Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD04-02121
StatusFinaled
Name VAN AUKER CONSTRUCTION
Site Address 12551 W EXECUTIVE DR
Project NameVAN AUKER WAREHOUSE
Customer Number 
ePlanReviewNo
Description
Ronald Van Auker Warehouse & Office (Shell Only) - To construct a new 17,000 square foot, one story, concrete tilt-up and steel shell warehouse and office building and related site improvements (16,000 square foot enclosed building shell with a 1,000 square foot roof covered storage area at the west side of the building). This permit is for the construction of the shell building only. There is no occupancy allowed under this permit. Separate tenant improvement permits will be required to finish this building for occupancy. All construction per the approved plans and attached comment list. #04-590/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection6/7/20056/8/20056/8/2005APASS
DetailsTroy Cobbley
Fire life safety already finaled
Letter of compliance  6/1/2005 DONE
Letter of Compliance issued 6-1-05.
BLD-Final5/26/20055/26/20055/27/2005PPASS
DetailsJim Sly
jim; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
OK for Perm Occ.
FIRE-Final Inspection5/25/20055/26/20055/26/2005APASS
DetailsTroy Cobbley
Fire life safety finaled
BLD-Final5/25/20055/26/20055/26/2005ANR
DetailsJim Sly
jim; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
FIRE-Final Inspection5/19/20055/20/20055/20/2005AFAIL
DetailsTroy Cobbley
Provide exit discharge lighting (if this is the only item left I can sign a temp per Sam Rogers), repair the two office exit lights, provide manual operation for the smoke vents per IFC 910.3.1
FIRE-Conference5/16/20055/17/20055/17/2005ADONE
DetailsTroy Cobbley
Spoke to Phil about duct smoke detector locations. The north one needs relocated to be ahead of the elbow
Code Occupancy Approval  5/10/2005 PASS
FINAL SIGNED OFF.
PubWorks Occupancy Approval5/3/20055/3/20055/3/2005 DONE
Drainage project complete, signed final occupancy 5/3/05. R.Rokovitz
Print Occupancy Form  4/6/2005 DONE
BLD-Concrete12/30/20041/3/20051/3/2005APART
DetailsLane Manuel
Jim; Phone #: ###-#### Internet Inspection Request from: Jan Rice
tilt up panels on north side.
Terracon to provide special insp. 1/3/2005 11:18:15 AM
BLD-Concrete12/30/200412/30/200412/30/2004PPART
DetailsLane Manuel
Jim; Phone #: 71der/slump test3-2139 Internet Inspection Request from: Jan Rice
5 tilt up panels on south side ok.
Terracon to provide special insp./cylinder/slump tests 12/30/2004 1:27:26 PM
BLD-Foundation12/21/200412/22/200412/22/2004PPART
DetailsLane Manuel
jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
remainder of perimeter footings ok.
terracon on site for special insp./ cylinders, etc. 12/22/2004 1:25:08 PM
BLD-Footing12/17/200412/17/200412/17/2004PPART
DetailsLane Manuel
Jim; Phone #: ###-#### Internet Inspection Request from: Jan Rice
one half of bldg perimeter footing ok.
Terracon performed special insp., and took cylinder samples 12/17/2004 2:54:48 PM
BLD-Foundation12/13/200412/13/200412/13/2004PPART
DetailsLane Manuel
Jim; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
two tilt up panels ok.
Terracon providing special insp. cylinder tests 12/13/2004 1:50:45 PM
Plan resubmittals received  12/10/2004  
BLD-Concrete12/6/200412/8/200412/8/2004PPART
DetailsLane Manuel
Jim; Phone #: ###-#### Internet Inspection Request from: Jan Rice
partial ok. see notes from Terracon 12/8/2004 1:37:08 PM
BLD-Footing11/4/200411/5/200411/5/2004APART
DetailsJim Sly
jim; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie Special insp Req. this Project.....(2) center footing Pads OK pending Terricon special inspections, tests and approvals. 11/5/2004 9:38:35 AM
(F) Reprint permit  10/25/2004  
Issue PAID IN FULL permit  10/22/2004 DONE
Inspection Record Card- Bld  10/15/2004  
Inspection Record Card- Bld  10/15/2004 DONE
Inspection Record Card- Bld  10/1/2004 DONE
Permit Ready to Issue  10/1/2004 DONE
Telephone call  10/1/2004 DONE
left mess that permit is ready with gayle ###-####
Plan assigned to (JCM)9/13/2004 9/28/2004 PASS
9/28/2004 08:31:02 JCM - activity updated through activity BLDA022 from case BLD04-02121.
Routing - PLAN CHECK9/27/2004 9/28/2004 PASS
PLANS/APPL TAKEN TO FRONT DESK  9/28/2004 DONE
Plan resubmittals received  9/27/2004 DONE
Received Transmittal Letter, & 2 Copys of SP-1,A-4 Taken to John Menard.....
Plan Review Completed(1st rev)  9/27/2004 FAIL
failed plan check.
Routing - FIRE9/23/2004 9/27/2004 PASS
review faxed to architect for informational purposes.
Routing Off Site - STRUCTURAL9/13/2004 9/27/2004 PASS
Called PDQ for pick up...
Plan resubmittals requested  9/23/2004 DONE
Mailed the applicant a copy of the comment list requesting revisions. JCM
Routing - PLAN CHECK9/21/2004 9/23/2004 FAIL
Routing - PLANNING9/20/2004 9/21/2004 PASS
Approved per DRH03-00099.
Routing - PLUMBING9/17/2004 9/20/2004 PASS
per plans and 2003 upc
Routing - Erosion and Sediment9/16/2004 9/17/2004 PASS
ESC plan approved with attached conditions.
Routing - PUBLIC WORKS9/14/2004 9/16/2004 PASS
Plans ACCEPTED BY PLAN TECH  9/13/2004  
Plan routing begun/NEW & ADDTN  9/13/2004  
Routing - PLANNING Land Div9/13/2004 9/13/2004 PASS
Lot 7, Block 3 of Trustmark Subdivision.
Application received  9/10/2004  
Fee Review-notes9/10/20049/10/2004