Case Summary (BLD) | | | 12/7/2007 | | DONE |
|
|
|
|
BLD-Aging Inspection | 10/13/2005 | 10/13/2005 | 10/13/2005 | | CANC |
Tom Arcoraci
|
|
|
|
DOC - Permit Expired | 10/13/2005 | 10/13/2005 | 10/13/2005 | P | PASS |
Tom Arcoraci
|
|
|
|
Code Occupancy Approval | 8/9/2005 | 8/9/2005 | 8/9/2005 | P | PASS |
Scott M.Brown
|
|
|
PASS FINAL SIGNED OFF
|
Code Occupancy Approval Temp | 8/1/2005 | 8/1/2005 | 8/1/2005 | P | FAIL |
Scott M.Brown
|
|
|
2 PARKING ISLANDS NOT LANDSCAPED TEMP ONLY
|
BLD-Final | 7/26/2005 | 7/29/2005 | 7/29/2005 | P | PASS |
Tom Arcoraci
|
|
|
ben; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa pending code enf approval
|
FIRE-Final Inspection | 7/27/2005 | 7/28/2005 | 7/28/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
FIRE-Final Inspection | 7/26/2005 | 7/27/2005 | 7/27/2005 | A | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
FIRE-Final Inspection | 7/25/2005 | 7/26/2005 | 7/26/2005 | P | CANC |
Troy Cobbley
|
|
|
Scheduled by a contractor via Hello! on 7/25/2005 at 3:13:04 PM. Contact: ###-####.
|
FIRE-Conference | 7/18/2005 | 7/18/2005 | 7/18/2005 | P | DONE |
Troy Cobbley
|
|
|
I met Ben with Dave Evans Const. and discussed exiting issues through the common restroom corridor. Hardware needs to allow passage as directed by the exit signs.
|
BLD-Energy code compliance | 6/1/2005 | 6/2/2005 | 6/2/2005 | A | PASS |
Mike Jordan
|
|
|
robbie; Phone #: ###-#### Internet Inspection Request from: Barbara Moore. REVIEWED AND INSPECTED TRUSS FIX FROM TRUSS ENGINEER AT BOTTOM CHORD WERE MECH. PLATFORM WAS PLACED.-OK
|
BLD-Framing/Rough-in | 5/25/2005 | 5/25/2005 | 5/25/2005 | P | FAIL |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 5/25/2005 at 7:38:12 AM. Contact: ###-####. cn posted
|
BLD-Framing/Rough-in | 4/21/2005 | 4/22/2005 | 4/22/2005 | A | PART |
Jim Sly
|
|
|
shear nailing ###-#### Robbie Roof shear nailing and blocking for diaphram.... OK 4/22/2005 11:28:54 AM
|
BLD-Foundation | 3/16/2005 | 3/16/2005 | 3/16/2005 | P | PASS |
Troy James
|
|
|
robbie; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
BLD-Footing | 3/14/2005 | 3/15/2005 | 3/15/2005 | P | PART |
Dave Hannah
|
|
|
robie; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie
|
(F) Reprint permit | | | 3/14/2005 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/10/2005 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/3/2005 | | 3/9/2005 | | |
|
|
|
|
Routing - PLANNING | 3/9/2005 | | 3/9/2005 | | PASS |
|
|
|
Approved per DRH04-129, CUP04-26, and per revised walkway design at northwest corner as shown on 8 1/2" x 11" from Toothman Ortman Engineering.
|
Routing - PLAN CHECK | 3/9/2005 | | 3/9/2005 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/9/2005 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 3/9/2005 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/9/2005 | | DONE |
|
|
|
|
Telephone call | | | 3/9/2005 | | DONE |
|
|
|
left mess that permit is ready--at ###-####
|
Plan assigned to (JCM) | 9/24/2004 | | 3/9/2005 | | PASS |
|
|
|
3/9/2005 09:53:43 JCM - activity updated through activity BLDA022 from case BLD04-02231.
|
Plan resubmittals received | | | 2/3/2005 | | DONE |
|
|
|
Received 1 Copy of sheet 9 Taken to John M.
|
Routing - PLUMBING | 2/3/2005 | | 2/3/2005 | | PASS |
|
|
|
I will assume that flush tank toilets are to be installed, if flushometer type toilets are installed plans will need to be resubmitted. min. 2" waste below slab.
|
Routing - PLANNING | 1/20/2005 | | 1/21/2005 | | FAIL |
|
|
|
Revised plans and documents that comply with conditions of approval for CUP04-26 and DRH04-129 have not been submitted to Planning Staff for review and approval.
|
Routing - PLUMBING | 1/18/2005 | | 1/20/2005 | | FAIL |
|
|
|
fixture schedule contains fixtures I am unfamiliar with, provide information as to required pipe sizing for waste and water on all fixtures. numerous fixtures appear to be missing waste connections, wc,lav,mop sink, breakroom sink. backflow preventors are not allowed outside of the building, show interior location. thermol expantion protection required. cold water header sizing can not be determined, provide a line drawing showing main and branch sizing. vent and prime all floor drains.
|
Routing - PLAN CHECK | 1/6/2005 | | 1/18/2005 | | |
|
|
|
|
Routing - PLANNING Land Div | 1/6/2005 | | 1/6/2005 | | PASS |
|
|
|
Final Plat of Century Landmark No. 7 recorded on December 10, 2004.
|
Routing - PLAN CHECK | 10/13/2004 | | 1/6/2005 | | |
|
|
|
|
Plan resubmittals received | | | 12/15/2004 | | DONE |
|
|
|
Received Transmittal & 3 Copys of sheets 1,2,3,4,5,6,7,8,9,10 Taken to John M.
|
Plan Reviewer's activity | | | 10/29/2004 | | PASS |
|
|
|
Reviewed and approved resubmittals. JCM
|
Plan resubmittals received | | | 10/26/2004 | | DONE |
|
|
|
Received two copies of revised sheet EN-1. Routed to John M. kmm
|
Routing - FIRE | 10/8/2004 | | 10/13/2004 | | PASS |
|
|
|
|
1st review completed | | | 10/13/2004 | | FAIL |
|
|
|
failed plan check, plumbing, planning, and planning land div.
|
Plan resubmittals requested | | | 10/8/2004 | | |
|
|
|
Mailed the architect a copy of the plan review comment list requesting revisions. JCM
|
Routing - PLAN CHECK | 10/7/2004 | | 10/8/2004 | | FAIL |
|
|
|
|
Routing - PLANNING | 10/6/2004 | | 10/7/2004 | | FAIL |
|
|
|
Design Review site specific conditions of approval not met.
|
Routing - PLUMBING | 10/5/2004 | | 10/5/2004 | | FAIL |
|
|
|
plans are of insufficient clarity to determine code compliance, resubmit plans.
|
Routing - Erosion and Sediment | 10/5/2004 | | 10/5/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PUBLIC WORKS | 9/28/2004 | | 10/4/2004 | | PASS |
|
|
|
|
Telephone call | | | 9/28/2004 | | DONE |
|
|
|
9-27-04 Called Wes Steele, left voise message for him that we need a TI Application submitted....
|
Routing - PLANNING Land Div | 9/23/2004 | | 9/28/2004 | | FAIL |
|
|
|
Do not issue building permit until Final Plat of Century Landmark Center No. 7 Subdivision is recorded. Final Plat has been signed by City Engineer on 9/13/04.
|
Application received | | | 9/23/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/23/2004 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/23/2004 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 9/23/2004 | | DONE |
|
|
|
|
Fee Review-notes | 9/23/2004 | 9/23/2004 | | | |
|
|
|
|
Routing - PLAN CHECK | 1/21/2005 | | | | |
|
|
|
|