To construct a 3970 sq. ft. two story DUPLEX / CONDO. UNIT "C" is a three bedroom, two and half bathroom two story unit with 1950 sq. ft. (900 sq. ft. first floor/1050 sq. ft. second floor) with a attached 495 sq. ft. two car garage, a 72 sq. ft. covered back porch and a 60 sq. ft. covered front porch. UNIT "D" is a three bedroom, two and half bathroom two story unit with 2020 sq. ft. (980 sq. ft. first floor/1040 sq. ft. second floor) with a attached 495 sq. ft. two car garage and a 68 sq. ft. covered back porch. Per approved plans, engineering and requirement list. CUP04-00006 per Karen Gallagher with Planning and Zoning. PC#559 (SAM)
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/8/20054/8/20054/8/2005PPASS
DetailsJim Storey
Extend Permit 180 days4/8/20054/8/20054/8/2005PCANC
DetailsTom Arcoraci
BLD-Final4/7/20054/8/20054/8/2005ACANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 4/7/2005 at 7:25:20 AM. Contact: ###-####.
DOC - Permit Finaled4/8/20054/8/20054/8/2005PPASS
DetailsJim Storey
Code Occupancy Approval  4/8/2005 PASS
Compliance met.
BLD-Other2/7/20052/8/20052/8/2005APASS
DetailsDave Hannah
fire wall nail inspection please///jay; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Energy code compliance2/1/20052/2/20052/2/2005APASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 2/1/2005 at 12:26:16 PM. Contact: ###-####.need nail insp on fire wall
BLD-Framing/Rough-in1/26/20051/27/20051/27/2005APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 1/26/2005 at 2:50:34 PM. Contact: ###-####. seal return air joist bay/remove foam from b-vent 1/27/2005 9:38:40 AM
BLD-Framing/Rough-in1/4/20051/5/20051/5/2005ANR
DetailsDave Hannah
Scheduled by a contractor via Hello! on 1/4/2005 at 12:31:56 PM. Contact: ###-####.
BLD-Conference1/4/20051/4/20051/4/2005PCANC
DetailsAimee Hughes
BLD-Footing11/10/200411/10/200411/10/2004PPART
DetailsLane Manuel
footings only ok
Inspection Record Card- Bld  11/2/2004 DONE
Telephone call  11/2/2004 DONE
left mess that permit is ready
Permit Ready to Issue  11/2/2004 DONE
Issue PAID IN FULL permit  11/2/2004 DONE
Routing - PLANNING Land Div10/29/2004 10/29/2004 PASS
Final Plat of Triangle Park Condominiums recorded on 10/25/04.
Case Summary (BLD)  10/29/2004  
Plan Review Report  10/29/2004  
PLANS/APPL TAKEN TO FRONT DESK  10/29/2004 DONE
Routing - PLAN CHECK10/25/2004 10/29/2004 PASS
Routed to Land Division for approval.
Plan assigned to (SAM)10/27/2004 10/29/2004 PASS
10/29/2004 14:36:15 SAM - activity updated through activity BLDA022 from case BLD04-02033.
Plan Reviewer's activity  10/28/2004 DONE
11:20 I called and talked to Jay Kelly about his plans. I let him know that I had some questions for the engineer and that Dave Abo is still waiting for the plat to be signed. (Dan O. listened)

I called and left a message for John Mortin. I need to know if holdowns are needed for the 8' wall of line 5 and recalc beam B5.
Pending Assignment by DJO9/1/2004 10/27/2004 DONE
10/27/2004 10:38:16 SAM - activity updated through activity BLDA183 from case BLD04-02033.
Routing - PLANNING10/25/2004 10/25/2004 PASS
Plans comply with CUP04-06 - approval from Drainage District #3 submitted. Condition of Approval includes compliance with Subdivision Division. Land Division to cover requirement to receive signed plat. kg
Routing - PLANNING Land Div9/16/2004 9/16/2004 FAIL
Plat needs to be recorded.
Routing - PUBLIC WORKS9/15/2004 9/15/2004 PASS
Routing - PLANNING Land Div9/15/2004 9/15/2004 FAIL
Need to record Final Plat of Triangle Park Condominium.
Routing - PLANNING9/14/2004 9/14/2004 FAIL
Plans for buildings are ok, but still need Drainage District #3's approval of drainage plan.
Routing - PLANNING9/1/2004 9/1/2004 FAIL
CUP04-00006. Need modifications of windows to match approved elevations and garage dimensions to meet minimums. KGallagher
Application received  8/31/2004  
Routing - PLAN CHECK10/25/2004    
Routed to Plan check. Land Division approval still need. KG