BLD-Final | 3/9/2006 | 3/9/2006 | 3/9/2006 | P | PASS |
Dave Hannah
|
|
|
christopher; Phone #: ###-#### 39 Internet Inspection Request from: Cathy Chiles ok for perm occ
|
BLD-Final | 4/20/2005 | 4/20/2005 | 4/20/2005 | A | PASS |
Dave Hannah
|
|
|
ok for perm occ
|
BLD-Framing/Rough-in | 4/18/2005 | 4/20/2005 | 4/20/2005 | A | CANC |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/18/2005 at 4:54:29 PM. Contact: ###-####.
|
BLD-Final | 4/19/2005 | 4/19/2005 | 4/19/2005 | P | FAIL |
Dave Hannah
|
|
|
needs to remove dead bolt for hall exit door 4/19/2005 2:05:08 PM
|
FIRE-Final Inspection | 4/18/2005 | 4/18/2005 | 4/18/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
FIRE-Final Inspection | 4/14/2005 | 4/14/2005 | 4/14/2005 | P | FAIL |
Troy Cobbley
|
|
|
The exit signs provided needed to have a separate illumination source to be listed. They didn't and I still need the letter from the electrician
|
FIRE-Final Inspection | 4/8/2005 | 4/8/2005 | 4/8/2005 | P | FAIL |
Forrest France
|
|
|
Provide additional exit signage at northwest corner as discussed and provide letter from electrical contractor stating emergency lighting has been installed per plan, having been tested and connected to the emergency circuit
|
BLD-Framing/Rough-in | 2/7/2005 | 2/8/2005 | 2/8/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/7/2005 at 10:04:17 PM. Contact: ###-####. ok to cover back area after elec r/i 2/9/2005 7:50:15 AM
|
BLD-Framing/Rough-in | 12/8/2004 | 12/9/2004 | 12/9/2004 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/8/2004 at 5:09:43 PM. phase II ok to cover walls 12/9/2004 3:55:57 PM
|
Issue PAID IN FULL permit | | | 10/12/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/22/2004 | | 9/23/2004 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/23/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/23/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/23/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/23/2004 | | |
|
|
|
|
Telephone call | | | 9/23/2004 | | DONE |
|
|
|
left mess for scott wendell -###-#### that permit is ready
|
Plan assigned to (CJW) | 9/2/2004 | | 9/23/2004 | | PASS |
|
|
|
9/23/2004 12:36:42 CJW - activity updated through activity BLDA022 from case BLD04-02016.
|
Routing - FIRE | 9/17/2004 | | 9/22/2004 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 9/22/2004 | | FAIL |
|
|
|
failed plan check
|
Plan resubmittals received | | | 9/20/2004 | | DONE |
|
|
|
Received two sets of sheets a0.1,a2.0,a2.1,a4.0,a5.0,a6.0,a7.0,a9.0,m2.0,e2.0f,e2.0l,e2.0p,e2.0S,E3.0 taken to Carl W.
|
Telephone call | | | 9/17/2004 | | DONE |
|
|
|
The architect's representative called. The owner has requested changes to the submitted drawings. He was instructed to submitt all sheet that are changed.
|
Routing - PLAN CHECK | 9/7/2004 | | 9/17/2004 | | |
|
|
|
Failed first IBC plan review. IBC plan review was started and finished September 17, 2004. Resubmitted drawings were required from the architect. See the plan reveiw report.
|
Routing - PUBLIC WORKS | 9/2/2004 | | 9/7/2004 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/1/2004 | | DONE |
|
|
|
|
Application received | | | 8/30/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/30/2004 | | DONE |
|
|
|
|
Fee Review-notes | 8/30/2004 | 8/30/2004 | | | |
|
|
|
|