DOC - Permit Finaled | 6/7/2005 | 6/7/2005 | 6/7/2005 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 3/16/2005 | 3/16/2005 | 3/16/2005 | P | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 3/16/2005 at 9:35:33 AM. Contact: ###-####. ok for cc 3/16/2005 2:37:52 PM
|
FIRE-Final Inspection | 3/15/2005 | 3/16/2005 | 3/16/2005 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 3/16/2005 11:12:36 AM
|
Code Occupancy Approval | 3/15/2005 | 3/15/2005 | 3/15/2005 | A | PASS |
Wm. Michael Meloy
|
|
|
Compliance with Landscaping plans per DRH03-000208 Mod. 1. 3/15/2005 11:15:57 AM
|
PubWorks Occupancy Approval | 3/14/2005 | 3/14/2005 | 3/15/2005 | | DONE |
|
|
|
drainage project complete, signed permanent occupancy 3/14/05 D.Erskine
|
Code Occupancy Approval | | | 3/15/2005 | | |
Wm. Michael Meloy
|
|
|
|
Override - Parcel Holds | | | 3/15/2005 | | |
|
|
|
|
Override - Parcel Holds | | | 3/15/2005 | | |
|
|
|
|
BLD-Framing/Rough-in | 1/31/2005 | 1/31/2005 | 1/31/2005 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/31/2005 at 10:22:07 AM. Contact: ###-####.store front framing ok.
|
BLD-Framing/Rough-in | 1/19/2005 | 1/20/2005 | 1/20/2005 | A | PASS |
Jim Storey
|
|
|
Ryan; Phone #: ###-#### Internet Inspection Request from: Jan Rice main roof deck ok for cover. 1/20/2005 11:13:58 AM
|
BLD-Concrete | 12/29/2004 | 12/30/2004 | 12/30/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/29/2004 at 4:17:12 PM. Contact: ###-####. topped out with si. 12/30/2004 1:26:30 PM
|
BLD-Concrete | 12/28/2004 | 12/29/2004 | 12/29/2004 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/28/2004 at 3:01:52 PM. Contact: ###-####. placed w si pending report. 12/29/2004 10:21:54 AM
|
BLD-Concrete | 12/27/2004 | 12/28/2004 | 12/28/2004 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/27/2004 at 2:57:11 PM. Contact: ###-####. they are going to pour at 12:00 first 8 ft lift placed with si repport on file ok. 12/28/2004 11:26:38 AM
|
BLD-Foundation | 11/19/2004 | 11/19/2004 | 11/19/2004 | P | PASS |
Jim Storey
|
|
|
Ryan-Pouring at 3:00, before 3 if possible; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 11/19/2004 | | |
|
|
|
Expired yesterday
|
BLD-Footing | 11/16/2004 | 11/17/2004 | 11/17/2004 | A | NR |
Dave Hannah
|
|
|
ryan; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Footing | 11/17/2004 | 11/17/2004 | 11/17/2004 | P | PASS |
Dave Hannah
|
|
|
ryan; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
BLD-Footing | 11/12/2004 | 11/16/2004 | 11/16/2004 | P | NR |
Troy James
|
|
|
ryan smith- ###-####--also subgrade for parking lot
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 11/16/2004 | | |
|
|
|
setting up insp
|
(F) Reprint permit | | | 11/15/2004 | | |
|
|
|
|
Override - Parcel Holds | | | 11/12/2004 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/12/2004 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 11/12/2004 | | |
|
|
|
|
OVERRIDE | | | 11/5/2004 | | |
|
|
|
|
OVERRIDE | | | 11/5/2004 | | |
|
|
|
|
Telephone call | | | 11/5/2004 | | DONE |
|
|
|
Spoke with Dave and told him that permit is ready, fees & that we need ACHD info///11/05/04 9:55am BAS
|
Inspection Record Card- Bld | | | 11/5/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/5/2004 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/4/2004 | | DONE |
|
|
|
engineering calculations received for canopy have also been sent directly to City engineer for review by architect. MLO
|
Plan resubmittals received | | | 11/4/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 3 Copys od sheet RA8.2 Taken to Mike Otto...
|
Routing - PLAN CHECK | 11/4/2004 | | 11/4/2004 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/4/2004 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 8/18/2004 | | 11/4/2004 | | PASS |
|
|
|
11/4/2004 14:57:00 MLO - activity updated through activity BLDA022 from case BLD04-01887.
|
Routing Off Site - STRUCTURAL | 11/1/2004 | | 11/4/2004 | | PASS |
|
|
|
Contacted PDQ for outside delivery.
|
Plan resubmittals received | | | 11/1/2004 | | DONE |
|
|
|
Received transmittal letter with 3 structrual calculations, 3 RS3 sheets taken to Mike Otto.
|
Routing Off Site - STRUCTURAL | 10/26/2004 | | 10/29/2004 | | FAIL |
|
|
|
Contacted PDQ to take resubmitted plans of 10-26-04 out to outside engineering. kmm Missing sheets sent to reviewer as requested. MLO
|
Routing - PLANNING | 10/27/2004 | | 10/29/2004 | | FAIL |
|
|
|
Need 5 foot setback along north property line per CUP 03-104.kg
|
Routing - PLAN CHECK | 10/29/2004 | | 10/29/2004 | | PEND |
|
|
|
waiting for resubs
|
Plan resubmittals received | | | 10/29/2004 | | DONE |
|
|
|
Received two sets of sheets RA2.1 taken to Mike O.
|
Routing - PLANNING | 10/29/2004 | | 10/29/2004 | | PASS |
|
|
|
Plans comply with CVA03-36 & CUP03-104. License Agreement submitted.
DR staff approved in previous routing on 9-7-04. kg
|
Routing Off Site - STRUCTURAL | 10/19/2004 | | 10/29/2004 | | FAIL |
|
|
|
Contacted PDQ for outside delivery corrections sent to architect
|
Plan resubmittals received | | | 10/26/2004 | | DONE |
|
|
|
Received one copy rA8.1 and rA8.2. Received two copies of revised sheets rA2.1 and rA2.2. Routed all to Mike Otto. kmm
|
Routing - FIRE | 10/21/2004 | | 10/25/2004 | | FAIL |
|
|
|
Water supply info not provided. Called architect; he'll get it and fax it.
|
Routing - FIRE | 10/25/2004 | | 10/25/2004 | | PASS |
|
|
|
Water report received, plans approved.
|
Routing - PLANNING | 10/20/2004 | | 10/21/2004 | | FAIL |
|
|
|
Resubmitted plans still do not meet setback reductions granted by variance CVA03-36 - on Broadway and alley - still need license agreement for landscaping on Belmont. The variance along the north boundary has not been acted on.
|
Routing - PLAN CHECK | 10/11/2004 | | 10/20/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/19/2004 | | DONE |
|
|
|
Received one copy of revised sheet rA4.2. Routed to Mike O. kmm
|
Plan resubmittals received | | | 10/11/2004 | | DONE |
|
|
|
Received response letter,internet mapping page, additional calculations letter with two copies of Structural Calculations, two sets of sheets RA2.1,RA2.2,RA2.3,RA2.4,RA4.1,RA4.2,RA8.1,RA8.2, three sets of sheets RS1,RS2,RS3,E1,E2,E3,E4, taken to Mike Otto.
|
Plan resubmittals received | | | 10/11/2004 | | DONE |
|
|
|
Received transmittal letter with revised BMP list given to Aimee.
|
Routing - FIRE | 9/10/2004 | | 9/15/2004 | | FAIL |
|
|
|
lacks hydrant location and fire flow. review faxed to architect.
|
Plan Review Completed(1st rev) | | | 9/15/2004 | | FAIL |
|
|
|
failed planning, plan check and fire.
|
Routing - PLAN CHECK | 9/15/2004 | | 9/15/2004 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 9/7/2004 | | 9/10/2004 | | FAIL |
|
|
|
Plans routed to MO. corrections sent to architect
|
Plan resubmittals requested | | | 9/10/2004 | | DONE |
|
|
|
IBC structural and non-structural corrections
|
Routing - PLANNING | 9/2/2004 | | 9/7/2004 | | FAIL |
|
|
|
Plans do not comply with variance granted on Broadway, need 5-ft setback on north prop. line, no property line shown on south half, need license agreement with ACHD for Belmont, eave encroaches on Broadway. KG CVA03-36/CUP03-104
Approved for Design Review per DRH03-208 & DRH03-208 Mod. #1.
|
Routing - PLUMBING | 8/31/2004 | | 9/2/2004 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/18/2004 | | 8/31/2004 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 8/31/2004 | | 8/31/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Plans ACCEPTED BY PLAN TECH | | | 8/18/2004 | | DONE |
|
|
|
|
Routing - PLANNING Land Div | 8/18/2004 | | 8/18/2004 | | PASS |
|
|
|
Lots 6-9, Block 24 of South Idaho First Subdivision.
|
Plan routing begun/NEW & ADDTN | | | 8/18/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/16/2004 | | |
|
|
|
|
Application received | | | 8/16/2004 | | |
|
|
|
|
Fee Review-notes | 8/16/2004 | 8/16/2004 | | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/18/2004 | | | | |
|
|
|
Called PDQ for pick-up
|