Permit NumberBLD04-01887
StatusFinaled
Name BENITON CONSTRUCTION
Site Address 1019 S BROADWAY AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
Retail Shell Building - To construct a new 3,360 sq. ft. one story, type VB retail shell building on the north side of an existing building on the same lot . Other work includes all demo shown on the plans, all new site work, paving and landscaping per approved plans and attachments, DRH03-0208, CUP03-104. No occupancy is authorized by this permit. Separate plans and permits are required to finish each tenant space. Completion of the building energy envelope and draftstoping to be installed under the tenant improvement permits.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled6/7/20056/7/20056/7/2005PPASS
DetailsJim Storey
BLD-Final3/16/20053/16/20053/16/2005PPASS
DetailsDave Hannah
Scheduled by a contractor via Hello! on 3/16/2005 at 9:35:33 AM. Contact: ###-####. ok for cc 3/16/2005 2:37:52 PM
FIRE-Final Inspection3/15/20053/16/20053/16/2005APASS
DetailsTroy Cobbley
fire life safety finaled 3/16/2005 11:12:36 AM
Code Occupancy Approval3/15/20053/15/20053/15/2005APASS
DetailsWm. Michael Meloy
Compliance with Landscaping plans per DRH03-000208 Mod. 1. 3/15/2005 11:15:57 AM
PubWorks Occupancy Approval3/14/20053/14/20053/15/2005 DONE
drainage project complete, signed permanent occupancy 3/14/05 D.Erskine
Code Occupancy Approval  3/15/2005  
DetailsWm. Michael Meloy
Override - Parcel Holds  3/15/2005  
Override - Parcel Holds  3/15/2005  
BLD-Framing/Rough-in1/31/20051/31/20051/31/2005PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 1/31/2005 at 10:22:07 AM. Contact: ###-####.store front framing ok.
BLD-Framing/Rough-in1/19/20051/20/20051/20/2005APASS
DetailsJim Storey
Ryan; Phone #: ###-#### Internet Inspection Request from: Jan Rice main roof deck ok for cover. 1/20/2005 11:13:58 AM
BLD-Concrete12/29/200412/30/200412/30/2004PPART
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/29/2004 at 4:17:12 PM. Contact: ###-####. topped out with si. 12/30/2004 1:26:30 PM
BLD-Concrete12/28/200412/29/200412/29/2004APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/28/2004 at 3:01:52 PM. Contact: ###-####. placed w si pending report. 12/29/2004 10:21:54 AM
BLD-Concrete12/27/200412/28/200412/28/2004APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 12/27/2004 at 2:57:11 PM. Contact: ###-####. they are going to pour at 12:00 first 8 ft lift placed with si repport on file ok. 12/28/2004 11:26:38 AM
BLD-Foundation11/19/200411/19/200411/19/2004PPASS
DetailsJim Storey
Ryan-Pouring at 3:00, before 3 if possible; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner
Override - Parcel Holds1/1/19001/1/190011/19/2004  
Expired yesterday
BLD-Footing11/16/200411/17/200411/17/2004ANR
DetailsDave Hannah
ryan; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Footing11/17/200411/17/200411/17/2004PPASS
DetailsDave Hannah
ryan; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
BLD-Footing11/12/200411/16/200411/16/2004PNR
DetailsTroy James
ryan smith- ###-####--also subgrade for parking lot
Override - Parcel Holds1/1/19001/1/190011/16/2004  
setting up insp
(F) Reprint permit  11/15/2004  
Override - Parcel Holds  11/12/2004  
Issue PAID IN FULL permit  11/12/2004 DONE
Override - Parcel Holds  11/12/2004  
OVERRIDE  11/5/2004  
OVERRIDE  11/5/2004  
Telephone call  11/5/2004 DONE
Spoke with Dave and told him that permit is ready, fees & that we need ACHD info///11/05/04 9:55am BAS
Inspection Record Card- Bld  11/5/2004 DONE
Permit Ready to Issue  11/5/2004 DONE
Plan resubmittals received  11/4/2004 DONE
engineering calculations received for canopy have also been sent directly to City engineer for review by architect. MLO
Plan resubmittals received  11/4/2004 DONE
Received Transmittal Letter, & 3 Copys od sheet RA8.2 Taken to Mike Otto...
Routing - PLAN CHECK11/4/2004 11/4/2004 PASS
PLANS/APPL TAKEN TO FRONT DESK  11/4/2004 DONE
Plan assigned to (MLO)8/18/2004 11/4/2004 PASS
11/4/2004 14:57:00 MLO - activity updated through activity BLDA022 from case BLD04-01887.
Routing Off Site - STRUCTURAL11/1/2004 11/4/2004 PASS
Contacted PDQ for outside delivery.
Plan resubmittals received  11/1/2004 DONE
Received transmittal letter with 3 structrual calculations, 3 RS3 sheets taken to Mike Otto.
Routing Off Site - STRUCTURAL10/26/2004 10/29/2004 FAIL
Contacted PDQ to take resubmitted plans of 10-26-04 out to outside engineering. kmm Missing sheets sent to reviewer as requested. MLO
Routing - PLANNING10/27/2004 10/29/2004 FAIL
Need 5 foot setback along north property line per CUP 03-104.kg
Routing - PLAN CHECK10/29/2004 10/29/2004 PEND
waiting for resubs
Plan resubmittals received  10/29/2004 DONE
Received two sets of sheets RA2.1 taken to Mike O.
Routing - PLANNING10/29/2004 10/29/2004 PASS
Plans comply with CVA03-36 & CUP03-104. License Agreement submitted.
DR staff approved in previous routing on 9-7-04. kg
Routing Off Site - STRUCTURAL10/19/2004 10/29/2004 FAIL
Contacted PDQ for outside delivery corrections sent to architect
Plan resubmittals received  10/26/2004 DONE
Received one copy rA8.1 and rA8.2. Received two copies of revised sheets rA2.1 and rA2.2. Routed all to Mike Otto. kmm
Routing - FIRE10/21/2004 10/25/2004 FAIL
Water supply info not provided. Called architect; he'll get it and fax it.
Routing - FIRE10/25/2004 10/25/2004 PASS
Water report received, plans approved.
Routing - PLANNING10/20/2004 10/21/2004 FAIL
Resubmitted plans still do not meet setback reductions granted by variance CVA03-36 - on Broadway and alley - still need license agreement for landscaping on Belmont. The variance along the north boundary has not been acted on.
Routing - PLAN CHECK10/11/2004 10/20/2004 PASS
Plan resubmittals received  10/19/2004 DONE
Received one copy of revised sheet rA4.2. Routed to Mike O. kmm
Plan resubmittals received  10/11/2004 DONE
Received response letter,internet mapping page, additional calculations letter with two copies of Structural Calculations, two sets of sheets RA2.1,RA2.2,RA2.3,RA2.4,RA4.1,RA4.2,RA8.1,RA8.2, three sets of sheets RS1,RS2,RS3,E1,E2,E3,E4, taken to Mike Otto.
Plan resubmittals received  10/11/2004 DONE
Received transmittal letter with revised BMP list given to Aimee.
Routing - FIRE9/10/2004 9/15/2004 FAIL
lacks hydrant location and fire flow. review faxed to architect.
Plan Review Completed(1st rev)  9/15/2004 FAIL
failed planning, plan check and fire.
Routing - PLAN CHECK9/15/2004 9/15/2004 PEND
Routing - PLAN CHECK9/7/2004 9/10/2004 FAIL
Plans routed to MO. corrections sent to architect
Plan resubmittals requested  9/10/2004 DONE
IBC structural and non-structural corrections
Routing - PLANNING9/2/2004 9/7/2004 FAIL
Plans do not comply with variance granted on Broadway, need 5-ft setback on north prop. line, no property line shown on south half, need license agreement with ACHD for Belmont, eave encroaches on Broadway. KG CVA03-36/CUP03-104
Approved for Design Review per DRH03-208 & DRH03-208 Mod. #1.
Routing - PLUMBING8/31/2004 9/2/2004 PASS
Routing - PUBLIC WORKS8/18/2004 8/31/2004 PASS
Routing - Erosion and Sediment8/31/2004 8/31/2004 PASS
ESC plan approved with attached conditions.
Plans ACCEPTED BY PLAN TECH  8/18/2004 DONE
Routing - PLANNING Land Div8/18/2004 8/18/2004 PASS
Lots 6-9, Block 24 of South Idaho First Subdivision.
Plan routing begun/NEW & ADDTN  8/18/2004  
Recd Pcfee & Taken To Pln CK  8/16/2004  
Application received  8/16/2004  
Fee Review-notes8/16/20048/16/2004   
Routing Off Site - STRUCTURAL8/18/2004    
Called PDQ for pick-up