Permit Information
Permit NumberBLD04-01918
StatusFinaled
Name N O A A
Site Address 10095 W EMERALD ST
Project NameEmerald Tech Center-Bldg #10
Customer Number 
ePlanReviewNo
Description
(N.O.A.A. - EMERALD TECH CENTER - BLDG #10) This building is fire sprinklered. To construct a 10,752 square foot office tenant space located within an existing 10,944 square foot building. The building shell was constructed under permit BLD04-00871. Work is to include interior nonbearing walls, 2 restrooms accessible to the disabled, interior doors, suspended ceilings, and finishes all per the approved drawings and the plan review report on file. The fire sprinkler system shall comply with NFPA 13-2002 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD5/20/20055/20/20056/8/2005 DONE
Second Notice has not been responded to.
Second Notice BLD4/26/20054/26/20055/20/2005 DONE
First Notice has not been responded to.
First Notice 2/16/20054/26/2005 DONE
Permanent Occupancy 2/16/20052/16/2005 DONE
Details
Permanent occupancy  2/16/2005 DONE
Perm. Occ. Cert. # 10452 issued 2-16-05 to N.O.A.A.
Temporary occupancy  11/22/2004 DONE
Temp. Occ. Cert. # 5172 issued 11-22-0-4 to N.O.A.A.
FIRE-Alarm Testing11/16/200411/17/200411/17/2004APASS
DetailsTroy Cobbley
Fire life safety, fire alarm and fire sprinkler finaled 11/17/2004 9:16:36 AM
BLD-Final11/16/200411/17/200411/17/2004PPART
DetailsLane Manuel
Scheduled by a contractor via Hello! on 11/16/2004 at 1:10:14 PM. Contact: ###-####.
temp c of o ok. still need electrical inspector approval for permanent c of o to be issued.
Everything pertaining to structural approval is ok.
received final approval letters from engineer of record, and special insp. firm. 11/17/2004 3:34:18 PM
FIRE-Final Inspection11/15/200411/16/200411/16/2004AFAIL
DetailsTroy Cobbley
Repair two emergency lights and final fire alarm 11/16/2004 10:09:18 AM
FIRE-Alarm Testing11/15/200411/16/200411/16/2004AFAIL
DetailsTroy Cobbley
Repair two emergency lights and final fire alarm 11/16/2004 10:09:26 AM
BLD-Final11/15/200411/16/200411/16/2004ACANC
DetailsJim Sly
Scheduled by a contractor via Hello! on 11/15/2004 at 12:14:37 PM. Contact: ###-####.
FIRE-Final Inspection11/12/200411/15/200411/15/2004ACANC
DetailsTroy Cobbley
Scheduled by a contractor via Hello! on 11/12/2004 at 1:57:52 PM. Contact: ###-####.
BLD-Final11/12/200411/15/200411/15/2004PCANC
DetailsLane Manuel
Scheduled by a contractor via Hello! on 11/12/2004 at 1:58:26 PM. Contact: ###-####.
BLD-Wall cover11/3/200411/3/200411/3/2004PCANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 11/3/2004 at 9:44:34 AM. Contact: ###-####.
BLD-Conference10/12/200410/12/200410/12/2004PPASS
DetailsJim Sly
Scheduled by a contractor via Hello! on 10/12/2004 at 8:25:37 AM. Contact: ###-####. Do grid ceiling per appr plan Old way) 10/12/2004 5:08:34 PM
BLD-Wall cover9/30/200410/1/200410/1/2004APART
DetailsLane Manuel
Scheduled by a contractor via Hello! on 9/30/2004 at 11:00:32 AM. Contact: ###-####.
bathrooms framing ok 10/1/2004 9:50:25 AM
BLD-Framing/Rough-in9/24/20049/27/20049/27/2004PPART
DetailsLane Manuel
Scheduled by a contractor via Hello! on 9/24/2004 at 3:10:50 PM. Contact: ###-####.
inter. partition wall framing other than bathrooms ok.R 9/27/2004 2:15:16 PM check! 9/27/2004 2:15:48 PM
Inspection Record Card- Bld  9/21/2004  
Print Occupancy Form  9/21/2004 DONE
Permit Ready to Issue  9/21/2004  
Telephone call  9/21/2004 DONE
customer will come in & pickup
Issue PAID IN FULL permit  9/21/2004  
Routing - PLAN CHECK9/14/2004 9/17/2004 DONE
Routed back to planning.
Routing - PLANNING9/17/2004 9/17/2004 PASS
Approved per DRH04-31. Scott Spjute approved DR sign off without final approval of CUP.(e-mail is in DR file) Applicant will be responsible for any changes required under the CUP not already in construction documents. Copies will need to be submitted to DR if any changes required.
Routing - PLAN CHECK9/17/2004 9/17/2004 DONE
PLANS/APPL TAKEN TO FRONT DESK  9/17/2004 DONE
Plan assigned to (CJW)8/25/2004 9/17/2004 PASS
9/17/2004 16:27:52 CJW - activity updated through activity BLDA022 from case BLD04-01918.
Routing - FIRE9/9/2004 9/14/2004 PASS
Plan Review Completed(1st rev)  9/14/2004 FAIL
failed planning
Routing - PLAN CHECK9/1/2004 9/9/2004 PASS
IBC plan review started September 9, 2004 and was finished the same day. The drawings were approved with clarifications. See the plan review report.
Routing - PLANNING8/31/2004 9/1/2004 FAIL
Sarah Schafer DRH04-00031

Applicant has not received CU approval to allow office within the M-1D zone. This was condition 1a in the DR approval. More than 25% of the building is office space. Wes Steele of Habitec has been notified. They will be submitting for the CU in September.
Routing - PUBLIC WORKS8/25/2004 8/31/2004 PASS
Plan resubmittals received  8/23/2004 DONE
Received a response letter with three sheets of E3 put with plans.
Plans ACCEPTED BY PLAN TECH  8/23/2004 DONE
Application received  8/19/2004  
Recd Pcfee & Taken To Pln CK  8/19/2004  
Fee Review-notes8/19/20048/19/2004