Permit Information
Permit NumberBLD04-02416
StatusFinaled
Name MCALVAIN CONSTRUCTION
Site Address 4497 N TORRIDON WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 3129 sq. ft. two story single family dwelling with a 898 sq. ft. attached three car garage, a 198 sq. ft. covered entry porch, a 303 sq. ft. wood deck and concrete patio at rear of structure per approved plans, all engineering and attached condition list. This lot is within a hillside area and is subject to the hillside ordinance. Class "A" roof system and 30 ft. defensible space shall be maintained. (1st floor 1927 sq. ft.)(2nd floor 1202 sq. ft.) PC #695 DJO
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/30/20056/30/20056/30/2005APASS
DetailsTony Young
Scheduled by a contractor via Hello! on 6/30/2005 at 5:26:01 AM. Contact: ###-####.
c of o issued
BLD-Final6/28/20056/29/20056/30/2005PCANC
DetailsTony Young
john; Phone #: ###-#### Internet Inspection Request from: Barbara Moore
BLD-Grading Inspection6/30/20056/30/20056/30/2005 DONE
Final grading and drainage approved.
DOC - Permit Finaled6/30/20056/30/20056/30/2005PPASS
DetailsTony Young
BLD-Wall cover4/7/20054/8/20054/8/2005PPASS
DetailsTroy James
Scheduled by a contractor via Hello! on 4/7/2005 at 12:35:17 PM. Contact: ###-####.
BLD-Framing/Rough-in4/5/20054/6/20054/6/2005PFAIL
DetailsTroy James
Scheduled by a contractor via Hello! on 4/5/2005 at 9:22:52 AM. Contact: ###-####.draftstopping mech. chase and triange dead space second level, strap top plates at master bedroom and open area at first and second level 4/6/2005 12:23:24 PM
BLD-Framing/Rough-in4/5/20054/6/20054/6/2005APASS
DetailsTroy James
shear inspection
BLD-Footing1/18/20051/18/20051/18/2005PPART
DetailsTroy James
Scheduled by a contractor via Hello! on 1/18/2005 at 8:03:58 AM. Contact: ###-####. rebar in place, wip 1/18/2005 2:37:53 PM
BLD-Footing1/13/20051/13/20051/13/2005PPART
DetailsTroy James
Scheduled by a contractor via Hello! on 1/13/2005 at 7:09:18 AM. set backs ok 1/13/2005 2:48:53 PM
BLD-Grading Inspection1/12/20051/12/20051/12/2005 DONE
footing subgrade approved by the geotechnical engineer
PubWorks Subgrade Approval11/9/200411/9/20041/12/2005 DONE
A letter from the applicants geotechnical engineer indicating that the footing subgrade is acceptable must be approved by Public Works prior to scheduling the footing inspection. Call Terry Records at ###-####.
Override - Activity Holds  1/4/2005  
Issue PAID IN FULL permit  1/4/2005 DONE
Override - Activity Holds  1/3/2005  
Permit Ready to Issue  1/3/2005  
Override - Activity Holds  1/3/2005  
Inspection Record Card- Bld  1/3/2005 DONE
Print Occupancy Form  1/3/2005 DONE
Telephone call  1/3/2005 DONE
Spoke with Gary and told him that permit is ready & fees///1/3/05 8:30am BAS
Plan assigned to (DJO)12/20/200412/20/200412/30/2004 PASS
12/30/2004 10:17:45 DJO - activity updated through activity BLDA022 from case BLD04-02416.
Routing - Erosion and Sediment12/30/2004 12/30/2004 PASS
ESC plan approved with attached conditions.
Plans ACCEPTED BY PLAN CHECK  12/30/2004 DONE
PLANS/APPL TAKEN TO FRONT DESK  12/30/2004 DONE
Routing - Erosion and Sediment12/27/2004 12/27/2004 FAIL
No rp listed and contractor has been identified. Discussed with plan designer.
Plans ACCEPTED BY PLAN CHECK  12/20/2004  
Case Summary (BLD)  12/20/2004  
Plan Review Report  12/20/2004  
Plan Reviewer's activity  12/20/2004  
will issue when ERS is approved.
Routing - PUBLIC WORKS GRADING12/20/2004 12/20/2004 PASS
plans routed back to ESC. failed on 12/16/2004
Routing - Erosion and Sediment12/20/2004 12/20/2004 FAIL
plans routed back to ESC. failed on 12/16/2004 by 420.
Pending Assignment by DJO10/13/2004 12/20/2004 FAIL
12/20/2004 11:18:11 DJO - activity updated through activity BLDA169 from case BLD04-02416.
Routing - Erosion and Sediment12/16/2004 12/16/2004 FAIL
Only one copy of plan submitted, no rp on application. Notified PD.
Routing - FIRE12/16/2004 12/16/2004 PASS
No fire sprinklers required (Highlands Hackberry # 4 sub.)
Routing - PLANNING12/15/2004 12/16/2004 PASS
Site plan is approved as redlined. Driveway must provide turn-around approx. as shown on architectural site plan. Plans routed back to Public Works (Terry Records) for approval of revised grading. Will call applicant to request a reduced site plan for records. CER
Routing - PUBLIC WORKS GRADING12/16/2004 12/16/2004 PASS
Revised grading approved 12/16/04. Planning required revised site plan, floor plans, and elevations. This required revisions to grading plan. Plans routed back to T. Records for approval. CER
Routing - PLANNING12/14/2004 12/14/2004 FAIL
Received new site/grading plans. Informed applicant that new floor plans, elevations, etc. would be required as the layout is changing.
Routing - PLANNING11/9/2004 11/10/2004 FAIL
House encroaches into 10' setbacks on both sides, and does not provide on-site turn-around as required on plat. Spoke w/ applicant at 8:00 a.m. CER
Routing - PUBLIC WORKS11/9/2004 11/9/2004 PASS
Routing - PUBLIC WORKS GRADING11/9/2004 11/9/2004 PASS
Approved as Category 3.
Routing - PUBLIC WORKS GRADING10/19/2004 10/20/2004 FAIL
No geotechnical report was submitted
Routing - PUBLIC WORKS10/13/2004 10/19/2004 PASS
Application received  10/13/2004  
Routing - PLAN CHECK12/16/2004    
Dan O.
Routing - PLAN CHECK12/30/2004