Third Notice BLD | 12/7/2005 | 12/7/2005 | 12/14/2005 | | DONE |
|
|
|
Second Notice has not been responded to.///Signed off 2004 permit per Jenifer & Rita
|
Second Notice | | 5/20/2005 | 12/7/2005 | | DONE |
|
|
|
|
Permanent Occupancy | | 5/22/2005 | 5/22/2005 | | DONE |
|
|
|
|
First Notice | | 3/23/2005 | 4/26/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/23/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10508 issued 3-23-05 to the DBSI Office in the Northgate Shopping Center.
|
FIRE-Final Inspection | 3/22/2005 | 3/22/2005 | 3/22/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled. Fire alarm and fire sprinkler finaled
|
Temporary occupancy | | | 10/6/2004 | | DONE |
|
|
|
Temp. Occ. Cert. # 5154 issued 10-6-04 to the DBSI Offices.
|
BLD-Final | 10/4/2004 | 10/5/2004 | 10/5/2004 | A | PASS |
Tom Arcoraci
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles ok for perm when others sign perm occ 10/5/2004 8:34:08 AM
|
FIRE-Final Inspection | 10/1/2004 | 10/4/2004 | 10/4/2004 | A | FAIL |
Troy Cobbley
|
|
|
Provide approved door hardware on one of the two front entrances. See review comments #8. Rmove manual flush bolts from both main exits. Provide approved door hardware on door to storage and old dressing room doors. Provide emergency lighting on second floor, stairway and breakroom that is the egress path. Repair four exit signs. Provide emergency lights in the northeast corner and the short exit corridor. Provide exit sign in the other short exit corridor. 9/4/2004 9:40:30 AM
|
BLD-Final | 10/1/2004 | 10/4/2004 | 10/4/2004 | A | FAIL |
Dave Hannah
|
|
|
dennis--pending fire ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie needs to finish handrails and get fire l/s c/n items completed 10/4/2004 10:58:25 AM
|
FIRE-Final Inspection | 10/4/2004 | 10/4/2004 | 10/4/2004 | P | PART |
Troy Cobbley
|
|
|
Life safety items complete. A temporary occupancy was given with dave millers and teresa's permission until the fire alarm and fire sprinklering of the outside canopies have been finished 10/4/2004 3:24:35 PM
|
FIRE-Sprinkler Rough-in | 9/29/2004 | 9/29/2004 | 9/29/2004 | P | FAIL |
Troy Cobbley
|
|
|
I spoke to Dave Miller and he has not heard back from Teresa about approval of the bond so no inspection was performed. Per Dave all life safety items will need to be complete prior to any temporyary occupancy being given. This was passed on to Dennis with HC. 9/29/2004 3:03:06 PM
|
BLD-Other | 9/29/2004 | 9/29/2004 | 9/29/2004 | P | PART |
Tony Young
|
|
|
dennis t-grid inspection; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
ok pending trades 9/29/2004 4:22:02 PM
|
FIRE-Sprinkler Rough-in | 9/23/2004 | 9/24/2004 | 9/24/2004 | A | CANC |
Troy Cobbley
|
|
|
I spoke to dennis about there is to be no fire signoffs until the sprinklers in the canopies and the fire alarm system has been installed and approved. 9/24/2004 12:20:19 PM
|
BLD-Framing/Rough-in | 9/23/2004 | 9/24/2004 | 9/24/2004 | A | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 9/23/2004 at 5:39:13 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 9/22/2004 | 9/23/2004 | 9/23/2004 | P | FAIL |
Troy James
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
Need to install (3) 17/8x117/8 LVL at hallway to restrooms or provide letter from engineer stating what is installed is ok. Ok to cover except at beam location. 9/23/2004 4:37:53 PM
|
BLD-Conference | 9/21/2004 | 9/21/2004 | 9/21/2004 | P | DONE |
Troy Cobbley
|
|
|
I left a notice with Dutch with DBSI that states that there will not be any more inspection sign offs or plan review on this tenant space or any others in the shopping center until the fire alarm system and sprinkler systems have met code requirements as enforced by boise fire dept.
|
BLD-Foundation | 9/17/2004 | 9/20/2004 | 9/20/2004 | A | PART |
Tony Young
|
|
|
dennis; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
int. ftg for moved bearing on existing 9/20/2004 10:07:19 AM
|
FIRE-Conference | 9/17/2004 | 9/20/2004 | 9/20/2004 | A | DONE |
Troy Cobbley
|
|
|
I spoke to Dutch with DSCI about sprinkler heads. I found several locations where sprinklers are overspaced. I told him he needs a sprinkler contractor to verify spacing throughout the tenant space. Also there is a control valve on a anti-freeze loop that does not have a tamper switch. 9/20/2004 2:47:09 PM
|
Permit Ready to Issue | | | 9/17/2004 | | DONE |
|
|
|
|
Telephone call | | | 9/17/2004 | | DONE |
|
|
|
Called and told permit is ready & fees///9/17/04 BAS
|
Issue PAID IN FULL permit | | | 9/17/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/16/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/16/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/15/2004 | | 9/15/2004 | | PASS |
|
|
|
|
Plan assigned to (R_H) | 8/13/2004 | | 9/15/2004 | | PASS |
|
|
|
9/15/2004 13:57:33 RMH - activity updated through activity BLDA022 from case BLD04-01819.
|
Routing - FIRE | 9/9/2004 | | 9/14/2004 | | PASS |
|
|
|
resubmittal acceptable.
|
Routing - PLAN CHECK | 8/27/2004 | | 9/9/2004 | | PEND |
|
|
|
No corrections required by building department review, Routed plans to the fire for there review of the revisions on 9/9/04 permit pending fire departments review and approval.
|
Plan resubmittals received | | | 9/7/2004 | | DONE |
|
|
|
Received transmittal letter with memo two sets of sheets G1.1,SD1.1,SD1.2,A2.1,A2.2,A3.1,A3.2,A5.1,M2.1MM2.2,E0.0,E2.0D,E2.0L,E2.1,E3.0,taken to Ron Hill
|
Routing - FIRE | 8/25/2004 | | 8/27/2004 | | FAIL |
|
|
|
Long list of IBC plan deficiencies inlcuding full plans and occupancy load of 2nd floor, and building exiting details; refer to attached review comments. Comments faxed to architect.
|
Plan Review Completed(1st rev) | | | 8/27/2004 | | FAIL |
|
|
|
failed plan check and Fire
|
Routing - PLAN CHECK | 8/18/2004 | | 8/25/2004 | | FAIL |
|
|
|
Plans failed in building department review, Faxed requirements to architect on 8/25/04, Routed plans to the fire department on 8/25/04.
|
Routing - PUBLIC WORKS | 8/13/2004 | | 8/18/2004 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/10/2004 | | DONE |
|
|
|
|
Application received | | | 8/6/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/6/2004 | | DONE |
|
|
|
|
Fee Review-notes | 8/6/2004 | 8/6/2004 | | | |
|
|
|
|