Permit Information
Permit NumberBLD04-02012
StatusFinaled
Name JOHN L KALOUSEK
Site Address 3201 W AIRPORT WAY
Project NameAIRPORT
Customer Number 
ePlanReviewNo
Description
(BOISE CITY AIR TERMINAL - GLASS DIFFUSER ART PROJECT) This building is fire sprinklered for fire area reasons. To install a glass diffuser art project on the 2nd floor of the Boise City Air Terminal. The project is located within the security area between the security check point and airplane loading. It will be installed below an existing skylight. Work is to include metal plates, glass elements, and support rods all per the approved drawings, engineering, and the plan review report on file. The eight (8) existing ½" steel rods, including their attachment to the roof structure, were installed earlier under the shell and core permit. The placement of fire sprinkler heads shall comply with NFPA 13-2002 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice BLD12/6/200512/6/200512/14/2005 DONE
Second Notice has not been responded to.///Signed off 2004 permit per Jenifer & Rita
Second Notice BLD9/29/20059/29/200512/6/2005 DONE
First Notice has not been responded to.
First Notice 8/22/20059/29/2005 DONE
BLD-Aging Inspection8/22/20058/22/20058/22/2005 PASS
DetailsJim Storey
DOC - Permit Finaled8/22/20058/22/20058/22/2005PPASS
DetailsJim Storey
BLD-Aging Inspection6/20/20056/20/20056/20/2005 PASS
DetailsJim Storey
wip
BLD-Aging Inspection12/7/200412/7/200412/7/2004 PART
DetailsJim Storey
wip 12/7/2004 7:18:28 AM
Permit Ready to Issue  9/7/2004  
Inspection Record Card- Bld  9/7/2004 DONE
Issue PAID IN FULL permit  9/7/2004  
Plan assigned to (CJW)9/1/2004 9/3/2004 PASS
9/3/2004 14:46:49 CJW - activity updated through activity BLDA022 from case BLD04-02012.
Routing - PLAN CHECK9/1/2004 9/3/2004 PASS
IBC plan review started September 2, 2004 and was finished the next day. The drawings were approved with clarifications. See the plan review report.
PLANS/APPL TAKEN TO FRONT DESK  9/3/2004 DONE
1st review completed  9/3/2004  
Application received  8/30/2004  
Recd Pcfee & Taken To Pln CK  8/30/2004 DONE