BLD-Final | 4/19/2005 | 4/20/2005 | 4/20/2005 | P | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 4/19/2005 at 4:28:15 PM. Contact: ###-####.
|
DOC - Permit Finaled | 4/20/2005 | 4/20/2005 | 4/20/2005 | P | PASS |
Troy James
|
|
|
Finaled by inspector at 4/20/2005 1:07:32 PM
|
BLD-Grading Inspection | 4/19/2005 | 4/19/2005 | 4/19/2005 | | DONE |
|
|
|
FINAL GRADING AND DAINAGE APPROVED
|
BLD-Energy code compliance | 1/10/2005 | 1/10/2005 | 1/10/2005 | P | PASS |
Troy James
|
|
|
Scheduled by a contractor via Hello! on 1/10/2005 at 10:28:03 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 12/29/2004 | 12/30/2004 | 12/30/2004 | A | FAIL |
Troy James
|
|
|
Ed; Phone #: ###-#### Internet Inspection Request from: Jan Rice
need mechanical connection to plate at 3 ply and 2 ply trusses in garage, need correct nailing to 3 ply truss. 12/30/2004 10:43:35 AM
|
BLD-Framing/Rough-in | 12/28/2004 | 12/28/2004 | 12/28/2004 | P | FAIL |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/28/2004 at 9:07:58 AM. Contact: ###-####.
no plans or stamped set of truss engineering on site,,,, no inspection made 12/28/2004 2:07:10 PM
|
BLD-Framing/Rough-in | 12/21/2004 | 12/22/2004 | 12/22/2004 | A | PASS |
Troy James
|
|
|
Shear nailing inspection please on 12/21/2004 at 12:49:34 PM. Contact: ###-####.
|
BLD-Wall cover | 11/1/2004 | 11/1/2004 | 11/1/2004 | P | PASS |
Troy James
|
|
|
Rick-Would like 1:30 inspection; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner
foundation wall ok to place concrete 11/1/2004 10:43:09 AM
|
BLD-Footing | 10/27/2004 | 10/28/2004 | 10/28/2004 | A | PASS |
Troy James
|
|
|
Phone #: ###-#### Internet Inspection Request from: Linda Hartwell
|
BLD-Grading Inspection | 10/28/2004 | 10/28/2004 | 10/28/2004 | | DONE |
|
|
|
Footing subgrade approved by the geotechnical engineer
|
Issue PAID IN FULL permit | | | 10/21/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/19/2004 | | |
|
|
|
|
Permit Ready to Issue | | | 10/19/2004 | | DONE |
|
|
|
|
Telephone call | | | 10/19/2004 | | DONE |
|
|
|
left mess that permit is ready
|
Print Occupancy Form | | | 10/19/2004 | | DONE |
|
|
|
|
Plan assigned to (SAM) | 10/12/2004 | | 10/18/2004 | | PASS |
|
|
|
10/18/2004 13:17:46 SAM - activity updated through activity BLDA022 from case BLD04-02242.
|
Case Summary (BLD) | | | 10/18/2004 | | |
|
|
|
|
Plan Review Report | | | 10/18/2004 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/7/2004 | | 10/18/2004 | | PASS |
|
|
|
Dan O.
|
Plan Reviewer's activity | | | 10/13/2004 | | DONE |
|
|
|
I called and talked to Cole Kunz about this project. I let him know that I need engineering calculations and / or drawing supporting what is on the plans. Plans are on hold till I recieve this information.
|
Routing - FIRE | 10/5/2004 | | 10/6/2004 | | PASS |
|
|
|
No fire sprinklers required (Highlands Hackberry sub.# 4)
|
Routing - Erosion and Sediment | 10/5/2004 | | 10/5/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLANNING | 10/4/2004 | | 10/5/2004 | | PASS |
|
|
|
O.K. per revised site plan.
|
Routing - PLANNING | 9/30/2004 | | 9/30/2004 | | FAIL |
|
|
|
Driveway does not provide adequate on-site turn around as required by plat. Spoke w/ applicant and requested revised drawings. CER-9/30/04 @ 11:00 a.m.
|
Routing - PUBLIC WORKS GRADING | 9/24/2004 | | 9/29/2004 | | PASS |
|
|
|
Approved as category 3
|
Routing - PUBLIC WORKS | 9/29/2004 | | 9/29/2004 | | PASS |
|
|
|
|
Application received | | | 9/24/2004 | | |
|
|
|
|