Third Notice BLD | 12/6/2005 | 12/6/2005 | 12/16/2005 | | DONE |
|
|
|
Second Notice has not been responded to.///Signed off 2004 permit per Jenifer & Rita
|
Second Notice BLD | 7/13/2005 | 7/13/2005 | 12/6/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/1/2005 | 7/13/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/1/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10603 issued 6-1-05 to Windermere Real Estate.
|
BLD-Final | 5/24/2005 | 5/24/2005 | 5/24/2005 | A | PASS |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/24/2005 at 7:28:09 AM. Contact: ###-####. ok for perm occ
|
Permanent Occupancy | | 5/24/2005 | 5/24/2005 | | DONE |
|
|
|
|
BLD-Conference | 5/6/2005 | 5/6/2005 | 5/6/2005 | P | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/6/2005 at 8:02:30 AM. Contact: ###-####.
|
BLD-Conference | 4/11/2005 | 4/11/2005 | 4/11/2005 | P | DONE |
Dave Hannah
|
|
|
dave ###-#### cable gaurd rails 4/11/2005 2:23:54 PM
|
BLD-Final | 3/18/2005 | 3/18/2005 | 3/18/2005 | P | FAIL |
Dave Hannah
|
|
|
greg; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles cables for gaurds to loss 3/21/2005 2:51:10 PM
|
FIRE-Final Inspection | 2/22/2005 | 2/22/2005 | 2/22/2005 | A | PASS |
Troy Cobbley
|
|
|
I signed on the fire sprinkler line on the sign off card. Other signatures already given. 2/22/2005 9:37:46 AM
|
BLD-Final | 2/22/2005 | 2/22/2005 | 2/22/2005 | P | NR |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 2/22/2005 at 7:20:18 AM. Contact: ###-####.
|
Temporary occupancy | | | 12/17/2004 | | DONE |
|
|
|
Temp. Occ. Cert. # 5183 issued 12-17-04 to Windermere Real Estate.
|
BLD-Final | 12/16/2004 | 12/16/2004 | 12/16/2004 | P | PART |
Dave Hannah
|
|
|
Greg; Phone #: ###-#### Internet Inspection Request from: Jan Rice ok for temp occ c/n on site needs to finish shell and core permit north half and finish some mis finish items 12/16/2004 3:47:27 PM
|
BLD-Final | 12/15/2004 | 12/15/2004 | 12/15/2004 | P | NR |
Dave Hannah
|
|
|
gregg; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
FIRE-Final Inspection | 12/15/2004 | 12/15/2004 | 12/15/2004 | P | PART |
Rick Jackson
|
|
|
gregg--pending bld fn ; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Complete sprinkler in SE office 12/15/2004 4:58:42 PM
|
FIRE-Conference | 12/13/2004 | 12/14/2004 | 12/14/2004 | A | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/13/2004 at 4:29:45 PM. Contact: ###-####. Requirements for final were reviewed with GC 12/14/2004 10:17:06 AM
|
BLD-Conference | 12/13/2004 | 12/14/2004 | 12/14/2004 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 12/13/2004 at 4:30:56 PM. Contact: ###-####. walked project talked about what needed to be completed to get a temp occ 12/14/2004 11:27:01 AM
|
BLD-Framing/Rough-in | 11/22/2004 | 11/23/2004 | 11/23/2004 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/22/2004 at 4:41:07 PM. Contact: ###-####. ok to start covering wall have new details for steel studs 11/23/2004 10:21:06 AM
|
BLD-Framing/Rough-in | 11/15/2004 | 11/15/2004 | 11/15/2004 | P | FAIL |
Dave Hannah
|
|
|
Greg; Phone #: ###-#### Internet Inspection Request from: Jan Rice plans call for all framing to be done in wood but crew has done it all in steel studs need new plans for arctect showing all new steel framing 11/15/2004 2:20:20 PM
|
Routing - PLAN CHECK | 10/12/2004 | | 10/13/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/13/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/13/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/13/2004 | | DONE |
|
|
|
|
Telephone call | | | 10/13/2004 | | DONE |
|
|
|
Spoke with Greg and told him that permit is ready & fees///10/13/04 3:05pm BAS
|
Issue PAID IN FULL permit | | | 10/13/2004 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/5/2004 | | 10/13/2004 | | PASS |
|
|
|
10/13/2004 08:26:38 CJW - activity updated through activity BLDA022 from case BLD04-02103.
|
1st review completed | | | 10/12/2004 | | PASS |
|
|
|
|
Routing - FIRE | 10/7/2004 | | 10/12/2004 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/16/2004 | | 10/7/2004 | | PASS |
|
|
|
IBC plan review started October 6, 2004 and was finished the next day. The drawings were approved with clarifications. See the plan review report.
|
Plan assigned to (JCB) | 9/13/2004 | | 10/5/2004 | | |
|
|
|
Reassigned to Carl Westfall in Jason's absense.
|
Routing - PUBLIC WORKS | 9/14/2004 | | 9/16/2004 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/10/2004 | | |
|
|
|
|
Application received | | | 9/9/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/9/2004 | | |
|
|
|
|
Fee Review-notes | 9/9/2004 | 9/9/2004 | | | |
|
|
|
|