Permit Information
Permit NumberBLD04-02144
StatusFinaled
Name K-2 CONSTRUCTION INC
Site Address 2222 S COLE RD
Project NameAIRWAY COURT-LOT #8
Customer Number 
ePlanReviewNo
Description
Lot #8, Airway Park Subdivision - (Shell & Core) * To construct a new 11,500 square foot, one story, masonry and wood framed shell and core building. This building is fully fire sprinkled. This building will contain 5 future tenant spaces. Four of the proposed tenant space will have a vanilla finish and include one accessible restroom (lease spaces #106-#109). The remaining 5610 square foot tenant space will be finished for Fast Glass (BLD04-02145). This is a shell and core permit only and no occupancy is allowed under this permit. Separate tenant improvements permits will be required to finish each tenant space for occupancy. All construction per the approved plans and attached comment list. #04-599/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  4/13/2005 DONE
Letter of Compliaince issued 4-13-05.
BLD-Final4/12/20054/12/20054/12/2005PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 4/12/2005 at 9:51:52 AM. Contact: ###-####. ok for perm 4/12/2005 3:50:58 PM
FIRE-Final Inspection4/5/20054/6/20054/6/2005APASS
DetailsForrest France
Fire life safety finaled
FIRE-Final Inspection4/1/20054/4/20054/4/2005AFAIL
DetailsTroy Cobbley
Provide as-builts for the fire alarm system and straighten sprig ups in Fast Glass
BLD-Final4/1/20054/4/20054/4/2005APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 4/1/2005 at 4:12:49 PM. Contact: ###-####. temp occ due to plunbing 4/4/2005 10:14:29 AM
BLD-Framing/Rough-in2/28/20052/28/20052/28/2005PPART
DetailsLane Manuel
Scheduled by a contractor via Hello! on 2/28/2005 at 8:24:41 AM. Contact: ###-####.
shell framing ok 2/28/2005 4:25:57 PM
BLD-Framing/Rough-in2/23/20052/23/20052/23/2005PPART
DetailsLane Manuel
Scheduled by a contractor via Hello! on 2/23/2005 at 8:54:47 AM. Contact: ###-####.
interior shearwall nailing ok 2/23/2005 3:18:44 PM
BLD-Framing/Rough-in2/11/20052/11/20052/11/2005PPART
DetailsLane Manuel
Scheduled by a contractor via Hello! on 2/11/2005 at 8:21:10 AM. Contact: ###-####.
roof nailing ok 2/11/2005 3:18:52 PM
BLD-Footing11/9/200411/10/200411/10/2004APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 11/9/2004 at 3:33:06 PM. Contact: ###-####. north west corner and wall at same ok 11/10/2004 9:37:26 AM
BLD-Foundation11/9/200411/10/200411/10/2004PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 11/9/2004 at 3:33:59 PM. Contact: ###-####. wall at n/w corner ok 11/10/2004 10:28:44 AM
BLD-Footing11/5/200411/8/200411/8/2004PPART
DetailsLane Manuel
Scheduled by a contractor via Hello! on 11/5/2004 at 2:35:23 PM. Contact: ###-####.
footings ok @ loading dock area. stemwall from line "c" thru "j" 11/8/2004 12:41:45 PM
BLD-Foundation11/4/200411/5/200411/5/2004APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 11/4/2004 at 2:29:28 PM. Contact: ###-####. wall at south and west ok 11/5/2004 8:54:25 AM
BLD-Footing11/4/200411/5/200411/5/2004APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 11/4/2004 at 2:30:40 PM. Contact: ###-####.
BLD-Footing11/1/200411/2/200411/2/2004APART
DetailsJim Sly
Scheduled by a contractor via Hello! on 11/1/2004 at 4:15:06 PM. Contact: ###-####. Most of west wall, all of S. wall, and 1/2 of E. wall OK....2500 PSI Soils test... Drain rock max 6" . 11/2/2004 9:22:32 AM 11/2/2004 9:23:06 AM
(F) Reprint permit  10/18/2004  
Inspection Record Card- Bld  10/15/2004 DONE
Permit Ready to Issue  10/15/2004 DONE
Telephone call  10/15/2004 DONE
cindy at ###-#### that permit is ready
Issue PAID IN FULL permit  10/15/2004 DONE
Routing - PLANNING10/11/2004 10/12/2004 PASS
Approved per DRH04-00158.
Routing - PLAN CHECK10/12/2004 10/12/2004 PASS
PLANS/APPL TAKEN TO FRONT DESK  10/12/2004 DONE
Plan assigned to (JCM)9/16/2004 10/12/2004 PASS
10/12/2004 16:06:34 JCM - activity updated through activity BLDA022 from case BLD04-02144.
Routing - PLAN CHECK9/30/2004 10/11/2004  
Plan Reviewer's activity  10/7/2004 PASS
Reviewed and approved resubmitted structural plan sheets and calculations. JCM
Plan resubmittals received  10/6/2004 DONE
Received Transmittal Letter, 3 Sets of S1.0,S2.0,S3.0,S4.0,S5.0 & 3 Booklets of Structural calcs.. Taken to John Menard.....
Plan resubmittals requested  10/1/2004  
FAxed a copy of the consulting structural engineer's comment list to the architect for response. JCM
Routing Off Site - STRUCTURAL9/16/2004 10/1/2004 FAIL
contacted PDQ for outside delivery. --- Received faxed comment list from the consulting structural engineer requesting revisions. JCM
Routing - FIRE9/27/2004 9/30/2004 PASS
1st review completed  9/30/2004 FAIL
failed planning
Plan Reviewer's activity  9/27/2004 PASS
Plans reviewed and approved as submitted with attached comment list and red lined notes. JCM
Routing - PLAN CHECK9/23/2004 9/27/2004 PASS
Routing - PLANNING9/22/2004 9/23/2004 FAIL
DRH04-00158 Sarah Schafer
Copies of the Recorded Cross Access Agreement and shared parking agreement have not been supplied. I contacted Cindy with Glancey Rockwell and she is working on obtaining the documents.
Routing - PLUMBING9/21/2004 9/22/2004 PASS
dont forget the ss-1 in the west t.i. per plans and 2003 upc.
Routing - PUBLIC WORKS9/16/2004 9/21/2004 PASS
Routing - Erosion and Sediment9/21/2004 9/21/2004 PASS
ESC plan approved with attached conditions.
Routing - PLANNING Land Div9/16/2004 9/16/2004 PASS
Parcel approved in Ada County prior to annexation into Boise City.
Plan routing begun/NEW & ADDTN  9/16/2004 DONE
Plans ACCEPTED BY PLAN TECH  9/16/2004 DONE
Application received  9/14/2004