Third Notice BLD | 12/7/2005 | 12/7/2005 | 12/14/2005 | | DONE |
|
|
|
Second Notice has not been responded to.///Signed off 2004 permit per Jenifer & Rita
|
Second Notice | | 7/13/2005 | 12/7/2005 | | DONE |
|
|
|
|
First Notice | | 6/6/2005 | 7/13/2005 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/6/2005 | | DONE |
|
|
|
Perm. Occ. Cert. # 10623 issued 6-6-05 to The Phix.
|
BLD-Final | 6/2/2005 | 6/3/2005 | 6/3/2005 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 6/2/2005 at 5:07:58 PM. Contact: ###-####.final ok card on site.
|
Permanent Occupancy | | 6/3/2005 | 6/3/2005 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/10/2005 | 5/10/2005 | 5/10/2005 | P | PASS |
Troy Cobbley
|
|
|
Fire life safety finaled
|
FIRE-Final Inspection | 4/29/2005 | 4/29/2005 | 4/29/2005 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Dave Lokkers permission until the interconnect between the spraying equipment and the fan has been completed. Owner was going to mount the signs after I left. Will verify when I return.
|
Issue PAID IN FULL permit | | | 11/29/2004 | | DONE |
|
|
|
|
Telephone call | | | 11/26/2004 | | DONE |
|
|
|
tlk to Tony Ritacco -###-#### that his permit is ready to be picked and fee
|
Telephone call | | | 11/26/2004 | | |
|
|
|
also left ms for cindy ###-#### that permit and fees are ready to be pickedup
|
Inspection Record Card- Bld | | | 11/24/2004 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/24/2004 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/24/2004 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/23/2004 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/17/2004 | | 11/23/2004 | | PASS |
|
|
|
Drawings approved after resubmittal review.
|
Plan assigned to (CJW) | 11/3/2004 | | 11/23/2004 | | PASS |
|
|
|
11/23/2004 13:03:58 CJW - activity updated through activity BLDA022 from case BLD04-02558.
|
Telephone call | | | 11/22/2004 | | DONE |
|
|
|
Talked to Cindy the architect's representative. Asked for documentation from the paint booth manufacturer that would allow the exhaust duct to be transistioned from a round duct to a rectangular duct to fit through the trusses. Said she would provide.
|
Plan resubmittals received | | | 11/18/2004 | | DONE |
|
|
|
Received Transmittal Letter, & 2 Copys of sheet A-1 Taken to Carl Westfall...
|
1st review completed | | | 11/17/2004 | | FAIL |
|
|
|
failed plan check
|
Routing - FIRE | 11/10/2004 | | 11/17/2004 | | PASS |
|
|
|
Passed with conditions. Review faxed to archtiect.
|
Routing - PLAN CHECK | 11/8/2004 | | 11/10/2004 | | |
|
|
|
Failed 1st IBC plan review. The IBC plan review was started November 9, 2004 and was finished the next day. A response from the Architect was required. See the plan review report.
|
Telephone call | | | 11/9/2004 | | DONE |
|
|
|
Dave Miller approved the dry chem protection for the spray booth, in light of limited quantities in storage and use. I advised Don of Superior Fire of the decision and he will bring down an application for a permit to install the dry chem system. Also advised him of need to get a FA permit to connect the discharge alarm to the FAC panel, similar to how a cooking hood system is monitored.
|
Routing - PUBLIC WORKS | 11/3/2004 | | 11/8/2004 | | PASS |
|
|
|
|
Meeting | | | 11/4/2004 | | DONE |
|
|
|
Don, with Superior Fire walked in plans for a dry chem system for the spray booth at this address. After finding this TI permit, I advised him the booth will require AS protection; dry chem will not be acceptable as an alternative agent (IFC 904.2.) unless approved by FM. I also called architect, Peter Rockwell and advised him. Immediately afrterward, recieved telcon form owner, tony Ritaco. I advised him of the requirement and referred him to Dave Miller to discuss a request for alternate agent approval. He will only have < 10 galllons and wants to minimize environmental clean-up costs associated with sprinler discharge on Haz Mat's.
|
Plans ACCEPTED BY PLAN TECH | | | 11/1/2004 | | |
|
|
|
|
Application received | | | 10/29/2004 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/29/2004 | | |
|
|
|
|
Fee Review-notes | 10/29/2004 | 10/29/2004 | | | |
|
|
|
|