Third Notice BLD | 12/6/2005 | 12/6/2005 | 12/16/2005 | | DONE |
|
|
|
Second Notice has not been responded to.///Signed off 2004 permit per Jenifer & Rita
|
Second Notice BLD | 9/29/2005 | 9/29/2005 | 12/6/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 9/14/2005 | 9/29/2005 | | DONE |
|
|
|
|
BLD-Final | 9/13/2005 | 9/14/2005 | 9/14/2005 | A | PASS |
Jim Storey
|
|
|
bill ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie final ok
|
Permanent occupancy | | | 9/14/2005 | | |
|
|
|
Perm. Occ. Cert. # 10720 issued 9-14-05 to Trinity Presbyterian Church.
|
FIRE-Final Inspection | 9/12/2005 | 9/13/2005 | 9/13/2005 | A | PASS |
Forrest France
|
|
|
ADA hardware at the previously noted locations has been installed, fire life safety finaled.
|
Permanent Occupancy | | 9/12/2005 | 9/12/2005 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/7/2005 | 9/8/2005 | 9/8/2005 | A | PART |
Forrest France
|
|
|
All fire life safety issues are satisfactory except for two doors, one at the mechanical room and one at an exterior storage room, which have non ADA approved hardware. Per Ken the GC the parts are on order and an inspection will be called in when installed, a temporary occupancy has been approved.
|
BLD-Final | 9/1/2005 | 9/2/2005 | 9/2/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 9/1/2005 at 3:29:07 PM. Contact: ###-####.temp ok final pending fire.
|
Code Occupancy Approval | 9/1/2005 | 9/1/2005 | 9/2/2005 | P | PASS |
Dena Gambrel
|
|
|
|
FIRE-Final Inspection | 9/1/2005 | 9/2/2005 | 9/2/2005 | A | PART |
Forrest France
|
|
|
Temporary occupancy approved with Sam Rogers permission pending completion of permanent dual phone lines for final of fire alarm permit. Life safety approved when fire alarm, door hardware, emergency light, and one exit sign are repaired as discussed.
|
FIRE-Final Inspection | 8/31/2005 | 9/1/2005 | 9/1/2005 | A | FAIL |
Forrest France
|
|
|
Emergency lighting and exit signs in some locations failed to operate, provide building address at Surprise Way, provide covers and keys for knox boxes, install missing door hardware.
|
BLD-Final | 8/31/2005 | 8/31/2005 | 8/31/2005 | P | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/31/2005 at 11:14:24 AM. Contact: ###-####. fire stop wall behind stage right/adjudest fire doors w/cordenators/instal ada sink pootection/missing two panic bars at exits of chapal// recieved si ok
|
PubWorks Occupancy Approval | 8/25/2005 | 8/25/2005 | 8/25/2005 | | DONE |
|
|
|
Drainage project complete, signed permanent occupancy 8/25/05. G.Fitts
|
BLD-Framing/Rough-in | 8/22/2005 | 8/23/2005 | 8/23/2005 | A | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 8/22/2005 at 3:52:09 PM. Contact: ###-####.
|
FIRE-Conference | 8/11/2005 | 8/11/2005 | 8/11/2005 | P | DONE |
Troy Cobbley
|
|
|
I marked up sheet C1.0 on the approved drawings in red for the curbing that needs to be painted to show the fire dept access routes.
|
BLD-Energy code compliance | 7/8/2005 | 7/11/2005 | 7/11/2005 | A | PASS |
Jim Storey
|
|
|
kim scags; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa
|
BLD-Framing/Rough-in | 7/1/2005 | 7/5/2005 | 7/5/2005 | A | PASS |
Jim Storey
|
|
|
ken; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa sanchuary soffit framing ok
|
BLD-Energy code compliance | 6/24/2005 | 6/27/2005 | 6/27/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/24/2005 at 1:06:17 PM. Contact: ###-####.c/n rfi not all areas are fured out to meet ec have arch address configuration on plan to complet envolpe.
|
BLD-Framing/Rough-in | 6/9/2005 | 6/10/2005 | 6/10/2005 | A | PASS |
Jim Storey
|
|
|
ken; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa kitchen ceilling ok/ storage floor and behind stage framing ok.
|
BLD-Framing/Rough-in | 5/25/2005 | 5/25/2005 | 5/25/2005 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/25/2005 at 10:44:05 AM. Contact: ###-####.hard ciellings in wing b ok for cover.
|
BLD-Framing/Rough-in | 5/14/2005 | 5/16/2005 | 5/16/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 5/14/2005 at 9:00:03 AM. Contact: ###-####.over build at sancawary ok
|
BLD-Framing/Rough-in | 4/27/2005 | 4/28/2005 | 4/28/2005 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/27/2005 at 2:43:37 PM. Contact: ###-####.
|
BLD-Energy code compliance | 4/26/2005 | 4/27/2005 | 4/27/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/26/2005 at 5:03:35 PM. Contact: ###-####. all gyp walls ok area b
|
BLD-Framing/Rough-in | 4/22/2005 | 4/25/2005 | 4/25/2005 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 4/22/2005 at 3:29:47 PM. Contact: ###-####.east side of area b ok for interior framing.
|
BLD-Foundation | 12/20/2004 | 12/20/2004 | 12/20/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/20/2004 at 8:23:01 AM. Contact: ###-####. placed w/si 12/20/2004 4:12:25 PM
|
BLD-Foundation | 12/16/2004 | 12/17/2004 | 12/17/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/16/2004 at 3:48:03 PM. Contact: ###-####.pwsi. 12/17/2004 3:59:13 PM
|
BLD-Foundation | 12/15/2004 | 12/16/2004 | 12/16/2004 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/15/2004 at 12:48:58 PM. Contact: ###-####. wip/psi 12/16/2004 10:00:29 AM
|
BLD-Footing | 12/13/2004 | 12/14/2004 | 12/14/2004 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/13/2004 at 9:00:09 AM. Contact: ###-####. ft on b ufer in place wip si pending. 12/14/2004 10:52:01 AM
|
BLD-Foundation | 12/8/2004 | 12/9/2004 | 12/9/2004 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 12/8/2004 at 12:52:46 PM. Contact: ###-####.
MTI to provide special inspection/ take cylinder samples. 12/9/2004 3:48:22 PM
|
BLD-Foundation | 12/7/2004 | 12/8/2004 | 12/8/2004 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/7/2004 at 11:39:40 AM. Contact: ###-####.
|
BLD-Footing | 12/3/2004 | 12/6/2004 | 12/6/2004 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/3/2004 at 9:25:08 AM. Contact: ###-####.
|
BLD-Footing | 12/2/2004 | 12/3/2004 | 12/3/2004 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/2/2004 at 2:50:27 PM. Contact: ###-####.
|
BLD-Footing | 12/1/2004 | 12/2/2004 | 12/2/2004 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/1/2004 at 12:30:16 PM. Contact: ###-####. crew is still working on placing rebar crew using cold weather protection MTI will be onsite to do rebar inspection and test concrete 12/2/2004 2:08:16 PM
|
BLD-Footing | 11/30/2004 | 12/1/2004 | 12/1/2004 | P | CANC |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 11/30/2004 at 3:05:59 PM. Contact: ###-####.
contractor not ready. MTI to be on site for insp. 12/1/2004 4:14:43 PM
|
BLD-Footing | 11/29/2004 | 11/30/2004 | 11/30/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/29/2004 at 3:17:05 PM. Contact: ###-####.mti pending report. 11/30/2004 4:43:28 PM
|
BLD-Footing | 11/29/2004 | 11/30/2004 | 11/30/2004 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 11/29/2004 at 3:17:05 PM. Contact: ###-####. placed with mti pending report. 11/30/2004 4:41:15 PM
|
BLD-Footing | 11/23/2004 | 11/24/2004 | 11/24/2004 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 11/23/2004 at 12:40:45 PM. Contact: ###-####.
partial footings ok. (see markings on plans)
MTI to provide reports. 11/24/2004 4:14:42 PM
|
BLD-Foundation | 10/23/2004 | 10/25/2004 | 10/25/2004 | A | NR |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/23/2004 at 10:03:59 AM. Contact: ###-####.
|
(F) Reprint permit | | | 10/21/2004 | | |
|
|
|
|
Issue & PRINT permit | | | 10/20/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/18/2004 | | DONE |
|
|
|
|
Telephone call | | | 10/18/2004 | | DONE |
|
|
|
left mess for scott wendell at ###-#### achd fees due
|
Inspection Record Card- Bld | | | 10/15/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/15/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/14/2004 | | DONE |
|
|
|
Plans taken to front desk to issue.
|
Plan assigned to (MLO) | 8/23/2004 | | 10/14/2004 | | PASS |
|
|
|
10/14/2004 07:52:30 MYS - activity updated through activity BLDA022 from case BLD04-01909.
|
Routing Off Site - STRUCTURAL | 9/30/2004 | | 10/13/2004 | | PASS |
|
|
|
Received approved review from outside engineer. MSouthard
|
Plan Reviewer's activity | | | 10/8/2004 | | DONE |
|
|
|
waiting for structural review contacted engineer and will not be done until 10/15. MLO
|
Routing - PLAN CHECK | 10/5/2004 | | 10/7/2004 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 10/7/2004 | | 10/7/2004 | | PASS |
|
|
|
added plumbing fixture fees redone ok
|
Routing - PLUMBING | 10/7/2004 | | 10/7/2004 | | PASS |
|
|
|
added plumbing fixture
|
Plan resubmittals received | | | 10/5/2004 | | DONE |
|
|
|
Received letter of transmittal with, child care plan review and approval form, response letter, letter from ACHD, two sets of sheets A2.12,A2.14,A5.01,A4.02, one sets of sheets E3.1,E5.2 taken to Mike Otto.
|
Routing - PLANNING | 10/4/2004 | | 10/5/2004 | | PASS |
|
|
|
|
Routing - PLANNING | 9/3/2004 | | 10/5/2004 | | PASS |
|
|
|
The applicant is submitting a staff level modification as they revised the site plan and elevations. I will fast track the modification application once it is submitted.
Application submitted & approved. Appeal date over, can now approve. Submitted a modified landscape plan which has been inserted into the plans for building permit.
|
Plan resubmittals received | | | 9/29/2004 | | DONE |
|
|
|
Received letter of transmittal with two copies of supplemental structural calculations two sets of sheets S1.0,S2.1,S2.2,S3.2,S4.0,S5.0,S5.2, taken to Mike Otto.
|
Routing - PLAN CHECK | 9/27/2004 | | 9/28/2004 | | PEND |
|
|
|
resubs do not address all corrections. Will have changes to plumbing with added fixtures per CDH. Architect will provide revised sheets. MIS permit for day care CO still needs to be provided as modification approved for the incidental use separations. MLO
|
Plan resubmittals received | | | 9/27/2004 | | DONE |
|
|
|
Received 2 Trandsmittal Letters, & 2 Sets of C4.0,C5.0,A1.01,A2.01,A2.12,A2.30,A2.32,A3.01 & 1of the transmittal letters Taken to Mike Otto... The other transmittal letter went to Jenifer Gilliland....
|
Plan Review Completed(1st rev) | | | 9/23/2004 | | FAIL |
|
|
|
failed structural, ESC, Plan check and Planning.
|
Routing - PLAN CHECK | 9/23/2004 | | 9/23/2004 | | PEND |
|
|
|
|
Routing - FIRE | 9/17/2004 | | 9/23/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/22/2004 | | DONE |
|
|
|
Steve Webb received response letter, two esc narratives, two esc plans taken to Mike Otto
|
Routing - Erosion and Sediment | 9/22/2004 | | 9/22/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLAN CHECK | 9/9/2004 | | 9/17/2004 | | FAIL |
|
|
|
corrections sent to architect Mike Otto
|
Routing Off Site - STRUCTURAL | 8/20/2004 | | 9/17/2004 | | FAIL |
|
|
|
CALLED PDQ FOR PICK-UP corrections sent to architect
|
Plan resubmittals requested | | | 9/17/2004 | | DONE |
|
|
|
IBC corrections
|
Plan resubmittals received | | | 9/15/2004 | | DONE |
|
|
|
2 - L1.0 sheet added to plan set by Susan Riggs
|
Routing - PLUMBING | 9/2/2004 | | 9/3/2004 | | PASS |
|
|
|
move grease interceptor vent downstream of discharge, use boise city approved grease interceptor detail, attached.
|
Routing - Erosion and Sediment | 9/1/2004 | | 9/2/2004 | | FAIL |
|
|
|
Does not meet requirements set forth in BCC 8-17, notified PD.
|
Routing - PUBLIC WORKS | 8/24/2004 | | 9/1/2004 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/24/2004 | | DONE |
|
|
|
Called Bud Fulleton with Central District Health Dept, to see if they needed to look at these plans, they do NOT need to see them. If any questions please give Bud a call ( office ###-#### cell ###-#### ) . This project requires CDH approval for the daycare and applicant has been sent back to CDH. MLO
|
Plan routing begun/NEW & ADDTN | | | 8/24/2004 | | |
|
|
|
|
Routing - PLANNING Land Div | 8/24/2004 | | 8/24/2004 | | PASS |
|
|
|
Site is over 5 acres in size.
|
Application received | | | 8/18/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/18/2004 | | DONE |
|
|
|
|