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 6/9/2005 at 8:17:49 AM. Contact: ###-####. ok for l/c
BLD-Final6/8/20056/8/20056/9/2005PNR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 6/8/2005 at 9:07:57 AM. Contact: ###-####.
FIRE-Final Inspection6/9/20056/9/20056/9/2005APASS
DetailsForrest France
Fire life safety finaled.
BLD-Final6/6/20056/6/20056/7/2005PCANC
DetailsDave Hannah
Scheduled by a contractor via Hello! on 6/6/2005 at 9:31:26 AM. Contact: ###-####.
BLD-Final6/6/20056/7/20056/7/2005ACANC
DetailsDave Hannah
Scheduled by a contractor via Hello! on 6/6/2005 at 11:33:45 AM. Contact: ###-####.
FIRE-Final Inspection6/6/20056/6/20056/6/2005PPART
DetailsForrest France
Final pending fire alarm sign off.
BLD-Other6/1/20056/1/20056/2/2005PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 6/1/2005 at 7:32:31 AM. Contact: ###-####. ceiling grid front area ok to cover
BLD-Other5/25/20055/25/20055/25/2005PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 5/25/2005 at 9:00:51 AM. Contact: ###-####. ceiling grid office area ok
BLD-Other5/23/20055/24/20055/24/2005PFAIL
DetailsDave Hannah
Scheduled by a contractor via Hello! on 5/23/2005 at 10:54:44 AM. Contact: ###-####. ceiling grid still not per plans
BLD-Framing/Rough-in5/19/20055/20/20055/23/2005PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 5/19/2005 at 3:33:13 PM. Contact: ###-####.ceiling gred ok
BLD-Framing/Rough-in4/7/20054/8/20054/8/2005PPASS
DetailsTroy James
Scheduled by a contractor via Hello! on 4/7/2005 at 9:22:43 AM. Contact: ###-####.
Issue PAID IN FULL permit  3/21/2005 DONE
CHANGE STATUS TO (RDY)  3/17/2005  
Plan assigned to (DRS)2/3/20052/3/20053/9/2005 PASS
3/9/2005 08:16:27 DRS - activity updated through activity BLDA022 from case BLD04-01705.
Routing - PLAN CHECK3/8/2005 3/9/2005 PASS
2nd plan modification review has been rerouted to PW, Plumbing, Fire Code & Plan Review and modification approved for the third time.
PLANS/APPL TAKEN TO FRONT DESK  3/9/2005 PASS
To permit desk to issue.
Plan assigned to (DRS)8/3/2004 3/9/2005 PASS
10/1/2004 13:01:16 DRS - activity updated through activity BLDA022 from case BLD04-01705. 12/15/04 - 1st plan modification reviewed and approved with plans to permit desk for second time. 3/09/05 - 2nd plan modification review completed with plans to permit desk for issuing permit.
Routing - PLUMBING3/8/2005 3/8/2005 PASS
approved per plan and 2003 UPC
Routing - FIRE3/1/2005 3/8/2005 PASS
revised comments faxed to architect.
Routing - PLAN CHECK3/8/2005 3/8/2005 PEND
Routing to plumbing reviewer.
Plan Reviewer's activity  3/1/2005 DONE
Assembled two sets of last submitted plan modification submittals, added original front and back sheets to plans, re-wrote permit scope description, reviewed new plans for code compliance, assembled copies of all items to be attached to front of plans and began routing to other agencies.
Routing - PLAN CHECK2/23/2005 3/1/2005 PEND
3rd plan modification plans assembled. The plans have been approved two times previously by all reviewing agencies and taken to permit desk for issuing permit. This is the third time plans will be circulated for review due to scope of work changes.
Routing - PUBLIC WORKS3/1/2005 3/1/2005 PASS
Plan resubmittals received  2/23/2005 DONE
Received Transmittal Letter,& 2 Copys of sheets A0.1,A0.2,A2.1,A2.2,A7.1,A8.1,A8.2,A8.3,MC1.1,M1.1,M1.2,M2.1,M2.2,M3.1,P1.1,P1.2,P2.1,P3.1,E0.0,E2.1,E2.2,E2.3,E3.0,E3.1 Taken to Dan S.
Telephone call  2/18/2005 DONE
Call to Bryan Gilbreath, ZGA, to tell him the plans have changed sufficiently from the original plans that a full submittal for all sheets is required.
Plan resubmittals received  2/17/2005 DONE
Received Transmittal Letter, 2 Copys of sheets A0.1,A2.1,A2.2,A7.1,A8.1,A8.2,A8.3,MC1.1,M1.1,M2.1,P1.1,P2.1,M3.1,E0.0,E2.0,E2.1,E2.2,E2.3,E3.0,E3.1,E3.2 & 7 Copys of sheet A0.2 Taken to Dan S.
Plan resubmittals received  2/3/2005 DONE
Received letter, & 5 Copys of sheets A0.2, A2.1 Taken to Dan S.
Permit Ready to Issue  12/20/2004 DONE
Inspection Record Card- Bld  12/20/2004 DONE
Telephone call  12/20/2004 DONE
Spoke with Joe and told him that permit is ready & fees///12/20/04 12:40pm BAS
Routing - PUBLIC WORKS12/14/2004 12/15/2004 PASS
Plans resubmitted with scope of work reduced removing all new plumbing fixtures, using existing sink and floor sink that already exist under original plans of BLD98-03343.
Routing - PLUMBING12/15/2004 12/15/2004 PASS
provide an r.p. for the humidifier over the existing floor sink.
Routing - PLAN CHECK12/15/2004 12/15/2004 PASS
Approved as noted and attached.
PLANS/APPL TAKEN TO FRONT DESK  12/15/2004 PASS
Routing - FIRE12/10/2004 12/14/2004 PASS
plan modification approved per revised comments.
Routing - PLAN CHECK12/14/2004 12/14/2004 PEND
Re-routing to public works.
Routing - PLAN CHECK12/9/2004 12/10/2004 PEND
No resubmittals required. Routing to fire code analyst for re-review.
Additional plans submitted  12/9/2004 DONE
Received two complete copies of new plans reducing scope of work and area involved. Plans need to be recirculated to plumbing & fire code analysts for re-review and approval.
Meeting  12/9/2004 DONE
Met with Steve Turney & Eric Anderson, ZGA to review resubmittal plans and accepted same for re-review.
Telephone call  11/30/2004 DONE
Call from Eric Anderson, ZGA, concerning the Idaho Elk's Rehabilitation Hospital Wound Clinic project. The plans have not been picked up from the permit desk (ready 10/1/04) and they would like to resubmit plans for reduction in scope of work, reducing the area involved in the remodel. They are preparing new plans for submittal. I have retrieved the plans from the permit desk and had status changed to review.
CHANGE STATUS TO (REV)  11/29/2004 DONE
per Dan S.
Plan resubmittals received  10/5/2004 DONE
Received Transmittal Letter, & 2 Copys of Exam Light Detail. Taken to Dan S.
Routing - PLAN CHECK10/1/2004 10/1/2004 PASS
Approved as noted on and attached plan review conditions.
PLANS/APPL TAKEN TO FRONT DESK  10/1/2004 PASS
To permit desk to issue.
Inspection Record Card- Bld  10/1/2004 DONE
Permit Ready to Issue  10/1/2004  
Telephone call  10/1/2004 DONE
talked to eric anderson at ###-#### that permit is ready
Routing - FIRE9/28/2004 10/1/2004 PASS
resubmittal acceptable; revised review comments accordingly.
Plan resubmittals received  9/29/2004 DONE
Received letter of transmittal with two M3.1 sheets taken to Dan S.
Routing - PLAN CHECK8/17/2004 9/28/2004 PEND
Plan resubmittals received and inserted into original plans. No further resubmittals required. Routing to fire code analyst for re-review.
Plan resubmittals received  9/24/2004 DONE
Received Transmittal Letter, & 2 Stes of A0.2,A2.1 Taken to Dan S....
Plan Review Completed(1st rev)  8/17/2004 FAIL
failed plan check and fire.
Routing - FIRE8/13/2004 8/17/2004 FAIL
lacks Haz mat inventory statement and details of system design. Review comments faxed to architect.
Routing - PLAN CHECK8/11/2004 8/13/2004 FAIL
PLAN REVIEW COMMENTS TO ARCHITECT FOR RESPONSE. ROUTING TO FIRE CODE ANALYST.
Plan resubmittals requested  8/13/2004 FAIL
COPY OF PLAN REVIEW FAXED AND MAILED TO STEVE TURNEY.
Telephone call  8/11/2004 DONE
Call from Eric Anderson, ZGA, stsating the plans had been submitted under the wrong occupancy use group. Major area of remodel to remain an "I" occupancy suite rather than change to a "B" use. The original "B" occupancy mechanical & office area is being modified to expand the "I" occupancy suite and the original two hour occupancy separation wall constructed under the UBC will be relocated behind the new Chamber room.
Plan resubmittals requested  8/10/2004 DONE
Talked with Eric at ZGA, designer, and faxed him a follow up notice concerning plan submittal occupancy use change proposal and need for analysis between existing under the UBC and the proposed changes under the IBC for the 1st floor. Also faxed a copy of the fire floor fire code analysis from BLD98-03343, original approved plans, for architects use.
Routing - PLAN CHECK8/5/2004 8/10/2004 FAIL
Plans are incomplete pertaining to the occupancy use change proposed based on comparison with the 1998 original plans, BLD98-03343. Have spoken with Eric at ZGA and have faxed him a follow up cover letter stating the deficiency. The code analysis for the proposed changes are needed before the plan review can continue. Routing ti fire code anlyst for review.
Routing - PLUMBING8/4/2004 8/5/2004 PASS
note 16 page P1.1- pipe condensate to branch tailpiece or other indirect waste receptor not located in a cabinet.
Routing - PUBLIC WORKS8/3/2004 8/4/2004 PASS
Plans ACCEPTED BY PLAN TECH  8/2/2004 DONE
No MEC or Envelope Compliance ...
Application received  7/28/2004  
Recd Pcfee & Taken To Pln CK  7/28/2004  
Fee Review-notes7/28/20047/28/2004