Second Notice BLD | 9/14/2005 | 9/14/2005 | 11/22/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
Telephone call | | | 10/10/2005 | | DONE |
|
|
|
Faxed notice to MEC and mailed notice to ELE to get final values. Also called Rick (GC) to get his sub-contractors final values///10/10/05 BAS
|
First Notice | | 8/9/2005 | 9/14/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 8/9/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10684 issued 8-9-05 to Zamzow's for greenhouse & warehouse addns.
|
BLD-Final | 8/2/2005 | 8/3/2005 | 8/3/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 8/2/2005 at 3:42:08 PM. Contact: ###-####. ok for perm occ
|
Permanent Occupancy | | 8/3/2005 | 8/3/2005 | | DONE |
|
|
|
|
Code Occupancy Approval | 6/20/2005 | 6/20/2005 | 6/20/2005 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance met.
|
BLD-Final | 6/17/2005 | 6/20/2005 | 6/20/2005 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/17/2005 at 9:13:28 AM. Contact: ###-####. can not use slider door for exit that will not break away.
|
Code Occupancy Approval | 6/17/2005 | 6/17/2005 | 6/17/2005 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance met.
|
FIRE-Final Inspection | 6/9/2005 | 6/9/2005 | 6/9/2005 | A | PASS |
Forrest France
|
|
|
Fire life safety finaled.
|
FIRE-Final Inspection | 6/1/2005 | 6/2/2005 | 6/2/2005 | A | FAIL |
Forrest France
|
|
|
Final pending installation of visual indicator at greenhouse main entry/exit door.
|
FIRE-Final Inspection | 5/18/2005 | 5/19/2005 | 5/19/2005 | A | FAIL |
Forrest France
|
|
|
Provide approved hardware on door to customer pick up area. Lower three provided fire ext. to no higher than 48" above floor. Verify proper hardware on two sets of double doors at exits from greenhouse when installed. Remove exit sign at door to cust
|
Code Occupancy Approval | 5/19/2005 | 5/19/2005 | 5/19/2005 | A | FAIL |
Wm. Michael Meloy
|
|
|
Landscaping along Federal Way not in. Parking in gravel covered by building material. 5/19/2005 10:43:14 AM
|
BLD-Foundation | 2/16/2005 | 2/17/2005 | 2/17/2005 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 2/16/2005 at 4:01:10 PM. Contact: ###-####.
stemwalls ok. Need to reinspect one pier w/ epoxied dowels for support post. 2/17/2005 3:32:53 PM
|
BLD-Footing | 2/14/2005 | 2/15/2005 | 2/15/2005 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 2/14/2005 at 4:07:25 PM. Contact: ###-####.
|
Issue PAID IN FULL permit | | | 12/7/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/1/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/1/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/1/2004 | | DONE |
|
|
|
talked to rick slain at ###-#### that permit is ready
|
Print Occupancy Form | | | 12/1/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/29/2004 | | 11/30/2004 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/30/2004 | | DONE |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 11/30/2004 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 11/30/2004 | | DONE |
|
|
|
|
Plan assigned to (M_P) | 9/22/2004 | | 11/30/2004 | | PASS |
|
|
|
11/30/2004 10:27:49 M_P - activity updated through activity BLDA022 from case BLD04-02154.
|
Routing Off Site - STRUCTURAL | 11/16/2004 | | 11/30/2004 | | PASS |
|
|
|
Called PDQ for pickup.
Letter will be sent to me reflecting this action.
|
Routing - FIRE | 11/22/2004 | | 11/29/2004 | | PASS |
|
|
|
resubmittal acceptable.
|
Case Summary (BLD) | | | 11/22/2004 | | |
|
|
|
|
Routing - PLAN CHECK | 10/15/2004 | | 11/22/2004 | | PEND |
|
|
|
Waiting for others to approve prior to issuing permit.
|
Routing - FIRE | 11/16/2004 | | 11/18/2004 | | PEND |
|
|
|
Returned plans to MP to revise bldg area per revised plans.
|
Plan resubmittals received | | | 11/15/2004 | | DONE |
|
|
|
Received 2 Transmittal Letters, 2 Sets of sheets A-0.0,A-0.1,A-1.0,A-2.0,A-4.0,A-5.0, & 3 extra sheets of A-5.0 Taken to Mike P.
|
Routing - FIRE | 10/14/2004 | | 10/15/2004 | | FAIL |
|
|
|
lacks sprinklers, fire flow and storage info. Review faxed to architect.
|
1st review completed | | | 10/15/2004 | | FAIL |
|
|
|
failed structural, plan check, and fire.
|
Routing Off Site - STRUCTURAL | 9/30/2004 | | 10/14/2004 | | FAIL |
|
|
|
Contacted PDQ for outside delivery.
Sent correction report further review required by outside engineering firm.
|
Routing - PLAN CHECK | 10/5/2004 | | 10/14/2004 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect requesting additional information be submitted for further review prior to issuing permit.
|
Routing - PLANNING | 10/1/2004 | | 10/5/2004 | | PASS |
|
|
|
Approved per DRH03-00165.
|
Routing - Erosion and Sediment | 10/1/2004 | | 10/1/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING Land Div | 9/30/2004 | | 9/30/2004 | | PASS |
|
|
|
Approved, existing building. Parcel defined by public street right-of-way and ROS 4611.
|
Routing - PUBLIC WORKS | 10/1/2004 | | 9/30/2004 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/30/2004 | | DONE |
|
|
|
per John M.
|
Plan routing begun/NEW & ADDTN | | | 9/30/2004 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/21/2004 | | FAIL |
|
|
|
No MEC sheet/ comcheck, Brian will check for Drainage issue..
Plans in hold box waiting for engineered green house plans....
|
Application received | | | 9/15/2004 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/4/2004 | | | | |
|
|
|
Called PDQ for pick-up...
|