BLD-Final | 12/1/2004 | 12/2/2004 | 12/2/2004 | A | PASS |
Dave Hannah
|
|
|
Bill; Phone #: ###-#### Internet Inspection Request from: Jan Rice ok for perm occ 12/2/2004 11:08:54 AM
|
FIRE-Final Inspection | 12/1/2004 | 12/1/2004 | 12/1/2004 | P | PASS |
Rick Jackson
|
|
|
Bill; Phone #: ###-#### Internet Inspection Request from: Jan Rice The door at the second exit from the mezzanine that leads to lobby was removed instead of changing the swing to the path of egress - called Carl W. (PDS plan review) and he has approved this change; fire/life safety final okay 12/1/2004 3:33:43 PM
|
FIRE-Final Inspection | 11/22/2004 | 11/23/2004 | 11/23/2004 | A | NR |
Rick Jackson
|
|
|
Bill; Phone #: ###-#### Internet Inspection Request from: Jan Rice Bill never called as agreed to when he was ready for final 11/23/2004 5:08:09 PM
|
BLD-Final | 11/19/2004 | 11/22/2004 | 11/22/2004 | A | FAIL |
Rick Jackson
|
|
|
Bill; Phone #: ###-#### Internet Inspection Request from: Cheryl Baumgartner No fire alarm plans were needed as walls did not cause any coverage problems; door at bottom of stair not swinging in direction of travel per plans 11/22/2004 2:13:42 PM
|
FIRE-Conference | 10/27/2004 | 10/27/2004 | 10/27/2004 | P | PART |
Rick Jackson
|
|
|
bill ; Phone #: ###-#### Internet Inspection Request from: Linda Hartwell Met with Bill about needing fire alarm permit as a new strobe will be needed due to wall additions and the need for the door swing change at bottom of stairs 10/27/2004 2:16:31 PM
|
Plan assigned to (CJW) | 10/14/2004 | | 10/22/2004 | | PASS |
|
|
|
10/22/2004 09:31:07 CJW - activity updated through activity BLDA022 from case BLD04-02423.
|
Routing - FIRE | 10/20/2004 | | 10/22/2004 | | PASS |
|
|
|
|
1st review completed | | | 10/22/2004 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/22/2004 | | 10/22/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/22/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/22/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/22/2004 | | |
|
|
|
|
Telephone call | | | 10/22/2004 | | DONE |
|
|
|
talked to andrea ###-#### is ready
|
Issue PAID IN FULL permit | | | 10/22/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/15/2004 | | 10/20/2004 | | PASS |
|
|
|
IBC plan review started October 19, 2004 and was finished the next day. The drawings were approved with clarifications. See the plan review report.
|
Routing - PUBLIC WORKS | 10/14/2004 | | 10/15/2004 | | PASS |
|
|
|
|
Routing - PLUMBING | 10/15/2004 | | 10/15/2004 | | PASS |
|
|
|
approved for removal, capping and relocation of one sink to new wall per floor plan and 2003 UPC. no plumbing plan
|
Plans ACCEPTED BY PLAN TECH | | | 10/14/2004 | | DONE |
|
|
|
Ok per Carl Westfall. kmm
|
Application received | | | 10/13/2004 | | |
|
|
|
|