Case Summary (BLD) | | | 12/6/2013 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/6/2012 | | |
|
|
|
|
Letter of compliance | | | 4/1/2005 | | DONE |
|
|
|
Letter of Compliance issued 4-1-05.
|
FIRE-Final Inspection | 3/25/2005 | 3/30/2005 | 3/30/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled 3/30/2005 9:53:56 AM
|
BLD-Final | 3/25/2005 | 3/30/2005 | 3/30/2005 | P | PART |
Tony Young
|
|
|
jim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
ok as long as trades are signed off (zoning)
contractor had no occupancy card 3/30/2005 1:47:44 PM
|
BLD-Framing/Rough-in | 2/22/2005 | 2/22/2005 | 2/22/2005 | P | PART |
Dave Hannah
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Jan Rice ok to cover framing for the infill of old entryway 2/22/2005 12:46:16 PM
|
FIRE-Final Inspection | 2/10/2005 | 2/15/2005 | 2/15/2005 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given until the rest of the storefront has been completed. 2/15/2005 9:08:12 AM
|
BLD-Other | 2/9/2005 | 2/10/2005 | 2/10/2005 | A | PART |
Tony Young
|
|
|
Tim-wheelchair access/ramp/door; Phone #: ###-#### Internet Inspection Request from: Jan Rice
new door ok to start using pending fire/lifesaftey,,, ramp ok,,, they want to change handicap space painting by blocking w/ planters,, so they dont have to paint new pavers,, will need to get plan reviewers approval, and Building Official approval,,, ok w/ me either way,, 415 2/10/2005 9:18:39 AM
|
FIRE-Final Inspection | 2/10/2005 | 2/10/2005 | 2/10/2005 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled for next week per Jim 2/10/2005 11:44:32 AM
|
BLD-Framing/Rough-in | 1/7/2005 | 1/10/2005 | 1/10/2005 | P | PART |
Dave Hannah
|
|
|
Butch; Phone #: ###-#### Internet Inspection Request from: Jan Rice crew has already installed epoxy bolts in cmu walls for door jam should of had spec inspection told contractor to get engineer reveiw and respond on what he needs also told contractor to get spec inspection on epoxy bolts for cmu wall suports 1/10/2005 2:00:25 PM
|
Case Summary (BLD) | | | 12/6/2004 | | |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/1/2004 | | DONE |
|
|
|
plan mod already pd --changed status
|
(F) Reprint permit | | | 12/1/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/30/2004 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/30/2004 | | DONE |
|
|
|
|
Telephone call | | | 11/30/2004 | | DONE |
|
|
|
left mess for jerry teal at ###-#### that permit is ready
|
Routing - PLAN CHECK | 11/24/2004 | | 11/29/2004 | | PASS |
|
|
|
Delayed for one week waiting for approveal of $500 fee waiver. Modified drawings approved.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/29/2004 | | DONE |
|
|
|
|
Routing - PLANNING | 11/23/2004 | | 11/24/2004 | | PASS |
|
|
|
Approved as noted on sheet A1.1. The handicapped parking stall and access aisle must be a minimum of 18' deep and can utilize a 2' bumper overhang.
|
Routing - PLAN CHECK | 11/15/2004 | | 11/23/2004 | | PASS |
|
|
|
Modified drawings approved.
|
BLD-Footing | 11/19/2004 | 11/22/2004 | 11/22/2004 | A | PART |
Tony Young
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner
front colunm ftgs,,, modified plans resubmitted to city 11/22/2004 11:01:13 AM
|
BLD-Framing/Rough-in | 11/12/2004 | 11/15/2004 | 11/15/2004 | A | PART |
Tony Young
|
|
|
Roof cap framing, Jim; ph.# ###-####
new soffit /facia covering,,, need letter/ drawings from architect on changes out front and on "as built" as structure is different from plans 11/15/2004 12:00:00 PM
|
BLD-Framing/Rough-in | 11/12/2004 | 11/12/2004 | 11/12/2004 | P | NH |
Tony Young
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
BLD-Conference | 10/28/2004 | 10/28/2004 | 10/28/2004 | P | DONE |
Tony Young
|
|
|
Jim-Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner
|
Issue PAID IN FULL permit | | | 9/29/2004 | | |
|
|
|
|
(F) Reprint permit | | | 9/29/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/1/2004 | | 9/10/2004 | | DONE |
|
|
|
Routed to ESC.
|
Routing - Erosion and Sediment | 9/10/2004 | | 9/10/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLAN CHECK | 9/10/2004 | | 9/10/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/10/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/10/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/10/2004 | | DONE |
|
|
|
|
Telephone call | | | 9/10/2004 | | DONE |
|
|
|
PERMIT READY AND FEE DUE
|
Plan assigned to (CJW) | 8/13/2004 | | 9/10/2004 | | PASS |
|
|
|
9/10/2004 14:32:47 CJW - activity updated through activity BLDA022 from case BLD04-01847.
|
Plan resubmittals received | | | 9/9/2004 | | DONE |
|
|
|
Received ESC PERMIT APPLICATON, 2 Sediment plans, & 1 Set of A1-1 Taken to Carl Westfall.....
|
Routing - FIRE | 8/26/2004 | | 9/1/2004 | | PASS |
|
|
|
approved subject to satisfacotyr inspeciton; no written review comments.
|
Plan Review Completed(1st rev) | | | 9/1/2004 | | FAIL |
|
|
|
failed ESC
|
Routing - PLAN CHECK | 8/23/2004 | | 8/26/2004 | | PASS |
|
|
|
IBC plan review started August 25, 2004 and finished the next day. The drawings were approved with clarifications. See the plan review report.
|
Routing - PLANNING | 8/20/2004 | | 8/23/2004 | | PASS |
|
|
|
Approve per DRH04-00063
|
Routing - PUBLIC WORKS | 8/13/2004 | | 8/20/2004 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 8/20/2004 | | 8/20/2004 | | |
|
|
|
Failed first review. Request for plan waiver denied, not allowed for this work under BCC 8-17. Notified contact.
|
Plans ACCEPTED BY PLAN TECH | | | 8/12/2004 | | DONE |
|
|
|
|
Application received | | | 8/11/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/11/2004 | | |
|
|
|
|
Fee Review-notes | 8/11/2004 | 8/11/2004 | | | |
|
|
|
|