Third Notice BLD | 3/15/2006 | 3/15/2006 | 3/23/2006 | | DONE |
|
|
|
Second Notice has not been responded to.
|
Second Notice BLD | 3/1/2006 | 3/1/2006 | 3/15/2006 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 2/1/2006 | 3/1/2006 | | DONE |
|
|
|
|
BLD-Final | 1/31/2006 | 1/31/2006 | 2/1/2006 | P | PASS |
Dave Hannah
|
|
|
Dave the last is here for Medical Imaging ready for final thanks Phil; Phone #: ###-#### Internet Inspection Request from: Phil Doble ok for perm occ
|
Permanent occupancy | | | 2/1/2006 | | DONE |
|
|
|
Perm. Occ. Cert. # 10891 issued 2-1-06 to St. Luke's Regional Medical Center (medical imaging).
|
BLD - Resubmittal Approved | 1/31/2006 | 1/31/2006 | 1/31/2006 | A | CANC |
Dave Hannah
|
|
|
Dave the last is here for Medical Imaging ready for final thanks Phil; Phone #: ###-#### Internet Inspection Request from: Phil Doble
|
BLD-Final | 1/31/2006 | 1/31/2006 | 1/31/2006 | A | DONE |
Dave Hannah
|
|
|
Forest we are ready for a final life safety for C area thanks Phil; Phone #: ###-#### Internet Inspection Request from: Phil Doble
|
FIRE-Final Inspection | 1/31/2006 | 1/31/2006 | 1/31/2006 | P | PASS |
Forrest France
|
|
|
Fire life safety is acceptable for final, missing handle at fire ext. cabinet adjacent to south exterior exit door to be installed today per P. Doble. Noted that fire sprinkler heads in common fire areas are to be of the same response type at the divisions between remodel and exsisting areas, two missing escutcheons at restrooms to be re-installed today.
|
Permanent Occupancy | | 1/31/2006 | 1/31/2006 | | DONE |
|
|
|
|
BLD-Other | 12/29/2005 | 12/29/2005 | 12/29/2005 | P | PART |
Dave Hannah
|
|
|
Ed has a grid ceiling ready for cover ; Phone #: ###-#### Internet Inspection Request from: Phil Doble ok for temp occ needs to finish ada rest rooms
|
BLD-Framing/Rough-in | 12/16/2005 | 12/16/2005 | 12/16/2005 | A | PART |
Dave Hannah
|
|
|
Couple of hard lids for cover. Thanks Phil ; Phone #: ###-#### Internet Inspection Request from: Phil Doble needs to finish fire proofing walls above hardlids
|
BLD-Framing/Rough-in | 12/9/2005 | 12/9/2005 | 12/9/2005 | P | PART |
Dave Hannah
|
|
|
We have six offices,two restrooms,one lockeroom,& one lounge, in "D" area ; Phone #: ###-#### Internet Inspection Request from: Phil Doble ceiling grid ok ok to cover
|
BLD-Wall cover | 12/9/2005 | 12/9/2005 | 12/9/2005 | A | CANC |
Dave Hannah
|
|
|
We have six offices,two restrooms,one lockeroom,& one lounge, in "D" area ; Phone #: ###-#### Internet Inspection Request from: Phil Doble
|
BLD-Wall cover | 12/5/2005 | 12/5/2005 | 12/5/2005 | A | PASS |
Dave Hannah
|
|
|
Area D conference, thanks Phil; Phone #: ###-#### Internet Inspection Request from: Phil Doble ok to cover
|
BLD-Wall cover | 12/2/2005 | 12/2/2005 | 12/2/2005 | A | PART |
Dave Hannah
|
|
|
Dave, not sure if you looked at the fire caulk; Phone #: ###-#### Internet Inspection Request from: Phil Doble floor pent ok ok to cover walls
|
BLD-Wall cover | 11/30/2005 | 11/30/2005 | 11/30/2005 | A | FAIL |
Dave Hannah
|
|
|
Last piece of the puzzle; Phone #: ###-#### Internet Inspection Request from: Phil Doble framing ok but needs to fire prooof pluming pens in floor
|
BLD-Wall cover | 11/14/2005 | 11/15/2005 | 11/15/2005 | A | PART |
Dave Hannah
|
|
|
Dave, last piece of D area. ; Phone #: ###-#### Internet Inspection Request from: Phil Doble ok to cover walls but needs to clean up old shafts
|
BLD-Final | 10/21/2005 | 10/24/2005 | 10/25/2005 | P | PART |
Dave Hannah
|
|
|
Dave, just need you to look at one room. Phil; Phone #: ###-#### Internet Inspection Request from: Phil Doble x-ray room ok to use
|
BLD-Final | 9/28/2005 | 9/29/2005 | 9/29/2005 | A | PART |
Dave Hannah
|
|
|
Dave, cloverdale pluming has Gary Z. coming this afternoon so we should be ready mid afternoon for you. Phil; Phone #: ###-#### Internet Inspection Request from: Phil Doble phase II AREA S A&B ok to occ
|
BLD-Final | 9/28/2005 | 9/28/2005 | 9/29/2005 | P | CANC |
Dave Hannah
|
|
|
Dave, cloverdale pluming has Gary Z. coming this afternoon so we should be ready mid afternoon for you. Phil; Phone #: ###-#### Internet Inspection Request from: Phil Doble
|
FIRE-Final Inspection | 9/27/2005 | 9/27/2005 | 9/27/2005 | P | PART |
Forrest France
|
|
|
Area A and area B life safety, not including the specials lab and men's lockers as marked on approved plans, passed inspection.
|
BLD-Wall cover | 9/13/2005 | 9/13/2005 | 9/13/2005 | A | PART |
Dave Hannah
|
|
|
Dave, beep me when in the area thanks Phil; Phone #: ###-#### x3006 Internet Inspection Request from: Phil Doble ceiling grid second area ok to cover
|
FIRE-Conference | 7/29/2005 | 7/29/2005 | 7/29/2005 | A | DONE |
Forrest France
|
|
|
On site discussion with Phil Doble in regards to sprinkler code issues related to obstructions in a restroom by a soffit and by rolling cabinets in a records room.
|
BLD-Conference | 7/28/2005 | 7/28/2005 | 7/28/2005 | A | PASS |
Dave Hannah
|
|
|
Dave, need you to look at a height issue, code on height above rolling cabinets,and have letter from MTI on I beams. thanks Phil ; Phone #: ###-#### Internet Inspection Request from: Phil Doble
|
BLD-Framing/Rough-in | 7/21/2005 | 7/21/2005 | 7/25/2005 | A | DONE |
Dave Hannah
|
|
|
Hi Dave, This will be for most of A area; Phone #: ###-#### Internet Inspection Request from: Phil Doble
|
BLD-Framing/Rough-in | 7/25/2005 | 7/25/2005 | 7/25/2005 | A | PART |
Dave Hannah
|
|
|
Hi Dave, need you to look at area A for cover. Phil; Phone #: ###-#### Internet Inspection Request from: Phil Doble area a ok to start covering
|
BLD-Framing/Rough-in | 7/6/2005 | 7/6/2005 | 7/7/2005 | P | PART |
Dave Hannah
|
|
|
Hi Dave, this will be for the "B" area; Phone #: ###-#### Internet Inspection Request from: Phil Doble ok to start covering area b
|
BLD-Final | 6/28/2005 | 6/28/2005 | 6/28/2005 | A | PART |
Dave Hannah
|
|
|
Well let's try today; Phone #: ###-#### Internet Inspection Request from: Phil Doble ok to move into area c this is a multy phs project
|
FIRE-Final Inspection | 6/28/2005 | 6/28/2005 | 6/28/2005 | A | PART |
Troy Cobbley
|
|
|
Early Completion area is ok to occupy. The pocket door in the pharmacy still needs ada approved hardware prior to a final.
|
BLD-Final | 6/27/2005 | 6/27/2005 | 6/28/2005 | A | CANC |
Dave Hannah
|
|
|
Hi Dave, need you to look at the early completion area by Forest, Gary, and you ; Phone #: ###-#### Internet Inspection Request from: Phil Doble
|
BLD-Framing/Rough-in | 6/17/2005 | 6/17/2005 | 6/17/2005 | P | PASS |
Dave Hannah
|
|
|
Dave, this is the early completion phase for the Medical Imaging.; Phone #: ###-#### Internet Inspection Request from: Phil Doble ceiling grid most ok several areas perm wires not 1 in 6 crew will redue this areas
|
BLD-Conference | 5/31/2005 | 6/1/2005 | 6/1/2005 | A | PART |
Dave Hannah
|
|
|
Hi Dave, Would like you to walk thru the early completion area. Phil ; Phone #: ###-#### Internet Inspection Request from: Phil Doble walked area c with phill and forest needs to fix ceiling grid and fire protect three post and get spec inspec on fi
|
BLD-Wall cover | 5/10/2005 | 5/10/2005 | 5/10/2005 | A | PART |
Dave Hannah
|
|
|
Hi Dave, Need you to look at a shaft wall before covering Phil; Phone #: ###-#### Internet Inspection Request from: Phil Doble ok to cover shaft
|
BLD-Framing/Rough-in | 4/20/2005 | 4/21/2005 | 4/21/2005 | A | PART |
Dave Hannah
|
|
|
phill ###-#### shaft wall two sides ok 4/21/2005 10:39:25 AM
|
Override - Parcel Holds | | | 4/20/2005 | | |
|
|
|
|
BLD-Framing/Rough-in | 4/11/2005 | 4/11/2005 | 4/11/2005 | P | NR |
Dave Hannah
|
|
|
ceiling inspection please///dan wilson; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
Override - Parcel Holds | 1/1/1900 | 1/1/1900 | 4/11/2005 | | |
|
|
|
ceiling inspection
|
BLD-Framing/Rough-in | 4/8/2005 | 4/8/2005 | 4/8/2005 | P | PART |
Dave Hannah
|
|
|
###-#### Phil phase one area ok to cover walls 4/8/2005 12:50:26 PM
|
Override - Parcel Holds | | | 4/8/2005 | | |
|
|
|
|
BLD-Conference | 4/4/2005 | 4/4/2005 | 4/4/2005 | P | PART |
Dave Hannah
|
|
|
phil ###-#### phase one area steel studs ok 4/4/2005 2:00:48 PM
|
Override - Parcel Holds | | | 4/4/2005 | | |
|
|
|
|
BLD-Aging Inspection | 1/10/2005 | 1/10/2005 | 1/10/2005 | | PASS |
Dave Hannah
|
|
|
wip 1/10/2005 8:13:03 AM
|
Routing - PLAN CHECK | 10/8/2004 | | 10/11/2004 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/11/2004 | | PASS |
|
|
|
To permit desk for issue of permit.
|
Permit Ready to Issue | | | 10/11/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/11/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/11/2004 | | DONE |
|
|
|
|
Telephone call | | | 10/11/2004 | | DONE |
|
|
|
E-mailed Curtis that permit is ready & fees///10/11/04 2:15pm BAS
|
Issue & PRINT to be Invoiced | | | 10/11/2004 | | DONE |
|
|
|
|
Plan assigned to (DRS) | 9/23/2004 | | 10/11/2004 | | PASS |
|
|
|
10/11/2004 07:51:08 DRS - activity updated through activity BLDA022 from case BLD04-02203.
|
Routing - FIRE | 10/5/2004 | | 10/8/2004 | | PASS |
|
|
|
|
1st review completed | | | 10/8/2004 | | |
|
|
|
|
Routing - PLAN CHECK | 9/29/2004 | | 10/5/2004 | | PEND |
|
|
|
No resubmittals required. Routing to fire code analyst for review.
|
Routing - PLUMBING | 9/27/2004 | | 9/29/2004 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/23/2004 | | 9/27/2004 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/23/2004 | | DONE |
|
|
|
|
Pending Assignment by MYS | 9/23/2004 | | 9/23/2004 | | DONE |
|
|
|
9/23/2004 13:16:38 MYS - activity updated through activity BLDA168 from case BLD04-02203.
|
Application received | | | 9/21/2004 | | |
|
|
|
|
(F) Reprint permit | | | 9/21/2004 | | DONE |
|
|
|
|