Third Notice BLD | 12/6/2005 | 12/6/2005 | 12/15/2005 | | DONE |
|
|
|
Second Notice has not been responded to.///Signed off 2004 permit per Jenifer & Rita
|
Second Notice BLD | 10/10/2005 | 10/10/2005 | 12/6/2005 | | DONE |
|
|
|
First Notice has not been responded to.
|
First Notice | | 9/26/2005 | 10/10/2005 | | DONE |
|
|
|
|
BLD-Final | 9/23/2005 | 9/26/2005 | 9/26/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 9/23/2005 at 3:33:01 PM. Contact: ###-####. ok for perm
|
Permanent Occupancy | | 9/26/2005 | 9/26/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 9/26/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10744 issued 9-26-05 to Lyle Pearson, Porsche Showroom.
|
FIRE-Final Inspection | 9/23/2005 | 9/23/2005 | 9/23/2005 | P | PASS |
Troy Cobbley
|
|
|
life safety finaled
|
BLD-Aging Inspection | 9/21/2005 | 9/21/2005 | 9/21/2005 | | CANC |
Tom Arcoraci
|
|
|
|
BLD-Aging Inspection | 7/22/2005 | 7/22/2005 | 7/22/2005 | | PASS |
Tom Arcoraci
|
|
|
|
Temporary occupancy | | | 7/11/2005 | | |
|
|
|
Temporary Occupancy extended until October 3, 2005 per Jenifer Gilliland. Applicant working on providing proper fire department access to Porsche dealership from Gratz Drive. Estimated completion date: August 15, 2005.
|
FIRE-Conference | 5/17/2005 | 5/18/2005 | 5/18/2005 | A | DONE |
Troy Cobbley
|
|
|
fire conference//leonard; Phone #: ###-#### I went over fire dept access requirements with Leonard and gave him the copy of the approved drawings to keep for reference.
|
Routing - FIRE | 4/19/2005 | | 4/19/2005 | | PASS |
|
|
|
Review of 2 copies of resubmitted sheet A1.1 - for modified FD access roadways - approved as shown. One copy of approved plan sent to Fire Inspector for final inspection. One copy to records.
|
Routing - FIRE | 4/12/2005 | | 4/13/2005 | | FAIL |
|
|
|
revised FD access plan does not reflect the roadway design approved in the field for the TOC and is not code compliant. Called architect, left vm to call me to discuss. Advised Fire Inspector to revisit site to verify the temporary roadway designations still meet the design approved for the TOC.
|
Plan resubmittals received | | | 4/13/2005 | | DONE |
|
|
|
Received Transmittal Letter, & 1 Copy of sheet A1.1 Taken to Mike O.
|
Plan resubmittals received | | | 4/12/2005 | | DONE |
|
|
|
3 copies of hydrant/access resubmittal plan sheet A1.1 received and forwarded to Sam Rogers.
|
FIRE-Final Inspection | 4/7/2005 | 4/8/2005 | 4/8/2005 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Lokkers permission until the fire dept access plans have been review, approve and implemented
|
BLD-Final | 4/7/2005 | 4/8/2005 | 4/8/2005 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 4/7/2005 at 5:14:15 PM. Contact: ###-####. ok for temp occ needs to fix landing out side of side door 4/8/2005 4:01:00 PM
|
Temporary occupancy | | | 4/8/2005 | | DONE |
|
|
|
Temp. Occ. Cert. # 5228 issued 4-8-05 to the Lyle pearson Porsche Showroom.
|
FIRE-Final Inspection | 4/6/2005 | 4/7/2005 | 4/7/2005 | A | FAIL |
Forrest France
|
|
|
Need approved fire dept access plan
|
Code Occupancy Approval | 4/7/2005 | 4/7/2005 | 4/7/2005 | P | PASS |
Scott M.Brown
|
|
|
ok finaled signed 4/7/2005 3:57:44 PM
|
Telephone call | | | 4/5/2005 | | DONE |
|
|
|
Phone call from architect. Set up meeting for him to bring in modified plans later this morning showing revisions to FD access roadways shown on original approved plans.
|
Meeting | | | 4/5/2005 | | DONE |
|
|
|
Meeting with architect, Brian to review revised plans showing modifiacations they want to FD access routes they showed on origianl approved plans. He only brought in one set and the propsed revisions are not acceptable. He'll revise and bring in two sets.
|
Plan resubmittals received | | | 4/5/2005 | | PASS |
|
|
|
approved two resubmitted two copies of revised sheet A1.1 showing revisions to originally approved FD access roadways. Called architect to pick up revised plans stamped by fire only. No resubmittal fees charged. Attempted to call architect but not available and voice mail available. Will call tomorrow to advise him to come pick up approved plans.
|
FIRE-Conference | 4/4/2005 | 4/4/2005 | 4/4/2005 | A | DONE |
Troy Cobbley
|
|
|
Contact: ###-####. Went over life safety comments with superintendant. Includes type of door hardware and fire dept access on the north side
|
BLD-Other | 3/9/2005 | 3/10/2005 | 3/10/2005 | A | NR |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/9/2005 at 3:06:03 PM. Contact: ###-####.
|
BLD-Energy code compliance | 2/14/2005 | 2/14/2005 | 2/14/2005 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 2/14/2005 at 8:27:39 AM. Contact: ###-####.
walls ok 2/14/2005 2:15:25 PM
|
BLD-Framing/Rough-in | 2/10/2005 | 2/11/2005 | 2/11/2005 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 2/10/2005 at 5:26:30 PM. Contact: ###-####. ok to start drywall 2/11/2005 10:26:42 AM
|
BLD-Framing/Rough-in | 1/19/2005 | 1/19/2005 | 1/19/2005 | A | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 1/19/2005 at 7:21:27 AM. Contact: ###-####.
need engineer to address bracing req's @ bldg front/soffit. Gave ok to apply 1/2" plywood on face of storefront.
1/19/2005 11:46:00 AM 1/19/2005 11:46:36 AM
|
BLD-Foundation | 12/2/2004 | 12/2/2004 | 12/2/2004 | P | PART |
Lane Manuel
|
|
|
Scheduled by a contractor via Hello! on 12/2/2004 at 8:37:48 AM. Contact: ###-####.
stemwalls and piers at columns ok.
MTI to provide special insp. 12/2/2004 12:25:11 PM
|
BLD-Footing | 11/24/2004 | 11/29/2004 | 11/29/2004 | A | PASS |
Tom Arcoraci
|
|
|
bob; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles pending mti reports 11/29/2004 9:09:38 AM
|
(F) Reprint permit | | | 11/22/2004 | | |
|
|
|
|
Permit Ready to Issue | | | 11/19/2004 | | DONE |
|
|
|
|
Telephone call | | | 11/19/2004 | | |
|
|
|
tlk to brian ###-#### - that is permit and fees are ready to picked up
|
Issue PAID IN FULL permit | | | 11/19/2004 | | DONE |
|
|
|
|
Routing - FIRE | 11/16/2004 | | 11/18/2004 | | PASS |
|
|
|
11/18/04 - Passed per telcon agreement by architect to make the modification to turning radius as "red" lined on plans. Review comments faxed to architect.
1/17/04 - One FD access roadway requires modifying the turning radius. Phoned architect, n/a; left message. Holding to discuss with architect tomorrow.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/18/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/18/2004 | | DONE |
|
|
|
|
Plan assigned to (MLO) | 10/6/2004 | | 11/18/2004 | | PASS |
|
|
|
11/18/2004 14:06:33 MLO - activity updated through activity BLDA022 from case BLD04-02345.
|
Plan resubmittals received | | | 11/17/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 2 Copys of Sheet A0.1 Taken to Mike Otto.
|
Routing Off Site - STRUCTURAL | 11/16/2004 | | 11/17/2004 | | PASS |
|
|
|
calculations faxed to engineer for review. MLO
|
Plan resubmittals received | | | 11/16/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 2 Copys of sheet A0.1 Taken to Mike Otto...
|
Plan resubmittals received | | | 11/16/2004 | | DONE |
|
|
|
Received sheet A0.1 taken to Mike Otto.Note: These sheets have a correction and are different than the sheets submitted earlier in the day. MLO
|
Routing - PLAN CHECK | 11/12/2004 | | 11/16/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 11/16/2004 | | DONE |
|
|
|
Received letter of transmittal two copies of additional structural calculations taken to Mike Otto.
|
Routing Off Site - STRUCTURAL | 11/8/2004 | | 11/15/2004 | | FAIL |
|
|
|
Contacted PDQ to take revised structural calcs and plans of 11-5-04 to outside engineering. kmm
|
Telephone call | | | 11/15/2004 | | DONE |
|
|
|
Phone call to architect regarding inconsistancies with the energy report and the plans. Architect is re doing energy design to match plans. MLO
|
Plan resubmittals received | | | 11/12/2004 | | DONE |
|
|
|
Received transmittal letter with 2 united water letters, 4 copies of sheet A1.1 taken to Mike O.
|
Plan resubmittals received | | | 11/10/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 2 Sets of A0.1,C-1,A1.0,A2.2,A4.0,A7.0,E2.0,E2.0F,E2.0L,E2.0P,E2.0S,E3.0,E3.1 Taken to Mike Otto..
|
Plan resubmittals received | | | 11/8/2004 | | DONE |
|
|
|
Received three copies of revised sheets S1.0,S1.1, S1.2, S2.0, S2.1, S3.0, S3.1, S4.0, S4.1, two copies of revised sheets, A2.0, A2.2, A3.0, A5.0, A8.0, A8.1. Three copies of plan review responses and revised calculations. Two copies of 11x 17 copies of Addendum #1 and Addendum #2. Routed to Mike Otto. kmm
|
1st review completed | | | 10/28/2004 | | FAIL |
|
|
|
failed structural, plan check and Fire.
|
Routing - PLAN CHECK | 10/28/2004 | | 10/28/2004 | | PEND |
|
|
|
waiting for resubs
|
Routing - FIRE | 10/26/2004 | | 10/28/2004 | | FAIL |
|
|
|
FD access, fire hydrant and fire flow issues have not been addressed from the failed Grading review under BLD04-02344. Review faxed to architect.
|
Routing Off Site - STRUCTURAL | 10/7/2004 | | 10/26/2004 | | FAIL |
|
|
|
corrections sent to architect
|
Routing - PLAN CHECK | 10/12/2004 | | 10/26/2004 | | FAIL |
|
|
|
corrections sent to architect
|
Plan resubmittals requested | | | 10/26/2004 | | DONE |
|
|
|
IBC corrections
|
Plan resubmittals received | | | 10/15/2004 | | DONE |
|
|
|
Received 4 Copys of sheet C-1, & 2 Sets of MS1.0,M1.0,M1.1,M1.2,M2.1,M3.1,M4.1,P1.1,P2.1 Taken to Mike Otto...
|
Routing - PLANNING | 10/11/2004 | | 10/12/2004 | | PASS |
|
|
|
Approve per DRH04-105.
|
Routing - PUBLIC WORKS | 10/7/2004 | | 10/11/2004 | | PASS |
|
|
|
|
Routing - Erosion and Sediment | 10/11/2004 | | 10/11/2004 | | PASS |
|
|
|
ESC plan approved with attached conditions.
|
Routing - PLUMBING | 10/11/2004 | | 10/11/2004 | | PASS |
|
|
|
per plans and 2003 upc
|
Plans ACCEPTED BY PLAN TECH | | | 10/7/2004 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 10/7/2004 | | |
|
|
|
|
Routing - PLANNING Land Div | 10/7/2004 | | 10/7/2004 | | PASS |
|
|
|
Lot 1, Block 1 of Lyle Pearson Subdivision.
|
Application received | | | 10/5/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/5/2004 | | DONE |
|
|
|
|
Fee Review-notes | 10/5/2004 | 10/5/2004 | | | |
|
|
|
|