Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD04-01885
StatusFinaled
Name FARMERS & MERCHANTS STATE BANK
Site Address 121 N 9TH ST
Project NamePLAZA 121
Customer Number 
ePlanReviewNo
Description
(FARMERS & MERCHANTS STATE BANK - SUITES 4B, 100, 200) This building is required to be fully fire sprinklered. To remodel a 1,602 square foot area in the basement, a 3,398 square foot area on the first floor, and the entire second floor (12,085 square feet) for a new bank tenant. Work is to include interior nonbearing walls, interior windows, millwork, suspended ceilings, gypsum board soffits and ceilings, and interior finishes all per the approved drawings and the plan review report on file. The fire sprinkler system shall comply with NFPA 13-2002 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD1/29/20091/29/20091/30/2009 DONE
DetailsCathy Brown
Second Notice has not been responded to.
Second Notice BLD1/2/20091/2/20091/29/2009 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice12/3/200812/3/20081/2/2009 DONE
DetailsDave Hannah
BLD-Aging Inspection12/3/200812/3/200812/3/2008 PASS
DetailsDave Hannah
DOC - Permit Finaled12/3/200812/3/200812/3/2008PPASS
DetailsDave Hannah
BLD-Final8/15/20088/15/20088/15/2008PPASS
DetailsDave Hannah
randy Phone #: ###-#### ok for perm occ
BLD-Aging Inspection8/14/20088/14/20088/15/2008 PASS
DetailsDave Hannah
BLD-Aging Inspection2/1/20082/1/20082/4/2008PPASS
DetailsForrest France
Okay for final.
BLD-Aging Inspection1/29/20081/29/20082/1/2008 DEFR
DetailsDave Hannah
sent to fire
BLD-Aging Inspection10/10/200710/10/200710/15/2007 DEFR
DetailsDave Hannah
BLD-Final4/11/20064/12/20064/17/2006ADONE
DetailsForrest France
wip, pending alarm and sprinkler permit finals.
Plan resubmittals received  5/27/2005  
Received (2) copies of sheet A0.1 and A2.2. Routed to Carl W.
BLD-Final5/19/20055/20/20055/23/2005PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 5/19/2005 at 12:14:56 PM. Contact: ###-####. ok to occ ground level
FIRE-Alarm Testing5/19/20055/20/20055/20/2005ACANC
DetailsForrest France
Cancel per. Dave, the general contractor. Duplicate inspection.
FIRE-Final Inspection5/19/20055/20/20055/20/2005AFAIL
DetailsForrest France
Fail inspection due to several issues, all of which are indicated on the correction notice. Some items are; install fire ext. in basement and 2nd floors, provide suite address, verify door hardware not yet installed, provide approved hardware on teller d
Plan resubmittals received  5/20/2005  
Received (2) copies of sheet A0.1, A2.0, A2.1, A2.2 and A3.0. Routed to Carl W.
FIRE-Final Inspection4/22/20054/22/20054/22/2005PPART
DetailsTroy Cobbley
Temp occupancy is ok for the second floor tenant area only. Area just south of the new lobby is unfinished. Door security items are in the process of being added to two doors. Their operation will need to be verified prior to finaling. Emergency lighting
FIRE-Final Inspection4/22/20054/22/20054/22/2005PPART
DetailsTroy Cobbley
A temporary occupancy was given for the second floor. The fire alarm system passed in the finished areas. The area to the south of the new lobby is unfinished and will require a separate FIR permit if not finished by the time the building is finaled
BLD-Final4/22/20054/22/20054/22/2005PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/21/2005 at 11:44:24 AM. Contact: ###-####. ok to occ the second floor 4/22/2005 1:59:58 PM
BLD-Final4/21/20054/22/20054/22/2005ACANC
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/21/2005 at 11:44:24 AM. Contact: ###-####.
BLD-Other4/19/20054/19/20054/19/2005PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/19/2005 at 9:05:26 AM. Contact: ###-####.
BLD-Other4/11/20054/11/20054/11/2005PPART
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/11/2005 at 7:38:42 AM. Contact: ###-####.ceiling grid ok to cover 4/11/2005 2:58:49 PM
BLD-Framing/Rough-in4/8/20054/8/20054/8/2005PFAIL
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/8/2005 at 9:08:10 AM. Contact: ###-####. ceiling grid prim wires not 1 in 6 4/8/2005 1:21:30 PM
BLD-Other4/1/20054/1/20054/1/2005PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 4/1/2005 at 8:13:01 AM. Contact: ###-####. ceiling grid ok 4/1/2005 1:19:31 PM
FIRE-Conference3/1/20053/1/20053/1/2005PDONE
DetailsTroy Cobbley
For temporary occupancy for the 6th floor I need a letter stating full functionability of the emergency lighting system, two emergency lights added on the sixth floor, signage in the stairs, a barrier at ground level landing to keep people from continuing to the basement, fire extinguisher for the first floor main lobby and sprinkler protection in the mechanical closet on the first floor.
BLD-Conference2/17/20052/18/20052/18/2005ADONE
DetailsDave Hannah
Scheduled by a contractor via Hello! on 2/17/2005 at 4:01:22 PM. Contact: ###-####.
BLD-Framing/Rough-in2/15/20052/16/20052/16/2005APART
DetailsTroy James
Scheduled by a contractor via Hello! on 2/15/2005 at 4:17:50 PM. Contact: ###-####. ok to cover walls only at first floor teller area and second level framing if all trades have approved cover. Need bracing at existing office area walls. 2/16/2005 10:20:33 AM 2/16/2005 10:22:07 AM
BLD-Conference2/16/20052/16/20052/16/2005PDONE
DetailsTroy James
contractor wanted to know if they need to protect existing steel beams at third level roof assembly. I talked to Carl and he said that the existing beams need to be protected. I informed Dave with Kincaid that he needs to protect the beams. 2/16/2005 3:06:13 PM 2/16/2005 3:06:45 PM
BLD-Aging Inspection12/21/200412/21/200412/21/2004 PASS
DetailsDave Hannah
work in progress 12/21/2004 9:33:48 AM
Issue PAID IN FULL permit  9/21/2004 DONE
Permit Ready to Issue  9/17/2004 DONE
Telephone call  9/17/2004 DONE
Spoke with Maria and told her that permit is ready & fees///9/17/04 8:15am BAS
Routing - PLAN CHECK9/3/2004 9/16/2004 PASS
Drawings approved after resubmittal review.
PLANS/APPL TAKEN TO FRONT DESK  9/16/2004 DONE
Inspection Record Card- Bld  9/16/2004 DONE
Print Occupancy Form  9/16/2004 DONE
Plan assigned to (CJW)8/17/2004 9/16/2004 PASS
9/16/2004 12:29:26 CJW - activity updated through activity BLDA022 from case BLD04-01885.
Plan resubmittals received  9/13/2004 DONE
Received letter of transmittal with plan review response letter and two sets of sheets A0.1,A2.2,A3.0,taken to Carl W.
Routing - FIRE8/31/2004 9/3/2004 PASS
Plan Review Completed(1st rev)  9/3/2004 FAIL
failed Plan check
Routing - PLAN CHECK8/20/2004 8/31/2004  
Failed 1st IBC plan review. IBC plan review started August 30, 2004 and finished the next day. A revision to the drawings was required. See the plan review report.
Routing - PUBLIC WORKS8/17/2004 8/20/2004 PASS
Plans ACCEPTED BY PLAN TECH  8/17/2004 DONE
Application received  8/13/2004  
Recd Pcfee & Taken To Pln CK  8/13/2004 DONE
Fee Review-notes8/13/20048/13/2004