Second Notice BLD | 7/13/2005 | 7/13/2005 | 8/27/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 6/1/2005 | 7/13/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/1/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10608 issued 6-1-05 to Idaho River Sports.
|
Permanent Occupancy | | 5/25/2005 | 5/25/2005 | | DONE |
|
|
|
|
BLD-Other | 5/17/2005 | 5/18/2005 | 5/18/2005 | A | DONE |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 5/17/2005 at 11:17:10 PM. Contact: ###-####.
|
BLD-Final | 3/2/2005 | 3/3/2005 | 3/3/2005 | A | PASS |
Dave Hannah
|
|
|
Gary; Phone #: ###-#### or Stan ###-#### Internet Inspection Request from: Jan Rice ok for perm occ 3/3/2005 8:45:00 AM
|
BLD-Final | 2/10/2005 | 2/11/2005 | 2/11/2005 | A | NR |
Jim Sly
|
|
|
gordon; Phone #: ###-#### Internet Inspection Request from: Jan Rice Need proof of bonding for landscape, need insp from Code Inforcement, and Plumb Needs to final verified on computer (no record on computer). 2/11/2005 10:37:21 AM
|
FIRE-Final Inspection | 2/10/2005 | 2/11/2005 | 2/11/2005 | A | PASS |
Troy Cobbley
|
|
|
fire life safety finaled 2/11/2005 10:12:43 AM
|
BLD-Final | 2/11/2005 | 2/11/2005 | 2/11/2005 | P | PART |
Dave Hannah
|
|
|
Gordon; Phone #: ###-#### Internet Inspection Request from: Jan Rice ok for temp occ after boned is posted c/n items for perm occ are finsh ada restrooms 2/11/2005 3:29:19 PM
|
Temporary occupancy | | | 2/11/2005 | | DONE |
|
|
|
Temp. Occ. Cert. # 5209 issued 2-11-05 to Idaho River Sports.
|
FIRE-Final Inspection | 2/8/2005 | 2/8/2005 | 2/8/2005 | P | FAIL |
Troy Cobbley
|
|
|
Provide correct remote annunciators for the duct smoke detectors and then test. Remove thumbturn from the main entry/exit. Keyed is ok. Provide approved hardware on all other doors as per review comments and drawings. Provide exit discharge lighting as per review comments. 2/8/2005 3:27:36 PM
|
BLD-Final | 2/7/2005 | 2/7/2005 | 2/7/2005 | P | NR |
Tom Arcoraci
|
|
|
please call 15 mins prior to inspection so he can meet ya there///gordon; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Other | 2/7/2005 | 2/7/2005 | 2/7/2005 | P | FAIL |
Tom Arcoraci
|
|
|
grid not per plan ok to set perimeter tiles when per plan
|
BLD-Framing/Rough-in | 12/28/2004 | 12/29/2004 | 12/29/2004 | A | PASS |
Dave Hannah
|
|
|
gordon; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Framing/Rough-in | 12/28/2004 | 12/29/2004 | 12/29/2004 | A | PASS |
Dave Hannah
|
|
|
gordon; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
(F) Reprint permit | | | 12/14/2004 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/30/2004 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 11/29/2004 | | |
|
|
|
|
Permit Ready to Issue | | | 11/29/2004 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 11/29/2004 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/29/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/29/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/2/2004 | | 11/24/2004 | | PEND |
|
|
|
Plans to route to Marty for Planning approval.
|
Routing - PLANNING | 11/24/2004 | | 11/24/2004 | | PASS |
|
|
|
Approved per DRH04-218 and per letter from Matt Reed to Scott Spjute, dated November 24, 2004.
|
Routing - PLAN CHECK | 11/24/2004 | | 11/24/2004 | | PASS |
|
|
|
Permit and plans approved and taken to front desk.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/24/2004 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 11/24/2004 | | |
|
|
|
|
Plan assigned to (JCB) | 9/23/2004 | | 11/24/2004 | | PASS |
|
|
|
11/24/2004 16:28:50 JCB - activity updated through activity BLDA022 from case BLD04-02204.
|
Routing - PLAN CHECK | 10/27/2004 | | 11/2/2004 | | PEND |
|
|
|
Permit approval dependent on approval from Planning. Marty Santoyo will let me know when Planning can approve the plans/project.
|
Plan resubmittals received | | | 11/1/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 1 Lighting Compliance.. Taken to Jason B.
|
Routing - PLAN CHECK | 10/18/2004 | | 10/27/2004 | | FAIL |
|
|
|
Two items still need to be addressed. Called and left message with architect representative.
|
Plan resubmittals received | | | 10/25/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 2 Sets of T1.0, A1.0,A2.0,S1,S2,LEC-1 Taken to Jason B...
|
BLD-Conference | 10/21/2004 | 10/21/2004 | 10/21/2004 | P | PART |
Bob Archibald
|
|
|
Met with Gary Beck on site to discuss infill framing prior to issuance of building permit. Gary was authorized to begin framing but no cover is allowed.
|
1st review completed | | | 10/18/2004 | | FAIL |
|
|
|
failed planning and plan check.
|
Routing - FIRE | 10/15/2004 | | 10/18/2004 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 10/15/2004 | | |
|
|
|
Plan resubmittals and written response required for further review.
|
Routing - PLAN CHECK | 9/30/2004 | | 10/14/2004 | | FAIL |
|
|
|
Plan review sent and faxed to architect. Plan resubmittals and written response required for further review. Plans to route to Fire Dept. for review.
|
Routing - PLANNING | 9/27/2004 | | 9/30/2004 | | FAIL |
|
|
|
Carl Miller CAR04-00026--Rezone to C-1D/DA has not been finaled.
Marty Santoyo DRH04-00218
|
Routing - PUBLIC WORKS | 9/23/2004 | | 9/27/2004 | | PASS |
|
|
|
|
Routing - PLANNING Land Div | 9/23/2004 | | 9/23/2004 | | PASS |
|
|
|
Approved as Parcel E on ROS 5819.
|
Plans ACCEPTED BY PLAN TECH | | | 9/23/2004 | | PASS |
|
|
|
Sheets A1.3 and A2.0 not signed on extra set of plans. kmm
|
Application received | | | 9/21/2004 | | |
|
|
|
|
Fee Review-notes | 9/21/2004 | 9/21/2004 | | | |
|
|
|
|