Letter of compliance | | | 12/21/2005 | | DONE |
|
|
|
Letter of Compliance issued 12-21-05.
|
BLD-Final | 12/20/2005 | 12/20/2005 | 12/20/2005 | P | PART |
Jim Storey
|
|
|
nick bateman; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa ok for l/c pending mech sign off of permit for gas/hydronics
|
FIRE-Final Inspection | 12/19/2005 | 12/20/2005 | 12/20/2005 | P | PASS |
Forrest France
|
|
|
Fire life safety is acceptable, door hardware at some locations is not installed at this time-hardware is on site and verified for approval, to be installed prior to structural final for verification.
|
BLD-Final | 12/15/2005 | 12/16/2005 | 12/16/2005 | P | NR |
Jim Storey
|
|
|
nick; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
|
FIRE-Final Inspection | 12/15/2005 | 12/16/2005 | 12/16/2005 | A | NR |
Forrest France
|
|
|
Associated fire alarm permit must be finaled prior to life safety final.
|
FIRE-Final Inspection | 12/13/2005 | 12/14/2005 | 12/14/2005 | P | NR |
Forrest France
|
|
|
Fire alarm and fire sprinkler must be inspected and approved prior to life safety final.
|
Code Occupancy Approval | 10/26/2005 | 10/26/2005 | 10/26/2005 | P | PASS |
Wm. Michael Meloy
|
|
|
Compliance Met.
|
BLD-Aging Inspection | 9/26/2005 | 9/26/2005 | 9/26/2005 | | PASS |
Jim Storey
|
|
|
ti work in progess.
|
FIRE-Conference | 7/27/2005 | 7/27/2005 | 7/27/2005 | P | DONE |
Forrest France
|
|
|
On site discussion with Nick the general contractor regarding fire department lane and street access requirements.
|
BLD-Framing/Rough-in | 6/15/2005 | 6/15/2005 | 6/15/2005 | P | PASS |
Jim Storey
|
|
|
fr on the roof- nick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie roof wall framing and sheer atchment ok
|
BLD-Framing/Rough-in | 6/8/2005 | 6/8/2005 | 6/8/2005 | P | PASS |
Jim Storey
|
|
|
nick; Phone #: ###-#### Internet Inspection Request from: Letitia Mesa exterior framing ok.
|
Case Summary (BLD) | | | 6/3/2005 | | |
|
|
|
|
BLD-Other | 5/23/2005 | 5/23/2005 | 5/23/2005 | P | PASS |
Jim Storey
|
|
|
roof ok /walls ext. east end ok
|
BLD-Framing/Rough-in | 5/19/2005 | 5/23/2005 | 5/23/2005 | A | NR |
Jim Storey
|
|
|
nick; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles
|
BLD-Concrete | 4/26/2005 | 4/27/2005 | 4/27/2005 | P | PASS |
Jim Storey
|
|
|
nick; Phone #: ###-#### Internet Inspection Request from: Barbara Moore thidr floor deck ok
|
BLD-Other | 3/10/2005 | 3/10/2005 | 3/10/2005 | P | PASS |
Jim Storey
|
|
|
cmu cinder block re-bar//nick; Phone #: ###-#### Internet Inspection Request from: Barbara Moore reviewed special insp. reports to date/ spoke with insp. will top out next week. 3/10/2005 4:29:23 PM
|
BLD-Foundation | 2/14/2005 | 2/14/2005 | 2/14/2005 | P | PART |
Dave Hannah
|
|
|
Nick; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
BLD-Foundation | 2/1/2005 | 2/1/2005 | 2/1/2005 | P | PART |
Tom Arcoraci
|
|
|
nick; Phone #: ###-#### Internet Inspection Request from: Barbara Moore wip ok 2/1/2005 1:59:42 PM
|
BLD-Footing | 1/28/2005 | 1/31/2005 | 1/31/2005 | A | PART |
Jim Storey
|
|
|
Nick; Phone #: ###-#### Internet Inspection Request from: Jan Rice north center tower ft cage ok verts to be insp by si. 1/31/2005 10:20:13 AM
|
BLD-Foundation | 1/24/2005 | 1/25/2005 | 1/25/2005 | A | PART |
Dave Hannah
|
|
|
Rebar insp.; Phone #: ###-#### Internet Inspection Request from: Jan Rice
|
BLD-Footing | 1/20/2005 | 1/21/2005 | 1/21/2005 | A | PART |
Jim Storey
|
|
|
Nick; Phone #: ###-#### Internet Inspection Request from: Jan Rice si to verrify 5c step ft hook bar spacing to per plan in report, 1/21/2005 11:52:48 AM
|
FIRE-Final Inspection | 1/20/2005 | 1/21/2005 | 1/21/2005 | A | CANC |
Rick Jackson
|
|
|
Jim; Phone #: ###-#### Internet Inspection Request from: Jan Rice Wrong permit number called in 1/21/2005 9:52:13 AM
|
BLD-Footing | 1/19/2005 | 1/19/2005 | 1/19/2005 | P | PART |
Jim Storey
|
|
|
nick; Phone #: ###-#### Internet Inspection Request from: Marsha Smylie 5.3 grid line around elavator si pending bar ok 1/19/2005 11:57:40 AM
|
BLD-Footing | 1/12/2005 | 1/13/2005 | 1/13/2005 | A | PART |
Jim Storey
|
|
|
nick; Phone #: ###-#### Internet Inspection Request from: Jan Rice si 1/13/2005 10:10:22 AM
|
BLD-Foundation | 1/12/2005 | 1/13/2005 | 1/13/2005 | A | PART |
Jim Storey
|
|
|
nick; Phone #: ###-#### Internet Inspection Request from: Jan Rice si 1/13/2005 10:10:28 AM
|
(F) Reprint permit | | | 12/15/2004 | | |
|
|
|
|
Issue & PRINT permit | | | 12/14/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/3/2007 | | 12/7/2004 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/7/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/7/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/7/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/7/2004 | | DONE |
|
|
|
talked to trent koci at ###-#### that permit is ready & need a.c.h.d.
|
Plan assigned to (M_P) | 10/27/2004 | | 12/7/2004 | | PASS |
|
|
|
12/7/2004 09:22:53 M_P - activity updated through activity BLDA022 from case BLD04-02409.
|
Routing - PLANNING | 12/3/2004 | | 12/3/2004 | | PASS |
|
|
|
Resubmitted Plans comply with CUP04-63. Kgallagher
DRH previously approved per TWilson.
|
Routing - PLANNING | 11/30/2004 | | 12/2/2004 | | FAIL |
|
|
|
Failed - resubmittals were not included.
|
Plan resubmittals received | | | 12/2/2004 | | DONE |
|
|
|
Received two copies of revised sheets C-2.0 and LS-1. Routed to Karen G. kmm
|
Routing - PUBLIC WORKS | 11/22/2004 | | 11/30/2004 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/30/2004 | | 11/30/2004 | | |
|
|
|
Route to Planning.
|
Routing - PLAN CHECK | 11/19/2004 | | 11/22/2004 | | |
|
|
|
Routing to P.W.
|
Routing - PLAN CHECK | 11/12/2004 | | 11/19/2004 | | PEND |
|
|
|
Review accessible entrance to this building when new site plans arrive because of raising the building because of flood plane issues.
Waiting for others to approve prior to issuing permit.
|
Routing - PLANNING | 11/8/2004 | | 11/12/2004 | | FAIL |
|
|
|
Failed per Conditional Use: need Drainage Dist #3, BPR (including tree pruning notes), and ACHD License Agreement. Approved 11/8/04 by Tempra Wilson per DRH04-118.
|
Plan resubmittals received | | | 11/8/2004 | | DONE |
|
|
|
Received two copies of revised sheets A-1.1, A-1.2, A-1.3, A-2, A-5.1, A-5.2, A-5.3, A-5.4, A-6.1, A-6.2, A-7.1 and one copy of response letter. Routed to Mike P. kmm
|
Routing - PLAN CHECK | 11/5/2004 | | 11/8/2004 | | |
|
|
|
Routing to Planning
|
Routing - PUBLIC WORKS | 11/5/2004 | | 11/5/2004 | | FAIL |
|
|
|
Nees elevation certificate documenting compliance with floodplain ordinance. Contact Jim Wyllie at ###-####
|
1st review completed | | | 11/5/2004 | | FAIL |
|
|
|
failed Planning, plan check, structural, and public works.
|
Routing - PLAN CHECK | 11/5/2004 | | 11/5/2004 | | |
|
|
|
Routing to P.W.
|
Routing - FIRE | 11/1/2004 | | 11/5/2004 | | PASS |
|
|
|
|
Plan resubmittals received | | | 11/2/2004 | | DONE |
|
|
|
Received two copies of revised sheets C1.0, C2.0, C3.0, C.4.0, C.5.0, C.5.1, C.6.0, SD-1, LS-1. Routed to Mike P. kmm
|
Routing - PLAN CHECK | 10/27/2004 | | 11/1/2004 | | FAIL |
|
|
|
Plan review completed, sent correction report to architect, requesting additional information be submitted for further review prior to issuing permit.
|
Plan Reviewer's activity | | | 11/1/2004 | | |
|
|
|
Structural review completed by plan reviewer. No further review required for structural comments.
|
Routing - PARKS DEPARTME | 10/27/2004 | | 10/27/2004 | | PASS |
|
|
|
Plans approved by Cheyne Weston as noted on the plans and per letter of 10/26/04 to Bill Strite (attached to plan sets).
|
Routing - PLANNING | 10/22/2004 | | 10/27/2004 | | FAIL |
|
|
|
Failed due to non-compliance with conditions of approval for CUP04-63 (Karen Gallagher) and DRH04-00118 (Tempra Wilson).
|
Plan assigned to (JCM) | 10/13/2004 | | 10/27/2004 | | DONE |
|
|
|
Because of work load this project was reassigned to Mike Phillips. JCM
|
Plan resubmittals received | | | 10/26/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 3 Copys of sheets S5.1,S1.1,S2.1,S2.2,S2.3 & 1 EXTRA SHEET OF S5.1 Taken to John Menard......
|
Routing - PLUMBING | 10/21/2004 | | 10/22/2004 | | PASS |
|
|
|
upproved per plan and 2003 UPC
|
Routing - Erosion and Sediment | 10/20/2004 | | 10/21/2004 | | PASS |
|
|
|
ESC approved under former ESC permit, #04-01378.
|
Routing Off Site - STRUCTURAL | 10/18/2004 | | 10/20/2004 | | FAIL |
|
|
|
Contacted PDQ for outside delivery. - Received faxed comment list from the consulting structural engineer requesting revisions. JCM
|
Plan resubmittals requested | | | 10/20/2004 | | |
|
|
|
Faxed the architect a copy of the comment list from the consulting structural engineer requesting revisions. JCM
|
Routing - PUBLIC WORKS | 10/18/2004 | | 10/20/2004 | | FAIL |
|
|
|
Requires separate sewer plans and requires DEQ approval. Contact Jim Pardy at ###-####
|
Routing - PLANNING Land Div | 10/13/2004 | | 10/18/2004 | | PASS |
|
|
|
Approved. Block 9 of Boise City Park Subdivision. Alleys have been vacated by ACHD.
|
Plans ACCEPTED BY PLAN TECH | | | 10/13/2004 | | DONE |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 10/13/2004 | | DONE |
|
|
|
|
Application received | | | 10/12/2004 | | |
|
|
|
|