FIRE-Final Inspection | 3/14/2005 | 3/14/2005 | 3/14/2005 | A | PASS |
Troy Cobbley
|
|
|
Inspection done by Sam Rogers. Fire life safety finaled.
|
Meeting | | | 3/14/2005 | | PASS |
|
|
|
Final UL field evaluation report received approving the fireplace combustion system, subject to a few items required to be field verified by the Fire Inspector; all those UL items were satisfactorily verified at a special inspection done by Sam Rogers on 3/11/2005. Per telcon 3/14/2005 with Steve Bastian, Mech Engr, the variable speed fan control shall be set at the maximum speed unless an air balance test is done to verify a lower speed setting will achieve the required 1500 cfm exhaust and the knob removed and a label attached indicating required speed setting. Per discussion with Karen Bubb, Airport art commission, she will verify the fan is set at maximum speed and attach a label by the switch indicating that the fan speed is to be maintained at the maximum speed setting. Per telcon with structural inspector, Jim Story, no further inspections are necessary. Permit is now ready to be "finaled" and a certificate of completion issued.
|
Letter of compliance | | | 3/14/2005 | | DONE |
|
|
|
Letter of Compliance issued 3-14-05
|
Meeting | | | 3/14/2005 | | |
|
|
|
|
Meeting | | | 1/12/2005 | | DONE |
|
|
|
Met with UL rep, Mr Ko and Josh Olsen (arts commission) at airport on 1/11 & 1/12 during UL testing of fireplace unit. Testing was concluded on 1/12 by UL leaving a list of mandatory corrections to be made to the burner system. Mr. Ko expects to have UL return in two weeks to re-inspect the modifications and conduct additional tests. It was made clear to Mr. Ko that the burner unit is NOT to be lighted until the UL rep returns and is present for the re-lighting. If UL indicates any stipulation on depth of the glass bed or other operating conditions, these shall be included in the operations manual. An operating and maintenance manual shall be provided by Mr. Ko which shall incorporate the burner manufacturer's instructions, as well as any stipulations made in the approval by the UL rep.
|
FIRE-Alarm Testing | 12/9/2004 | 12/10/2004 | 12/10/2004 | A | PART |
Rick Jackson
|
|
|
lawrence Note: Also fire sprinker & also please call 1/2 hr prior to inspections; Phone #: ###-#### Internet Inspection Request from: Cathy Chiles Will need the unit UL listed as a system before using 12/10/2004 11:53:43 AM
|
BLD-Framing/Rough-in | 12/9/2004 | 12/9/2004 | 12/9/2004 | P | PASS |
Jim Storey
|
|
|
Lawrence; Phone #: ###-#### Internet Inspection Request from: Jan Rice floor supports and encloser per plan. 12/9/2004 4:06:43 PM
|
Plan assigned to (CJW) | 11/3/2004 | | 12/7/2004 | | PASS |
|
|
|
12/7/2004 08:08:29 CJW - activity updated through activity BLDA022 from case BLD04-02548.
|
Routing - PLAN CHECK | 12/6/2004 | | 12/7/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/7/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/7/2004 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/7/2004 | | DONE |
|
|
|
|
Telephone call | | | 12/7/2004 | | DONE |
|
|
|
left mess for lawrence ko at ###-#### that permit is ready
|
Issue PAID IN FULL permit | | | 12/7/2004 | | DONE |
|
|
|
|
Routing - FIRE | 12/3/2004 | | 12/6/2004 | | PASS |
|
|
|
Resubmittal approved subject to UL Field Evaluated Product Mark. Review faxed to architect.
|
Plan resubmittals received | | | 12/3/2004 | | DONE |
|
|
|
Received one copy of revised sheet SH-F1, SH-F7, SH-F6. Routed to Carl W.
|
Routing - PLAN CHECK | 11/12/2004 | | 12/3/2004 | | PASS |
|
|
|
Drawings approved, with clarifications after the resubmittal review.
|
Plan resubmittals received | | | 12/2/2004 | | DONE |
|
|
|
Received one copy of revised sheet SH-F1, SH-F7, SH-F6. Routed to Carl W. kmm
|
Telephone call | | | 11/18/2004 | | DONE |
|
|
|
telcon from ME, Steve Bastian, Elkhorn Engr's; explained nature of our concern and requirement for PE stamp on the entire system design. He will provide the stamped plans. He also said the installation is essentially complete and availbale to see if I wanted to do an onsite review; I declined the offer.
|
Routing - FIRE | 11/8/2004 | | 11/12/2004 | | FAIL |
|
|
|
Discussed with Dave Miller. Need PE stamp on plans due to special design and A occupancy exposure to open flame. Discussed with architect and faxed review comments to architect.
|
Plan resubmittals received | | | 11/12/2004 | | DONE |
|
|
|
Received transmittal letter, response letter, load calculations, two sets of sheets SH-F2,SH-F5 taken to Carl W.
|
1st review completed | | | 11/12/2004 | | FAIL |
|
|
|
failed Plan Check and Fire.
|
Routing - PLAN CHECK | 11/3/2004 | | 11/8/2004 | | FAIL |
|
|
|
Failed 1st IBC plan review. The IBC plan review was started on November 5, 2004 and was finished on November 8, 2004. A response from the Architect was required. See the plan review report.
|
Application received | | | 10/28/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/28/2004 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/28/2004 | | DONE |
|
|
|
Certificate of Value sheet has not been filled out on the Mechanical value, I spoke with Karen Bubb and was told that Lawrence Ko has been over this with Carl Westfall . From what I understand the project at this time will need a Mechanical Permit as the Flue,exhaust ect... will need to be inspected .
|
Fee Review-notes | 10/28/2004 | 10/28/2004 | | | |
|
|
|
|