Permanent Occupancy | | | 4/5/2013 | | DONE |
|
|
|
|
Letter of compliance | | | 2/8/2005 | | DONE |
|
|
|
Letter of Compliance issued 2-8-05.
|
Code Occupancy Approval | 1/18/2005 | 1/18/2005 | 1/18/2005 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance met. 1/18/2005 2:20:11 PM
|
BLD-Final | 1/12/2005 | 1/13/2005 | 1/13/2005 | A | PART |
Jim Storey
|
|
|
Justin; Phone #: ###-#### Internet Inspection Request from: Jan Rice final ok pending all other signoffs. 1/13/2005 11:24:57 AM
|
FIRE-Final Inspection | 1/11/2005 | 1/12/2005 | 1/12/2005 | A | PASS |
Rick Jackson
|
|
|
justin; Phone #: ###-#### Internet Inspection Request from: Barbara Moore Need to verify address; was taken down for exterior work on west side at new door 1/12/2005 10:08:09 AM
|
BLD-Framing/Rough-in | 12/15/2004 | 12/16/2004 | 12/16/2004 | A | PASS |
Jim Storey
|
|
|
Justin; Phone #: ###-#### Internet Inspection Request from: Jan Rice c/n made ok 12/16/2004 11:28:44 AM
|
BLD-Framing/Rough-in | 12/15/2004 | 12/15/2004 | 12/15/2004 | P | FAIL |
Troy James
|
|
|
Justin; Phone #: ###-#### Internet Inspection Request from: Jan Rice
left c/n with contractor 12/15/2004 2:14:45 PM
|
Inspection Record Card- Bld | | | 12/13/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/13/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/13/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/13/2004 | | DONE |
|
|
|
left mess with chiles collett at ###-#### that permit is ready
|
Issue PAID IN FULL permit | | | 12/13/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/10/2004 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 9/22/2004 | | 12/10/2004 | | PASS |
|
|
|
12/10/2004 09:11:35 CJW - activity updated through activity BLDA022 from case BLD04-01996.
|
Routing - PLAN CHECK | 10/7/2004 | | 12/10/2004 | | PASS |
|
|
|
Approved after 2nd resubmittal review.
|
Plan resubmittals received | | | 12/9/2004 | | DONE |
|
|
|
Received two copies of revised sheet EN-1 and one copy of cover letter. routed to Carl W. kmm
|
Plan resubmittals received | | | 11/30/2004 | | |
|
|
|
Received three copies of revised sheets A1, EN-1. Routed to Carl W. kmm
|
Routing - PLAN CHECK | 10/5/2004 | | 10/7/2004 | | DONE |
|
|
|
Sent to ESC.
|
Routing - Erosion and Sediment | 10/7/2004 | | 10/7/2004 | | PASS |
|
|
|
ESC plan waiver approved with attached conditions.
|
Routing - FIRE | 10/1/2004 | | 10/5/2004 | | PASS |
|
|
|
approved subject to satisfactory field inspection; no written review comments.
|
1st review completed | | | 10/5/2004 | | FAIL |
|
|
|
failed plan check.
|
Routing - PLAN CHECK | 9/28/2004 | | 10/1/2004 | | FAIL |
|
|
|
Failed first IBC plan review. IBC plan review started September 30, 2004 and was finished the next day. Resubmitted drawings were required. See the plan review report.
|
Routing - PLUMBING | 9/24/2004 | | 9/28/2004 | | PASS |
|
|
|
Idaho requires two inch minimum under slab with an inch and one half vent
|
Routing - PLANNING | 9/23/2004 | | 9/24/2004 | | PASS |
|
|
|
Approved per CZC04-00164
|
Routing - PUBLIC WORKS | 9/22/2004 | | 9/23/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 9/22/2004 | | DONE |
|
|
|
Received ESC Permit Application & Waiver Request Taken to Carl Westfall...
|
Plans ACCEPTED BY PLAN TECH | | | 9/20/2004 | | DONE |
|
|
|
Received Zoning Certificate .
|
Plans ACCEPTED BY PLAN TECH | | | 8/31/2004 | | |
|
|
|
Plans Failed as they have not been through Zonning Plan Review.. Call was made to Richard Freiheit on 8-31-04 @ 1:20 message was left that he has 5- working days to get his Zonning Plan Review taken care of , if not done with-in those 5 working days his plans will by VOIDED out per Marlene S. .Also left in the message that if he had any questions he could call Marlene S. or Sara S.
|
Application received | | | 8/27/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/27/2004 | | DONE |
|
|
|
|
First Notice | | 4/15/2013 | | | |
|
|
|
|
Fee Review-notes | 8/27/2004 | 8/27/2004 | | | |
|
|
|
|