Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberBLD04-02372
StatusFinaled
Name BOISE CITY HOUSING
Site Address 575 S 13TH ST
Project NameCommunity House - temp housing
Customer Number 
ePlanReviewNo
Description
TEMPORARY OCCUPANCY - A permit to install a 26 x 56 2016 sq. ft. modular building to be used as a dormatory for a maximum of 48 occupants for a period of time not to exceed 180 days from final approval. This permit includes the foundation, tie-downs, accessible ramp and stairs, new panic hardware on exit doors, new exit signs, emergency light, fire alarms and smoke detectors per approved plans and attachments, CZC04-00149. State of Idaho Tag # WA-IDI 0320CC. A Temporary Certificate of Occupancy for 180 days is to be issued on final approval. This temporary building has been approved in accordance with IBC Section 107.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (FNL)  3/12/2007 DONE
Case Summary (BLD)  9/9/2005 DONE
BLD-Final11/3/200411/4/200411/4/2004PPASS
DetailsBob Archibald
Bill- need sign off for ele & fir...Call before you go out; Phone #: ###-#### Internet Inspection Request from: Jan Rice. Corrections made ok.
FIRE-Final Inspection11/4/200411/4/200411/4/2004APASS
DetailsRick Jackson
Fire/life safety okay 11/4/2004 3:45:25 PM
DOC - Permit Finaled  11/4/2004 DONE
BLD-Other11/2/200411/2/200411/2/2004PPART
DetailsBob Archibald
Corrections being made.
BLD-Conference10/29/200410/29/200410/29/2004PPART
DetailsBob Archibald
CN issued identifying requirements for occupancy.
BLD-Conference10/20/200410/20/200410/20/2004PPART
DetailsBob Archibald
Conference with Bill on stairs located at south end of structure. Lowest riser on eastside and top riser on westside require identification as hazardous. Electrical utility drop to structure installed and approved by Jim Schmer. No other new construction in progress.
BLD-Other10/18/200410/18/200410/18/2004PPASS
DetailsBob Archibald
Remainder of tie downs verified. Stair and ramp construction in progress.
Permit Ready to Issue  10/18/2004 DONE
Issue & PRINT to be Invoiced  10/18/2004 DONE
BLD-Conference10/15/200410/15/200410/15/2004PPART
DetailsBob Archibald
Site visit and conference with contractors. Discussed scheduling and verified tie downs on west units, east unit to be left with access for verification. Ramp scheduled for completion on 10/19/04.
Telephone call  10/14/2004 DONE
Spoke with Mike Hopkins regarding the letter that is needed for impact fees to remind him that I still need this so that we can get this permit finished and picked up///10/14/04 8:30am BAS
Inspection Record Card- Bld  10/11/2004 DONE
Print Occupancy Form  10/11/2004 DONE
Routing - FIRE10/8/2004 10/8/2004 PASS
Routing - PLAN CHECK10/8/2004 10/8/2004 PASS
per plan and field verification
Routing - PLANNING10/8/2004 10/8/2004 PASS
approved by Hal Simmons
PLANS/APPL TAKEN TO FRONT DESK  10/8/2004 DONE
1st review completed  10/8/2004  
Application received  10/7/2004  
Plans ACCEPTED BY PLAN TECH  10/7/2004  
Plans have been taken to Mike Otto for him to route...
Fee Review-notes10/7/200410/7/2004